BILL OE ENGINEERING MEASUREMENTS AND 

EVALUATION

ITEM  DESCRIPTION  UNIT  QTY  RATE (N)  AMOUNT (N)


         1.00 SITE CLEARANCE
         1.01 Clear site downstream of dam and make it 
free of vegetative growth  m2 640                     110.00                 70,400.00
         1.02
Ditto for site clearance upstream of dam. 
Rate to include for carting away to spoil  m2 3200                     110.00               352,000.00
Sub Total Item 1.00              422,400.00

         2.00 EARTHWORKS EXCAVATION
         2.01 Excavate in soil for the Dam / Weir in 
foundation works along its axis, rate to 
include for storage if found reusable as per 
the appropriat work drawings.  m3 817                 3,384.00            2,764,728.00
         2.02 Ditto for rock excavation Provisional 
quantity only (PQ)  m3 245.1                 4,000.00               980,400.00
         2.03
Ditto for excavaion in rock for the trench and 
toe key to foundation works.(PQ)  m3 64.5                 4,000.00               258,000.00
         2.04 Drill in Rock for the anchorage of the dam to 
solid weathered rock, holes of size 1.5M x 
50mm Diameter in trench and toe key.  (212 
Nos holes) m3 0.63                 5,000.00                   3,150.00
         2.05 Supply and place in position suitable sand / 
cement slurry as hold‐down to anchor bars 
in holes.  m3 0.53               25,000.00                 13,250.00
         2.06 Ditto for the supply and place in position 
anchor bars of size 20mm Diameter x 1.5M 
long ton 0.8             561,330.00               449,064.00
Sub Total item 2.00           4,468,592.00

         3.00 CONCRETE WORKS
         3.01
Supply and place in position 50mm layer 
Grade 20 concrete as blinding to foundation 
works base slab to dam, rate to include for 
adequate tapping to level  m2 344               45,257.00         15,568,408.00
         3.02 Ditto for blinding concrete in trench and the 
toe key m2 94.6               45,257.00            4,281,312.20
         3.03 Ditto for Grade 35 Concrete in Dam's trench 
and the toe key  m3 64.5               85,000.00            5,482,500.00
         3.04 Ditto for grade 35 concrete to foundation 
works to dam as per the appropriate work 
drawing, rate to include for necessary 
compaction  m3 302.4               85,000.00         25,704,000.00
         3.05 Ditto for grade 35 concrete in dam's wall and 
spill weir  m3 302.13               85,000.00         25,681,050.00

Sub Total item 3.00        76,717,270.20

         4.00 SHUTTERING FORMWORKS
         4.01 Supply and place in position wrought 
shuttering formworks to sides of concrete in 
trench and toe key, rate to include for 
removal  m2 81.9                 3,600.00               294,840.00
         4.02 Ditto for shutters to sides of foundation base 
to dam m2 90                 3,600.00               324,000.00
         4.03 Ditto for wrought shutters to sides of trench 
and toe key to dam's spill weir, rate to 
include for removal.  m2 54.5                 3,600.00               196,200.00
         4.04 Ditto for smooth surface shutters to dam's 
wall.  m2 272.4                 3,600.00               980,640.00
         4.05 Ditto for smooth surface shutters to spillweir 
section of dam  m2 170.4                 3,600.00               613,440.00
Sub Total item 4.00          2,409,120.00

         5.00 REINFORCEMENT IN DAM
         5.01 Supply and place in position high yield steel 
reinforcement in dam's trench and toe key 
as per the specification in the work 
drawings.  ton 5.064             380,000.00            1,924,320.00
         5.02 Ditto for high yield steel reinforcement in 
foundation works base slab to dam ton 11.87             380,000.00            4,510,600.00
         5.03 Ditto for high yield steel reinforcement bars 
in walls to dam  ton  14.79             380,000.00            5,620,200.00
         5.04 Ditto for high yield steel reinforcement bars 
in dams spillweir ton  8.93             380,000.00            3,393,400.00
Sub Total Item 5.00        15,448,520.00

         6.00 ABUTMENT WALLS TO SPILLWEIR
         6.01 Supply and place in position grade 35 
concrete in abutment walls to spillweir, 
upstream section only.  m3 2               85,000.00               170,000.00
         6.02 Ditto for Grade 35 concrete in abutment 
walls, downstream only.  m3 8.4               85,000.00               714,000.00
         6.03
Ditto for the supply and place in position 
high yield reinforcement bars in upstream 
and downstream abutment walls  ton  0.66             380,000.00               250,800.00
         6.04
Ditto for smooth surface shuttering 
formwork to abutment walls (both upstream 
and downstream) ate to include for removal m2 45.31                 3,600.00               163,116.00
Sub total item 6.00          1,297,916.00

         7.00 RETAINING WALL ‐ UPSTREAM OF DAM, 
ALONG THE RIVER BANK 
         7.01 Excavate in soil along the left hand side of 
the river bank to dam, rate to include for 
carting away to spoil.  m3 84.5                 3,384.00               285,948.00
         7.02 Ditto for rock excavation to foundation 
works base slab to retaining wall. Provisional 
Quantity only  m3 25.35                 4,000.00               101,400.00
         7.03 Supply and place in position grade 20 as 
blinding concrete to retaining wall footing, 
rate to include for tapping m2 23.8               45,257.00            1,077,116.60
         7.04 Ditto for grade 35 concrete in wall base 
footing, rate to include for necessary 
compaction  m3 12.24               85,000.00            1,040,400.00
         7.05 Ditto for grade 35 concrete in wall   m3 32.64              85,000.00           2,774,400.00
         7.06
Ditto for the supply and place in position 
high yield reinforcement bars in wall footing.  ton  0.961             380,000.00               365,180.00
         7.07 Ditto for high yield reinforcement in 
retaining wall.  ton  2.6             380,000.00               988,000.00
         7.08 Supply and place in position wrought surface 
formwork to wall footng, rate to include for 
removal  m2 21.12                 3,600.00                 76,032.00
         7.09 Ditto for shutters to retaining wal as per 
item 7.08 m2 219.52                 3,600.00               790,272.00
Sub Total item 7.00          7,498,748.60
         8.00 INTAKE WORK CHAMBER
         8.01 Excavate in soil for the foundation works to 
Intake work chamber, rate to include for 
carting away to spoil just as per the 
necessary work drawings.  m3 55.8                 3,384.00               188,827.20
         8.02 Ditto for rock excavation  m3 16.74                4,000.00                66,960.00
         8.03 Supply and place in position grade 20 
concrete as blinding to foundation base slab 
to Intake chamber  m2 30.25               45,257.00            1,369,024.25
         8.04 Ditto for grade 35 concrete in base slab to 
Intake chamber, rate to include for 
necessary compaction  m3 11.7               85,000.00               994,500.00
         8.05 Ditto for grade 35 in walls to chamber  m3 32.4              85,000.00           2,754,000.00
         8.06 Ditto for grade 35 concrete in roof slab to 
chamber  m3 5.81               85,000.00               493,850.00
         8.07 ditto for the supply and place in position 
high yield steel reinforcement basis in base 
slab to chamber  ton  0.92             380,000.00               349,600.00
         8.08
Ditto for high  yield bars in walls of chamber  ton  2.55             380,000.00               969,000.00
         8.09 Ditto for high yield reinforcement bars in 
roof slab of chamber ton  0.456             380,000.00               173,280.00
         8.10 ditto for side shutters to base of chamber, 
rate to include for removal  m2 8.64                 3,600.00                 31,104.00
         8.11 Ditto for shutters of walls of chamber, 
internal sides only m2 73.6                 3,600.00               264,960.00
         8.12 Ditto for shutters to walls of chamber, 
external sides only.  m2 88.32                 3,600.00               317,952.00
         8.13 Ditto for smooth surface shutters to soffit of 
roof slab to chamber  m2 19.36                 3,600.00                 69,696.00
         8.14 Ditto for sides shutters to roof slab of 
chamber  m2 5.28                 3,600.00                 19,008.00
Sub total Item 8.00          8,061,761.45

         9.00 PEDESTRIAN WALKWAY BRIDGE ‐ DAM TO 
INTAKE WORK CHAMBER
         9.01 Supply and place in position grade 35 
concrete in U‐beam precast concrete size 
300 x 1000 x 1800mm as per the appropriate 
work drawing.  m3 0.41               85,000.00                 34,850.00
         9.02 Ditto for high yield stel reinforcement bars in 
U‐beam  ton  0.1             380,000.00                 38,000.00
         9.03
Ditto for sides and soffit shutters to U‐beam.  m2 3.48                 3,600.00                 12,528.00
Sub Total Item 9.00                85,378.00

       10.00 MISCELLANEOUS ITEMS 
THE DAM
       10.01 Supply and place in position as per the 
specification in accordance with the 
appropriate wotk drawings Expansion Joint 
Sevitite type XJ size 13 x 140mm. M 82               10,000.00               820,000.00
       10.02 Ditto for Servitite CJ type size 13 x 150mm as 
construction joint in dam  M 12.5               12,000.00               150,000.00
       10.03
Allow for the supply and installation of steel 
pipe size 250mm diameter or High Density 
Plastic pipe or similar as silt desilting / 
dewatering through the dam, rate to include 
for the necessary pipe fittings  M 11             150,000.00            1,650,000.00
       10.04 Ditto for chute blocks downstream side of 
the dam, infrnt of the spillweir. Size of 
trianglarly shaped blocks 400 x 500 x 
2000mm.  nos  5               20,000.00               100,000.00
       10.05
Allow for the installation of 250mm 
diameter Steel pipe or High Density plastic 
pipe Provisional Quantity, rates inclusive of 
excavation for pipe laying and backfilling 
with fittings and appurtenances m 30             150,000.00            4,500,000.00
Sub total Item 10.00          7,220,000.00

       11.00 INTAKE CHAMBER
       11.01
Supply and place in steelwork ladder of size 
400 x 4600mm x 300mm rungs, rate to 
include for coating with approved anti ‐rust 
paints with one coat of prime and two coats 
of marine bitumonous paint.  no 1             250,000.00               250,000.00
       11.02 Ditto for the supply and installation of 
penstock gates, each of size 250mm nominal 
diameter as per the appropriate 
specification in accordance to the working 
drawings nos  4             300,000.00            1,200,000.00
       11.03
Ditto for the supply and place in position 
Servitite CJ types as construction joint to 
base slab of chamber  nos  17.6               12,000.00               211,200.00
       11.04 Ditto for Servitite CJ as joints in walls size 13 
x 150mm  no 9.2               12,000.00               110,400.00
       11.05
Allow for 250mm diameter holes in walls of 
chamber for raw water inlet and outlet  nos  5                 5,000.00                 25,000.00
Sub Total Item 11.00          1,796,600.00

       12.00 BANK RETAINING WALL 
       12.01 Allow for the supply and place in position  
Constrction Joint Servitite type CJ in wall and 
base slab to retaining wall. Size 13 x 150mm 
refers.  m 30.4               12,000.00               364,800.00
Sub total item 12.00              364,800.00

       13.00 BOULDERS TO UPSTREAM BASE OF DAM / 
WEIR
       13.01
Supply and place in position rock boulders of 
size 200 to 300mm as per the appropriate 
working drawings upstream face only m3 160               50,000.00            8,000,000.00
Sub total Item 13.00          8,000,000.00

SUMMARY
         1.00 SITE CLEARANCE              422,400.00
         2.00 EARTHWORKS EXCAVATION           4,468,592.00
         3.00 CONCRETE WORKS        76,717,270.20
         4.00 SHUTTERING FORMWORKS           2,409,120.00
         5.00 REINFORCEMENT IN DAM        15,448,520.00
         6.00 ABUTMENT WALLS TO SPILLWEIR           1,297,916.00
         7.00 RETAINING WALL ‐ UPSTREAM OF DAM, 
ALONG THE RIVER BANK             7,498,748.60
         8.00 INTAKE WORK CHAMBER           8,061,761.45
         9.00 PEDESTRIAN WALKWAY BRIDGE ‐ DAM TO 
INTAKE WORK CHAMBER                 85,378.00
       10.00 MISCELLANEOUS ITEMS            7,220,000.00
       11.00 INTAKE CHAMBER           1,796,600.00
       12.00 BANK RETAINING WALL               364,800.00
       13.00 BOULDERS TO UPSTREAM BASE OF DAM / 
WEIR            8,000,000.00

SUB TOTAL      133,791,106.25

Allow for physical Contingency % 10%   133,791,106.25        13,379,110.63

Allof for Engineering Services % 5%   133,791,106.25           6,689,555.31

GRAND TOTAL      153,859,772.19