24 March 2004
Background
Effective Date
Policy
4. The 2004 Edition of the General Conditions of Contract for Term Contracts
for Building Works as well as the new Articles of Agreement annexed thereto are now
put into use. They are now available for download in ETWB’s website under the
Publications page. Hard copies are being printed and will be available for sale in the
Government Publications Centre shortly. Works departments may continue with the
5. Clause 2 of the 2004 Edition provides that the Employer may impose
constraints on the powers of the Maintenance Surveyor. According to existing policy,
the Maintenance Surveyor shall obtain the agreement of the Employer before ordering
variation or otherwise committing the Government to additional expenditure under the
Contract, other than in respect of claims, in excess of $300,000. The Maintenance
Surveyor may subject to any prior contrary instructions given by the Employer to the
Maintenance Surveyor, order variation in accordance with the provisions of the Contract
or otherwise commit the Employer to additional expenditure under the Contract other
than in respect of claims if the value of such order or commitment is estimated not to
exceed $300,000. The works departments shall set out the foregoing in the Appendix
to the Form of Tender. A sample is given at Appendix A.
7. The heads of departments may delegate their authority to other officers who
may perform the functions of the Employer in each situation provided that the levels of
delegation are not inconsistent with the prevailing regulations. The above constraints
on the power of the Maintenance Surveyor also apply to in-house Maintenance
Surveyor.
( C S Wai )
Deputy Secretary for the Environment,
Transport and Works (Works) 2
NOTES TO TENDERERS
(a) refer the details of every variation to the Works, including the
reasons for the variation and its estimated value, to the Employer
for information as soon as the variation is ordered;
(b) refer the details of the evaluation to the Employer for information
as soon as the value of a variation to the Works has been
determined;
(c) report to the Employer all claims for additional payment made by
the Contractor and, except for those solely in respect of agreement
of rates, refer the principles underlying his assessment of each
claim, to enable the Employer to provide his view of the matter
before the Maintenance Surveyor reaches a decision; and
(d) report to the Employer all delays to the progress of any Works and,
except for those delays solely in respect of inclement weather
conditions or the hoisting of storm signals, refer his assessment of
grant of extension of time for completion, if any, to enable the
Employer to provide his view of the matter before the
Maintenance Surveyor reaches a decision.