Method Statement
For
Construction of Board Pile
Table of Content
1.0 Introduction................................................................................................................................. 3
10.0 Appendix B – Inspection and Test Plan for Piling work .......................................................... 21
2
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
1.0 Introduction
Port City Colombo is a brand new city development built as an extension of the Central
Business District of Sri Lanka’s vibrant commercial capital, Colombo. Spanning 269
hectares of reclaimed land from the sea, Port City Colombo will be South Asia’s premiere
residential, retail and business destination, offering unmatched planned city living along the
warm waters of the Indian Ocean. The development will comprise of 5 different precincts
including the Financial District, Central Park Living, Island Living, The Marina and the
International Island.
PHASE 1
PHASE 2
Package V – Pumping Stations & Storage Tanks under Infrastructure and Landscape Works
(Phase 1) Project of Colombo Port City Development Project, is to build Infrastructure and
Utility Buildings.
This method statement covers the details of materials, equipment, procedure and relevant
documents related to the work for the Concrete Board Piles in Buildings Listed in following
Table, including quality control and safety precautions to be implemented at site as follows;
3
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
4.0 Responsibilities
Detailed organizational responsibilities and accountabilities of key personal; Project
Manager, Construction manager, Engineering staff, Supervisory staff, etc…; whose scope
of works defined in ‘Occupational Health & Safety Plan’ shall be responsible for referred
construction activities under this project. Further, details of records in respect of carrying
out the works are outlined in the Inspection and Test Plan for Board Piling Works, which is
enclosed in Appendix A.
5.0 Resources
Whole Work would be categorised to specified sub tasks as follows to assign resources
effectively. The capacity/size of the below tools and equipment shall be judged in
accordance with site conditions, requirements, and availability at the time of execution.
5.1 Manpower:-
QAQC Manager - 01 Skilled Workers - As required
Site Engineer - 01 Labours - As required
5.3 Material
Bentonite
Concrete
Reinforcement
Metal casing
a. Technical director is responsible to ask relevant people to jointly review the drawing,
understand the design idea and study corresponding documents.
b. The constructors should be familiar with the geological situation of the project.
c. The technical director formulates and adds the technical schemes and measures of the
construction in accordance with the features of the project.
d. Make technical disclosure and record to all the constructors before the project starts.
e. Prepare the recording sheet and appliances for labor protection for the construction.
g. The construction site is smooth and flat. Road: know the entry road and arrange the
temporary road. Electricity: connect the power supply; Water: connect the water source
nearby.
h. Make a plan of the places for construction materials, slurry storage, arrangement of
temporary facilities and ground plan for the construction site.
5
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
Mixing
Casing Setting-out
Fabricating Steel Bentonite
Cage
Drilling
Inspection
Cleaning Base
OK
Inspection
OK
Insert Steel Cage
Recycling Bentonite
nd
Cleaning 2 Time
Concrete Placing
Placing Concrete Record
The pile location shall be set out in accordance with the approved Bored Pile Foundation
layout plan. All setting out reference points and related contractor drawings shall also be
referred. Setting out of pile location, ground level and ancillary control points shall be
checked and confirmed with the Engineer prior commencement of piling works. Once the
first section of pile casing is erected, the setting out with all ancillary control points and
vertically of the pile will be re-checked with the Engineer before piling works proceeds
further.
At least three ancillary control points offset from the pile should be established in its vicinity
for facilitating the execution of setting out and survey check related to the piling works. The
control points, which are established in the form of marking on wooden peg with concrete
6
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
surround set on ground, should be guarded and regularly check for their accuracy during the
piling works.
The temporary casing used will be free from any distortion and shall be uniform cross-
section throughout the length. The length of the casing will be approx. 6.0 meters, depending
on the cut-off level. The temporary steel casing will be driven in the pile center with a
minimum overlap of 50 cm below cut-off level. The top of the temporary casing should be
300mm over the ground.
Two numbers reference steel pins will be installed equidistant from the pile point. The
distance of the steel casing is measured from the reference pins and adjustment made so that
the reference pins are equidistant from the steel casing. The verticality of the steel casing is
checked with a spirit level in two perpendicular directions. Further the verticality can be
controlled by an inbuilt inclinometer fixed to the boom of machine. The verticality of the
drilled borehole will be recorded in the pile record sheet.
In the event that the location or verticality of a casing is out of tolerances as a result of
driving the casing should be vertically adjusted by use of an excavator. Alternatively the
casing will be backfilled, pulled out and re-driven if required. Otherwise, the contractor
would proposed alternative corrective method for the Engineer’s approval.
7
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
Bentonite comply with Specification DFCP-4 drilling fluid materials will be used for the
slurry. Control tests will be performed on the bentonite suspension as per specifications. The
drilling fluid is prepared in mixers and kept in tanks for storage and hydration purpose for a
minimum period of 4 hours. After fixing of guide casing, the borehole will be drilled down
to its final level by means of bucket and auger.
The drilled borehole will be filled with bentonite slurry and the slurry level maintained at
working platform level at all times. Care shall be taken to maintain the slurry 1.50 m above
the ground water table. In the event of a rapid loss of drilling fluid, the borehole will be
backfilled without delay using the drilled material from heap near the boreholes. The
Engineer’s approval must be obtain before resuming boring in that location.
Drilling penetration rate and soil cuttings will be kept under observation to notice any change
in the sub-soil conditions from previous soil investigation. The record of strata will be made
during excavation of the pile and recorded on the pile record sheet.
Any noticeable variation shall be brought to the attention of the Engineer. The depth of
borehole shall be measured using an end weight measuring tape and to be recorded in the
pile record sheet. The verticality of the borehole will be guaranteed in two ways:
1. A hand held sprit level of 1.0 m length shall be used to check the verticality of mast and
thereby that of the casing at two directions of 90° to one another at intervals.
2. Some machines are equipped with in built inclinometers fixed to the boom of the
machine, which can monitor the drilling operations to keep the verticality within the
specified limits. The maximum out of verticality allowed as per specification is 12.5%
of the pile diameter or 1.5% of pile length whichever is smaller.
Excavate shafts for closely spaced drilled piles (<3 x diameter), only after adjacent drilled
piles are filled with concrete and allowed to set. (Normally after 12.0 hours)
The drilling will be continued till the bed rock is encountered. When the bore has reached
the bedrock level, Engineer will be informed for inspection of that, which combines with the
drawing and the actual condition of the stratum.
Measurement of depth are usually taken by using a tape measure or a marked chain. The
measuring instrument should be checked for accuracy prior to commencement, and
periodically thereafter.
Drilling in rock for Rock Socketing shall continue after determining the actual founding
level after examining the excavated material/rock samples. The authorized representatives
of both parties should agree the founding level. Written agreement is required to certify that
founding has been achieved.
The process of cleaning the bentonite suspension from sands and silts to keep its quality
8
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
within the allowable limits is called recycling. The bentonite quality will be verified by
checking the sample taken from the top and bottom of the borehole. If excessive sand
contents are noticed in the bentonite sample then fresh bentonite sample be pumped through
the sealed tremie pipe. The tremie pipe shall extend to the bottom of the borehole. The
sample from the borehole shall be checked for its compliance with specification
requirements.
Recycling will be performed after excavation has been completed and before the bentonite
slurry has been replaced by concrete. The suspension from the borehole will be pumped to
the desanding plant during concreting. After being cleaned in the plant, the bentonite will be
pumped to the bentonite tank for further use. For cleaning operation of the bottom of the
borehole cleaning bucket will be used.
Recycling or circulation method of bentonite shall be used to clean the bottom of bore hole.
Circulation will continue until debris suspended in the circulating water deposited in the
slurry channel is negligible, and ensure that heavily contaminated support fluid, which could
impair the free flow of concrete from the tremie pipe, has not accumulated in the bottom of
the hole.
BENTONITE SUSPENSION
We propose a bentonite concentration of 5%. Bentonite slurry will have the following
properties.
Supply to: Sample From:
Pile Borehole Pile Borehole
Density : < 1.10 g/cm3 < 1.15 g/cm3
Plastic Viscosity : < 10 CP < 20 CP
Viscosity : 30 to 40 seconds < 60 seconds
Ph value : 9.5 to 10.80 9.5 to 11.70
Sand Cement : < 1% < 3%
Shear Strength : 4 – 25 N/m2 4 – 25 N/m2
(10 Min.) Gel strength
Fluid loss : < 30 mil. < 40 mil
9
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
The bentonite slurry shall be checked for specification compliance at suitable intervals. One
sample shall be taken from the top of the borehole and another sample from the bottom to
check compliance with the specification requirements. We propose the following sequence
of bentonite slurry testing for each pile.
The bentonite powder is supplied with the test certificate from independent agency. However
occasional testing can be carried out on powder sample if required by Engineer.
10
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
The reinforcement for the piles shall be according to the requirement of the specification and
the design of the pile. The reinforcement shall confirm to the mill certificate approved by
the Consultant. Reinforcement shall be free of mud, oil, other surface contamination and
excessive corrosion at time of concrete placement.
The reinforcement cages will be fabricated up to 12m length and rebar shall be lapped when
the requirement is more than 12m length, maintaining minimum lap length as specified. Full
length reinforcement cage fixed with helical shall be lowered to the borehole. The cage shall
be arrested in position when it reaches 2.0m above casing top level. Suitable crossbars shall
be provided to keep the cage hanging in position. The reinforcement segments for 600/900
mm diameter piles will be connected together using the couplers fixed to the end staggered
at a minimum clear distance of 70 cm c/c to receive the second segment pile cage. The helical
reinforcement / rings shall be fixed in place after connecting the two segments of
reinforcement for piles. The reinforcement shall be lowered to correct location and cage top
level and secured from movement using hangers and arresters.
A lifting platform shall be used for the lifting of the steel cage without distortion. The steel
cages will be lifted with the help of main crane (50 ton capacity) and an auxiliary crane
(service crane of 35 ton capacity) shall be used to lift the lifting platform along with the steel
cage. The lifting platform shall be released once the cage reaches 90°.
The concrete will be checked for the slump and temperature. Cubes will then be taken as per
specification. The concrete will be allowed to the site only after concrete quality has been
found in compliance with specifications. The concreting of the drilled piles should be
completed on the same date of completion of borehole. If there is an elapsed time of more
11
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
than 6 hours between the completion of borehole & cage installation, cleaning bucket shall
be carried out to clean the borehole.
The concrete shall be placed by tremie tube method, the tremie size will not be less than 150
mm. The tremie pipe is made of sections with sufficient length to reach the toe of the pile
and the joints provided with seals. The tremie pipe will be inserted at the center of the pile
and the joints provided with seals. The concrete from the concrete mixer shall be delivered
directly to the pile through the funnel connected to the tremie pipe of 150 mm diameter. The
tremie pipe will be lifted 100 mm above pile toe level prior to concreting. A Styrofoam ball
having a diameter slightly larger than the diameter of the tremie pipe shall be placed at the
mouth of the tremie pipe to avoid contact of concrete with bentonite slurry in the tremie pipe.
While concreting the length of the tremie pipe will be shortened if necessary but the tremie
pipe will be maintained full time into the concrete of at least 2.0m length. During the
concreting the level of the concrete within the pile will be monitored by use of an end weight
tape measure.
A sufficient quantity of concrete will be maintained within the tremie to ensure that the
pressure from it exceeds that from the external water pressure. The concrete will be brought
up to minimum 1.30 m above cut-off level and overflowing of concrete above casing top
level will be carried out to ensure good quality and contamination free concrete at pile cut-
off level. The concrete above the cut –off level will be chipped by the Main Contractor. The
bentonite slurry displaced by the concrete will be pumped back to the desander or tank.
The quantity of poured concrete volume will be measured & it will be compared with the
theoretical quantity. The theoretical volume, actual volume & % over break will be recorded
in the pile record sheet and plotted on a graph sheet for the submission to the main contractor.
Spoil from drilling of boreholes shall be removed from site to designated disposal area
12
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
provided by the local authorities and will be carried out by the Main Contractor.
The pile position shall be cross-checked by the Engineer, Contractor and Sub Contractor
before the installation of pile. If any out of position of the pile (more than the allowable
tolerance) has been noticed after the concreting of the pile, it shall be brought to the notice
of the Engineer through N.C.R.
13
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
During the drilling operation there are remote chances for the loss of drilling tools in the
bore holes due to the high torque applied to cut the soil/rock. In order to avoid the same
periodic checking shall be carried out on drilling tools. If any drilling tool has been lost in
the bore hole then the issue to be brought to the notice of Engineer immediately and all the
activities around that pile shall be stopped. A method statement for the excavation of drilling
tools will be submitted to the Engineer for approval and further action.
The collapse of borehole may happen if the drilling is carried out through the unstable strata
and poor quality bentonite slurry has been used for the drillings. This can be avoided by
checking the bentonite slurry properties during drilling operations. In the case of collapse of
borehole & rapid loss of drilling fluid, the borehole will be back filled without delay using
drilled material from the heap, near the borehole.
The Engineer’s approval will be obtained before resuming boring in that location.
During the installation of piling reinforcement cage support beams and jacks shall be
provided to hang the reinforcement segment in the bore hole in addition to the safety sling
from the service crane. The coupler connection between the reinforcement segments shall
be double verified by the Foreman before removing the support system for the bottom
segment. Any loss of reinforcement segment shall be notified immediately to the Engineer.
The tremie pipe is made of segments of 1.5 m for diameter 150 mm and approximately 2.0
m length for diameter 250 mm. the connection between the pipes to be checked before
lowering to the bore hole. Rubber ‘O’ ring and trimie grease shall be provided to make the
joints watertight. The concrete shall be checked for the workability before permitting to the
site.
Low slump concrete will clog in the tremie pipe. The tremie pipe shall be removed
immediately from the bore hole on clogging of pipe and Engineer’s instruction shall be
followed for the further action.
The bentonite slurry will be delivered to the pile bore by using a combination of flexible
hoses and steel pipes, connected with couplers.
As far as possible, hoses and pipes shall be placed below surface respectively shall be
covered by a rigid protection, such as casing etc. to avoid damage due to site traffic. In case
a hose / pipe bursts it shall be replaced immediately by a proper one and the spilled bentonite
shall be removed in order to clean the area.
14
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
7.1 The reinforcing steel, concrete and electrode at site should have certificates of
approval or warranty.
7.2 Temporary Bench Mark and setting-out points of the site should be re-surveyed.
When the survey points rechecked, the error should be within the scope allowed.
7.3 Check the position of the steel casing. It should be buried correctly and stably. The
space between the casing and wall should be fully filled with clay. The deviation
between the centre of the protective pipe and centre of pile should not be more than
50mm.
The drilling bit should be checked whether it is worn when it is going to be drilling.
It should be mended in time to ensure the quality of the construction.
7.4 After the bore hole is checked & qualified, the concrete should be poured at once.
7.5 Clean the hole: during the process, the thickness of the sediment at the bottom of the
borehole and sand-in-slurry volume should be usually measured. Once they meet the
requirements, the borehole cleaning should be stopped to prevent the wall from
collapsing.
1) The prefabricated steel reinforcement cage should be checked step by step with the
focus that the main steel, stiffened reinforcement stirrup, spiral reinforcement stirrup
spacing, the length of thickness area, the building of the main steels, the welding
quality of steel crossing points and anchorage length of the prefabricated steel
reinforcement cage should accord with the design requirements.
2) Check the position of the spacer blocks of the steel reinforcement cage. Spacer
blocks should be placed evenly to not only prevent the cage from collide with the
borehole wall but also ensure that the concrete covering is even and the right position
of the cage in the pile body.
3) The lifting of the steel reinforcement cage should be at two points: The cage axes
should be coincided with each other. It should remain vertical when it is lifted into
the hole and slowly put to the hole. It should not collide with the borehole wall.
Check the reasons once it is resisted. It is prohibited to be swayed or forcefully put
down. The height of the steel reinforcement cage should accord with the design
requirements.
15
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
1) The pressure water test should be given to the tremie pipe before it is used to ensure
that it is not leaking and penetrating. It should be used after check and accepted for
approval. The connecting point of the joints should be fastened with seal ring and
buckle.
2) When the concrete is pouring, water stop plug should be put in location. The concrete
volume poured for the first time should be measured according to the borehole
diameter to ensure that the burial depth should be more than 1.3m. During the
pouring process, the concrete height should be measured when the pipe is removed
to control the number of the removed pipes so that the pipe will not be pulled out and
the concrete will not mixed with mud.
3) Check the real concrete pouring volume of each pile. The height of the pouring pile
top should be higher than that in the design, which should not be less than 0.5m to
ensure the concrete strength of the pile top.
4) During the concrete pouring process, the slump constant of the concrete should be
checked as the sample and taken from the concrete at the site.
5) Contractor shall make a record of each pile, which will be checked irregularly.
7.8 Check whether the site administrative staff is present and the special types of work,
for instance, whether the electric welder, electrician and machinist have a proficiency
certificate before they can take up the job.
7.9 The procedures of hole drilling, borehole cleaning, the fixing of the steel
reinforcement cage and concrete pouring should be considered as the focus and
supervised according to the quality control standards.
7.10 The measuring instruments at site, such as theodolite, level gauge and steel tape,
should have quality certification issued by technical supervision organizations. The
drilling machine and electric welder, etc. should have the quality certificate. Measure
whether the diameter of the drilling bit is in accordance with the requirement.
Follow the principle of “Production with Safety” and push the safety worker to pay attention
to the safety for each step of work.
16
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
Standing under the lifting arm of the crane is prohibited; walking under the lifting
bucket is not allowed and the crane shall not be operated at random.
Binding the steel bar shall be separately placed in the fabricating workshop.
All the constructors should wear the safety helmet, safety shoes and others. The
workers of special work type should wear the special protective appliance.
The electric equipment shall be connected with earth device and there must be
protection measures. The switches in the control box shall be orderly installed.
Regularly check and maintain the bolts connect the bottom of the drilling machine,
and install the safety device.
After the protective pipes are buried and the concrete is poured, the pile pit should
be protected to prevent people or objects from dropping.
It should be mended once there is any trouble. It cannot operate with any fault and
rule violation. The machinery and traffic accidents are prohibited.
The operator of the machines (or the driver) should join professional training and
acquire the operation performance of the machine. They can take up the job only
after they get the certificate approved by the professional management department.
The operators of the machine and the directors should strictly abide by technical
safety operation specification. They should concentrate to work carefully. They
should not be absent without leave and not allowed to drunk driving. The
professional electrician should take the job after he gets the certificate. The
electrician has the right to refuse to accept the work which violates the security
standards. The safety officer is entitled to stop the behaviour which violates the
security standards. The violation of directing and working is not allowed.
17
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
Consequenc
Risk Level
Likelihood
es
Consequenc
Risk Level
Activity and hazard Proposed Mitigation Measures Mitigation Control Unit
Item
(Consider the Worst Credible (What Precautions you are going to (Who is responsible for
Scenarios) implement?) doing this?)
Injuries due to not wearing All workers should wear prescribe 01 Safety Engineer
1. 04 04 16 04 04 Site Engineer
personal protective equipment. personal protective equipment. (Safety
helmet, safety shoes, gloves, high Sub-contractor’s
visibility jackets,) Supervisor
Operating heavy machine Only trained and licensed operators in Safety Engineer
2. 03 04 12 01 05 05 Site Engineer
(Crane) for lifting loads. operation. Daily Pre-Operational checks
by Operators. Sub-contractor’s
Supervisor
Equipment’s are provided with side
mirrors and reverse beepers.
Maintaining distance to excavated trench
banks and machine placing position.
Poor visibility in working area Adequate lighting shall be provided not 01 Safety Engineer
3. 03 05 15 05 05 Site Engineer
during night work less than 15 Lux. Illuminated warning
signs shall be placed. All the personal Sub-contractor’s
18
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
20
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
21
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
satisfactory
1. Slump Test
RICF +
Concrete Sampling & In accordance each batch In accordance with
07 Each Pile Concreting W H SE/F + ENG
Testing with TS 2. Cube Test 7 mix designs
record
nos. per pile
1. Level check
Relevant TS & 2. Visual In accordance with
08 Pile cut-off level Construction inspection of tolerance given in Each Pile RSCF H H Survey + ENG
Drawing concrete TS
soundness
Relevant In accordance In accordance with
09 As-built survey Construction with survey tolerance given in Each Pile RSCF W H Survey + ENG
Drawing procedure TS
10
11
12
22
China Harbour Engineering Company
Colombo Port City Development Project
Package V – Pump Stations & Storage Tanks
23
China Harbour Engineering Company
CHINA HARBOUR ENGINEERING COMPANY
REPRESENTATIVE OFFICE IN SRI LANKA
COLOMBO PORT CITY DEVELOPMENT PROJECT
INFRASTRUCTURE AND LANDSCAPE WORKS (PHASE 1)
PACKAGE V - PUMP STATIONS & STORAGE TANKS
BORED PILE EXCAVATION RECORD
AM Day:
Weather
PM Page No.:
Location: Commencement Date:
Pile No.: Completion Date:
Ground Level: Casing Length:
Casing Top Level Casing Internal Dia:
Proposed Founding Level
Excavation Level Material
Date Time Activity Remarks
Top Bottom Length Soil Sample Bentonite
Date:
Casing Length: Casing Top Level:
Socket Length
Founding Level
Proposed:
Actual Concrete Volume: m3 Actual:
ELECTRICAL BUILDING
24
China Harbour Engineering Company
POTABLE AND FIRE WATER PUMPING STATION & RESERVOIR
B
150 (TYP.) 1007
25 mm THK. EXPANSION GAP
150
P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
5000 (TYP)
500
1000 MIN. CLEAR BETWEEN PILES
P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
500 15000
150
COMPARTMENT-1
29300
(92000 x 29300)
P1 P1 P1 P1
P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
300 (TYP)
P1 P1 P1 P1
P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
-3.40
P1 P1 P1 P1 1625
5000
-1.94
500
2430
25000
A P2
1007
P1 P1 P1 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
P1
2430
ZONE 1
5000
P1 P1 P1 P1 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
COMPARTMENT-2
(92000 x 29300)
ZONE 9
150
P1 P1 P1 P1
150 2200 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
ZONE 3 ZONE 5
500
ZONE 7
29300
-1.94
P3 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
ZONE 2' C
1007
C
1007
P3 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2 P2
P3 150
150
500 92000 500
B
1007
IRRIGATION PUMPING STATION & RESERVOIR
1 2 3 4 5 6 7 8 9 10 11
3550 5200 5250 5250 5200 5200 5200 5200 5200 5225 3375
B 350
C
350 1103 1103 375
TYP.
TYP.
375
375
TYP.
TYP. TYP.
A
P1 P1 P1 P1 P2 P2 P2 P2 P2 P2 P2
5225
P1 P1
-3.10 -2.40
1675
1675
P1 P1 P2 P2 P2 P2 P2 P2 P2
B
IRRIGATION RESERVOIR
-4.10
3285
PUMPING COMPARTMENT-1
1103 P1 P1 P1 P1 P2 P2 P2 P2 P2 P2 P2 1103
D
1940
-3.10
E
1785
P1 P1 -2.40
P1
P1
F
1500
P2 P2 P2 P2 P2 P2 P2
G
350 UP
RESERVOIR
2250
TYP.
P1 P1 P1 -3.85
COMPARTMENT-2
H
TYP.
350
400
B
2975
TYP.
1103 P2 P2 P2 P2 P2 P2 P2 P2
J 150
TYP.
TYP.
375
(TYP.)
C
150
1103
E F G H J B K
A B C D 1216
(TYP)
150
150
4200
(TYP)
(TYP)
P1
150
P3 P3 P3 P1 P1
2' 150 P4 P4
1100
P4 P4 P4 P3
(TYP)
2
RCW6
A
3500
1216
P4 P4 P4 P3 P3 P3 P3
P4 P4
3
P2 P2 P2
ZONE 1
(TYP)
150
A
P4 P4 P4 P4 P4
ZONE 2 ZONE 3
7100
1216
P4 P4 P4 P4 P4 P3 P3 P3 P2 P2
P3 P2
4
4800
RCW6
P4 P4 P4 P4 P4 P3 P3 P3 P3 P2 P2 P2
5
RCW5 RCW5
(TYP)
H' J'
B
1216
150
(TYP) 150
P1 P1 350 (TYP)
(TYP)
(TYP)
150
(TYP)
350
P1 P1 P1
PC1 PC1
4550
P1
2
P1
(TYP)
350
P1 P1 P1
5020
3
A
1012 P1 P1 P1 P1 P1 P1
PC1
5660
4
P1 P1 P1
P1 P1
2500
P1
5
2000
(TYP)
350
PC1 P1 P1 P1 P1 P1
(TYP.)
350
350
(TYP) B
1012