Method Statement for Pouring Concrete on

Slab on Grade
After backfilling works the next is casting slab on grade (ground), make sure that
all the area beneath grade slab have been properly backfilled and compacted.

Approval must be obtained from the Engineer for waterproofing and backfilling
works prior to start slab on grade casting.

Here is the method statement of Slab on Grade preparation and concrete


pouring.

1. Title
Method Statement for Casting Slab on Grade

2. Purpose and scope


The purpose of this method statement is to explain the proper procedure on how
to prepare and cast slab on grade1 or any horizontal element or member
including fixation of steel reinforcement, MEP embedment’s, fixing of shutter etc.
without injuries.
3. Work procedure
1. Site planning
 Delivery – fresh concrete shall be batched from the approved supplier
of concrete. Concrete will be delivered direct to the site and to be
received by assistant Quality Engineer for checking of the required
criteria of concrete. The assistant QC Engineer will make sure the
concrete delivered is as per the approved design mix for the situated
member to be casted.
 All data for testing on fresh concrete at site shall be recorded on the
concrete pour card.
2. Preparation
 After the blinding is casted and placement of waterproofing is done,
the preparation and casting for slab on grade shall be done.
 Fix the reinforcement steel as per the approved drawings, sometimes
A393 BRC mesh is indicated in the drawing and most commonly use
in 250mm thick concrete grade slab.
 Any loose binder or ties along the splices reinforcement steel shall be
re-tightened. Bend inward the free ends of the binding wire or ties.1
 Use PVC spacer for vertical bars and concrete spacer for bottom as
concrete covers.
 Ensure and coordinate with MEP staff for any MEP works required on
the area as per approved drawings.
 Fix the forms such; supports, sleeves etc., if any.
 Any damaged materials used for form work or shutter like plywood
shall not be used.
 All surface of forms or shutter facing concrete shall be treated with
shuttering oil and dampen with water few minutes before concrete will
be poured1.
 Clean the slabs on grade using air compressor for dust or any small
particles or deleterious materials that may impair the workability of
concrete.
 The surveyor will then checked the level of the projected top surface of
the slab and place level strips if necessary to mark the exact level.
 The concreting are as must be arranged with necessary equipment or
tools for concreting use such as vibrators, power float machine, shovel
etc.1
 Skilled and unskilled labor shall need to use safety requirements such
as safety helmet, safety shoes, goggles, gloves, vest etc.
 Safety devices and safety warnings shall be provided starting from the
site entrance gate till the casting area.
 Proper lighting must be available in case of night concreting.

3. Concrete pouring
 The concrete mixer must be stopped at the check point for the
inspection of slump test and to obtain sample cubes for test.
 One set of cubes shall be taken every 50 cubic meter concrete, each
set consist of 6 cubes, 3 cubes to be tested on 7th days and 3 cubes
to be tested for 28th days.
 Extra three cubes can be made for re-checking if in case
circumstances may happen.
 Unload the concrete within 90 minutes from the batching plant loading
time.
 Compact the concrete properly by using mechanical vibrators, extra
vibrator shall be available in case of any shortage or mechanical
problems.
 Use approved hardener material after casting concrete when required.
Make sure applications shall be as per manufacturer’s
recommendation.
 Use the power float for the smooth finish surface purpose. Store extra
power float near the casting area in case of any mechanical
malfunctioning.
 Cure the casted area properly with covering concrete with hessian
cloth and polythene sheet on top but before placing the concrete wet
the hessian with water.
 Cure the concrete by spraying water three times per day for a period of
7 days.
 The casted area or member shall be protected by placing barricade to
prevent plants and machineries damaged the concrete.
 Concrete pour card shall be filled by Quality Engineer and to be
submitted to the Engineer including concrete delivery notes, this task
will be done whenever required.
 Concrete cube test report shall be submitted to the Engineer
4. Safety
1. All works shall comply with safety procedure or instruction set out in project
safety plan and municipality rules and regulations.
2. Basic PPE to be worn by all staff and laborers.
3. Trained operator and banksman would be engaged to control or operate
heavy equipment machine.
4. Provide sufficient lighting whenever night casting.
5. Equipment and tools
1. Concrete Pump
2. Concrete Mixer
3. Mini truck
4. Bob cat
5. Concrete vibrators
6. Wheel borrow
7. Slump tray
8. Slump cone and other associated tools
9. Rubber hammer
6. Materials and References
1. C40/20 Concrete Grade with additives
2. Deformed bars or A393 BRC mesh
3. Approved drawing