DATE Shop Drawing Submission Summary Log

26.03.2018 Submission To CEG- FF & FAS


31.03.2018 Revise & Resubmit - from CEG - FFS
03.04.2018 FFS - CEG Commnets Complied & Resubmitted for approval
03.04.2018 FFS- Revise & Resubmit- From CEG
04.04.2018 FFS- CEG Comments Complied & Resubmitted for approval
04.04.2018 FAS- CEG Comments Complied & Resubmitted for approval
07.04.2018 Approved as noted- from CEG- FFS
08.04.2018 Revise & Resubmit - from CEG - FAS
09.04.2018 Pre-submission Meeting with QP - Revise & Resubmit
16.04.2018 received QP Drawing from GDI to Comply QP Comments
16.04.2018 Approved as noted- from CEG- FAS
18.04.2018 Hydraulic Calcualtion - Submitted to CEG, CEG Commented to revise drawings and submit
19.04.2018 FFS - CEG Comments Complied & Resubmitted for approval
19.04.2018 Approved as noted- From CEG- FFS
19.04.2018 GDI Requested to Submit technical submission summary
21.04.2018 Technical Submission summary Submitted to CEG office
23.04.2018 QP Pre-submission Meeting- Requested for additional calculation - AIG agreed to submit it to CEG by 25.04.2018- 1Pm
25.04.2018 Revised Calcualtion submitted to CEG, CEG Requested for Some changes
26.04.2018 CEG Comments Complied and submiited - CEG AAN
28.04.2018 CEG design team reviewed the calcualtion- Awating Reply
30.04.2018 Submitted Calculation + DWG to GDI for QP Submission- PROJECT PUT ON HOLD - unitl further approvals