Clause-by-clause comparison

CDM 2015 v CDM 2007

Designer Duties

MPW R&R Limited


Risk & Regulatory Solutions
Contents

About the Author 2

Introduction 3
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

Regulation 2 – Definitions 4

Regulation 8 – General Duties 5

Regulation 9 – Duties of Designers 8

Regulation 10 – Designs prepared or modified outside Great Britain 11

Document History
Version 1.0 20 February 2015 – Prior to CDM 2015 coming into force
Version 2.0 8 June 2015 – After CDM 2015 came into force

MPW R&R has made every effort to ensure that the information contained within this document is accurate. Its content should be used as guidance only and
not as a replacement for current regulations, existing standards or as a substitute for legal advice and is presented without any warranty, either express or
implied, as to its accuracy. In no event will MPW R&R be liable for any damages arising from reliance upon its content.

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic,
mechanical, photocopying, recording or otherwise, without the prior permission in writing from MPW R&R save that it may be read and saved by the original
recipient, for whose private use it was originally intended.

MPW R&R |1
About the Author
Profile CDM Experience

• Over 30 years’ experience • Led the independent evaluation of CDM 2007


• In the first part of his career, he was employed for the Health and Safety Executive (HSE),
by the Cement & Concrete Association on where the construction industry’s
concrete durability research and then by implementation of CDM 2007 was assessed to
see what changes had been made from the
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

Mouchel on the design, appraisal and site


supervision of building and bridge structures implementation of CDM 1994 and whether the
Dr Mike Webster
• For the past 20 years, he has focused on objectives of CDM 2007 had been met
BEng, MSc, PhD, DIC,
CEng, MICE, construction safety, risk and regulation
• Reviewed the implementation of CDM 2007 in
MIStructE • At the British Cement Association, his focus the construction of London 2012 on behalf of
was on structural safety and he led a range of HSE, the Olympic Delivery Authority and the
Director – MPW R&R projects to investigate the deterioration of Institution of Civil Engineers
concrete structures and develop guidance for
inspecting, assessing and managing existing • Helped HSE to analyse the responses to the
structures safely (including input to the Hong consultation on the draft ACoP for CDM 1994
Kong Building Safety Inspection System)
• As a Director at BOMEL Consultants, his • Acted as an expert witness on criminal
focus was more on human and organisational prosecutions of fatal and major injury
T: 07969 957471 risks, and he undertook a series of projects on accidents resulting from construction activity;
construction health and safety issues these cases have involved charges against
E: including the use of CDM Regulations clients, designers, planning supervisors,
mike.webster@mpwra principal contractors and contractors
• He undertook similar work as a Director of
ndr.co.uk
Frontline Consultants • Author of around 20 published reports and
W: • He recently set up MPW R&R to provide risk papers on construction health and safety and
http://mpwrandr.co.uk and regulatory solutions for regulators, CDM – details are available on
regulated organisations and litigants http://mpwrandr.co.uk/publications/

MPW R&R |2
Introduction

CDM 2015 This document

• The Construction (Design and Management) Regulations • This is the first document in this series, and provides a
2015 (CDM 2015) govern the management of health, safety clause-by-clause comparison of the Designer duties in CDM
and welfare when undertaking construction projects in Great 2015 and CDM 2007
Britain
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

• The relevant changes have been highlighted in bold


• CDM 2015 replaced CDM 2007 from 6 April 2015
• Comments are provided on the potential implication of the
• The key changes are: changes between the two versions of the regulations

– The CDM 2015 Regulations have a simplified structure • Comparisons are also available for Client duties and
– Clients’ responsibilities have been strengthened and Principal Contractor / Contractor duties:
broadened
– The exemption for Domestic Clients has been removed – http://mpwrandr.co.uk/client-duties-cdm-2015-v-cdm-
– The role of CDM Coordinator has been removed 2007/
– The new role of Principal Designer has been introduced – http://mpwrandr.co.uk/principal-contractor-and-contractor-
to plan, manage, monitor and coordinate the pre- duties-cdm-2015-v-cdm-2007/
construction (design) phase
– Notification of the project to the Health and Safety • A brief summary of eight key changes to the CDM 2015
Executive (HSE) has been removed as a trigger point for Regulations from CDM 2007 and what those changes mean
additional duties in practice: http://mpwrandr.co.uk/cdm-2015-summary-of-
– The threshold for appointing a Principal Designer and changes/
Principal Contractor is if more than one Contractor is
required on a project • If you have any comments, please drop me a line at
– The requirement for ‘competence’ has been removed and mike.webster@mpwrandr.co.uk
replaced with ‘skills, knowledge, experience and training’
and ‘organisational capability’

MPW R&R |3
Regulation 2 – Definitions

CDM 2015 CDM 2007 Initial Comments


Reg 2 (1) “design” includes drawings, Reg 2 (1) “design” includes drawings, • No differences
design details, specifications and bills of design details, specification and bill of
quantities (including specification of quantities (including specification of
articles or substances) relating to a articles or substances) relating to a
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

structure, and calculations prepared for structure, and calculations prepared for
the purpose of a design; the purpose of a design;
Reg 2 (1) “designer” means any person Reg 2 (1) “designer” means any person • Similar duty
(including a client, contractor or other (including a client, contractor or other
person referred to in these Regulations) person referred to in these Regulations)
who in the course or furtherance of a who in the course or furtherance of a
business— business—

(a) prepares or modifies a design; or (a) prepares or modifies a design; or


(b) arranges for, or instructs, any person (b) arranges for or instructs any person
under their control to do so, under his control to do so,

relating to a structure, or to a product or relating to a structure or to a product or


mechanical or electrical system intended mechanical or electrical system
for a particular structure, and a person is intended for a particular structure, and a
deemed to prepare a design where a person is deemed to prepare a design
design is prepared by a person under where a design is prepared by a person
their control; under his control;

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R |4
Regulation 8 – General Duties (1 of 3)

CDM 2015 CDM 2007 Initial Comments


Reg 8 (1) A designer (including a principal Reg 4 (2) Any reference in this regulation • Duty is now must rather than shall –
designer) or contractor (including a to a person being competent shall this is the case for all Designer duties
principal contractor) appointed to work on extend only to his being competent to— • Has split competence into its
a project must have the skills, (a) perform any requirement; and component parts of skills, knowledge,
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

knowledge and experience, and, if they (b) avoid contravening any prohibition, training and experience for individuals
are an organisation, the organisational imposed on him by or under any of the plus organisational capability for
capability, necessary to fulfil the role that relevant statutory provisions. organisations
they are appointed to undertake, in a
manner that secures the health and safety
of any person affected by the project.
Reg 8 (2) A designer or contractor must Reg 4 (1) No person on whom these • Only Contractors and Designers have
not accept an appointment to a project Regulations place a duty shall— this duty, not the Client
unless they fulfil the conditions in (b) accept such an appointment or
paragraph (1). engagement unless he is competent;
Reg 8 (3) A person who is responsible for Reg 4 (1) No person on whom these • Duty holders now only need to take
appointing a designer or contractor to Regulations place a duty shall— ‘reasonable steps to satisfy
carry out work on a project must take (a) appoint or engage a CDM co- themselves’ rather than ‘reasonable
reasonable steps to satisfy themselves ordinator, designer, principal contractor steps to ensure’
that the designer or contractor fulfils the or contractor unless he has taken
conditions in paragraph (1). reasonable steps to ensure that the
person to be appointed or engaged is
competent;

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R |5
Regulation 8 – General Duties (2 of 3)

CDM 2015 CDM 2007 Initial Comments


Reg 8 (4) A person with a duty or Reg 5 (1) Every person concerned in a • The duty to cooperate has been
function under these Regulations must project on whom a duty is placed by extended to those who have a ‘function’
cooperate with any other person working these Regulations, including paragraph under CDM
on or in relation to a project, at the same (2), shall— • The duty to ‘seek the co-operation of
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

or an adjoining construction site, to the (a) seek the co-operation of any other any other person concerned in any
extent necessary to enable any person person concerned in any project involving project ...’ has been removed – the duty
with a duty or function to fulfil that duty or construction work at the same or an to cooperate has been extended to
function. adjoining site so far as is necessary to ‘any other person’ is covered by
enable himself to perform any duty or ‘function’
function under these Regulations; and
(b) co-operate with any other person
concerned in any project involving
construction work at the same or an
adjoining site so far as is necessary to
enable that person to perform any duty or
function under these Regulations.
Reg 8 (5) A person working on a project Reg 5 (2) Every person concerned in a • Similar duty
under the control of another must report project who is working under the control of • Duty is now explicitly ‘in relation to the
to that person anything they are aware of another person shall report to that person project’
in relation to the project which is likely anything which he is aware is likely to
to endanger their own health or safety or endanger the health or safety of himself
that of others. or others.

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R |6
Regulation 8 – General Duties (3 of 3)

CDM 2015 CDM 2007 Initial Comments


Reg 8 (6) Any person who is required by • New duty to ‘ensure the information or
these Regulations to provide information instruction is comprehensible and
or instruction must ensure the information provided as soon as practicable’
or instruction is comprehensible and • Paragraphs 69 and 70 of HSE’s
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

provided as soon as is practicable. Guidance provides guidance on what is


considered to be ‘comprehensible
(easy to understand, / plain simple
clear English (and/or other languages)
• The duty is ‘practicable’ NOT
‘reasonably practicable’ (Paragraph 71
indicates ‘’before the work begins’_
Reg 8 (7) To the extent that they are • New duty to tie in with requirements for
applicable to a domestic client, the duties domestic clients
in paragraphs (3), (4) and (6) must be
carried out by the person specified in
regulation 7(1).
Reg 6 All persons concerned in a project • No explicit requirement for all duty
on whom a duty is placed by these holders (including Designers) to co-
Regulations shall co-ordinate their ordinate their activities in CDM 2015
activities with one another in a manner • However, Principal Designer (Reg 11(1)
which ensures, so far as is reasonably and (5)) and Principal Contractors (Reg
practicable, the health and safety of 13(1) and (3)) do have duties to
persons— coordinate
(a) carrying out the construction work; and
(b) affected by the construction work.
Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf
CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R |7
Regulation 9 – Duties of Designers (1 of 3)

CDM 2015 CDM 2007 Initial Comments


Reg 9 (1) A designer must not commence Reg 11 (1) No designer shall commence • Designer now needs to be ‘satisfied
work in relation to a project unless work in relation to a project unless any that the client is aware’ rather than
satisfied that the client is aware of the client for the project is aware of his duties ‘client for the project is aware’
duties owed by the client under these under these Regulations.
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

Regulations.
Reg 9 (2) When preparing or modifying a Reg 11 (2) The duties in paragraphs (3) • Duty now to take account of ‘any pre-
design the designer must take into and (4) shall be performed so far as is construction information’
account the general principles of reasonably practicable, taking due • The requirement for ‘taking due
prevention and any pre-construction account of other relevant design account of other relevant design
information to eliminate, so far as is considerations. considerations’ is not stated explicitly in
reasonably practicable, foreseeable risks (3) Every designer shall in preparing or the CDM 2015 Regulations, but is
to the health or safety of any person— modifying a design which may be used in covered in Paragraph 83 of HSE’s
(a) carrying out or liable to be affected by construction work in Great Britain avoid Guidance where it states that: ‘Health
construction work; foreseeable risks to the health and and safety risks need to be considered
(b) maintaining or cleaning a structure; or safety of any person— alongside other factors that influence
(c) using a structure designed as a (a) carrying out construction work; the design, such as cost, fitness for
workplace. (b) liable to be affected by such purpose, aesthetics and environmental
construction work; impact.’
(c) cleaning any window or any
transparent or translucent wall, ceiling or
roof in or on a structure;
(d) maintaining the permanent fixtures
and fittings of a structure; or
(e) using a structure designed as a
workplace.

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R |8
Regulation 9 – Duties of Designers (2 of 3)

CDM 2015 CDM 2007 Initial Comments


Reg 9 (3) If it is not possible to eliminate Reg 11 (4) In discharging the duty in • Now a duty to ‘control the risks’ if
these risks, the designer must, so far as paragraph (3), the designer shall— elimination or reduction are not
is reasonably practicable— (a) eliminate hazards which may give possible
(a) take steps to reduce or, if that is not rise to risks; and • Duty is now to ‘eliminate risks’ rather
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

possible, control the risks through the (b) reduce risks from any remaining than ‘eliminate hazards’
subsequent design process; hazards,
(b) provide information about those and in so doing shall give collective
risks to the principal designer; and measures priority over individual
(c) ensure appropriate information is measures.
included in the health and safety file.
Reg 9 (3) If it is not possible to eliminate Reg 18 (2) The designer shall take all • Duty is now ‘so far as reasonably
these risks, the designer must, so far as reasonable steps to provide with his practicable’ rather than ‘take all
is reasonably practicable— design sufficient information about reasonable steps’
(b) provide information about those aspects of the design of the structure or • Duty is now to provide ‘information
risks to the principal designer; and its construction or maintenance as will about those risks’ rather than ‘sufficient
(c) ensure appropriate information is adequately assist the CDM co-ordinator to information’ (to the Principal Designer
included in the health and safety file. comply with his duties under these rather than the CDM Co-ordinator)
Regulations, including his duties in • Duty is now to provide ‘appropriate
relation to the health and safety file. information’ rather than ‘sufficient
information’ for the Health and Safety
File

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R |9
Regulation 9 – Duties of Designers (3 of 3)

CDM 2015 CDM 2007 Initial Comments


Reg 9 (4) A designer must take all Reg 11 (6) The designer shall take all • Duty is no longer limited to ‘aspects of’
reasonable steps to provide, with the reasonable steps to provide with his
design, sufficient information about the design sufficient information about
design, construction or maintenance of aspects of the design of the structure or
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

the structure, to adequately assist the its construction or maintenance as will


client, other designers and contractors to adequately assist—
comply with their duties under these (a) clients;
Regulations. (b) other designers; and
(c) contractors,
to comply with their duties under these
Regulations.

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R | 10
Regulation 10 – Designs prepared or modified outside Great Britain

CDM 2015 CDM 2007 Initial Comments


Reg 10 (1) Where a design is prepared or Reg 12 Where a design is prepared or • Similar duty
modified outside Great Britain for use in modified outside Great Britain for use in
construction work to which these construction work to which these
Regulations apply— Regulations apply—
17\CDM\01 - MPW R&R - CDM 2015 vs CDM 2007 – Designer v2.0

(a) the person who commissions it, if (a) the person who commissions it, if he is
established within Great Britain; or established within Great Britain; or
(b) if that person is not so established, the (b) if that person is not so established,
client for the project, must ensure that any client for the project, shall ensure
regulation 9 is complied with. that regulation 11 is complied with.

Source: CDM 2007 http://www.hse.gov.uk/pubns/priced/l144.pdf


CDM 2015 http://www.legislation.gov.uk/uksi/2015/51/pdfs/uksi_20150051_en.pdf MPW R&R | 11