BHEL/JHA 04
NPCIL Date: 13/08/2013
TGPP for KAPP (3&4) Rev No: 00
PS-WR
Erection
Of
Temporary Sheds
Bharat Heavy Electricals Limited Doc No. BHEL/JHA 04
NPCIL Date: 13/08/2013
TGPP for KAPP (3&4) Rev No: 00
PS-WR
DATE:
PREPARED BY:
REVIEWED BY:
APPROVED BY:
2. Maintaining the
steps /ramp free of loose
material etc.
4. Construction and a) Crane failure 1. Ensure the crane and load Site engineer
erection of truss. lifting appliances are load
tested and certified by a
competent person and
available with valid
documents.
2. Ensure that the max safe
load of the crane is more
than the weight of the load to
be lifted.
3. Ensure there is no person
under the crane.
c) Hitting of sling
wire/D shackles 1. Intense care should be
to the body parts maintained while releasing.
of workers, while 2.Ensure proper clearance
releasing from the sling while releasing
6(B) Lifting of roof Fall of sheet while 1. Ensure suitable capacity Site engineer
sheet and fixing lifting and placing crane, wire rope are used and
their proper usage.
3 Whether the workmen are screened & fit for the job YES NO
Whether the crane and other lifting tool and tackles are load tested by
4 YES NO
competent person.
Whether the Safe working load of the crane and tools and tackles is
5 YES NO
more than the weight of the load to be lifted.
5 Whether regular inspection is carried out for tools & tackles. YES NO
Whether the personnel movement cleared during the time of
6 YES NO
unloading and loading to the respective places.
7 Whether the signal man is available. YES NO
10 Whether the tag line provided to control the movement of lifting loads. YES NO
11 Ensure Height work permit is taken for work above 2.5m. YES NO
Checked by Authorized by
Signature : ______________ _____________
Name : ______________ _____________