DAMEN GREEN LINE STATION

DAMEN GREEN LINE STATION


15% DESIGN REPORT

15% DESIGN REPORT – 06.15.18


AREA DIAGRAM perkinswill.com 62
Damen Avenue Corridor Connection
DESIGN STRATEGY
Concept Diagrams

MULTI-MODEL PROJECT SITE PROVIDE INTUITIVE ENTRY INCREASE TRANSPARENCY ESTABLISH ICONOGRAPHY

Located at the southwest corner of Lake The station entry is positioned to the The transparent station entry façade will The composition & articulation of the
Street and Damen Avenue, the multi- western side of the site to c reate the heighten perceived safety and security, elevator towers at the north and south
modal project will support east and capacity for multi-modal passengers to and provide intuitive wayfinding to ease sides of the platform, passenger bridge
westbound Green Line elevated trains, intuitively navigate to and from the passenger access. The western façade is and treatment of the new girder across
the #50 Damen Avenue bus, taxis, and station. This will enable both daily and more solid a t the south and west to help Damen provide the canvas for station
private and shared bicycles to promote special event scenario passengers to maintain privacy for the adjacent identity and further enhances wayfinding
multi-modal transportation. directly navigate to their preferred mode residents. to the station.
of transit.

perkinswill.com
DESIGN STRATEGY
Programmatic Elements

perkinswill.com
Level 01 - Plaza Level 02 - Platform Level 03 - Bridge

FLOOR PLANS perkinswill.com


perkinswill.com 66
RENDERINGS – VIEW FROM EAST
perkinswill.com 77
RENDERINGS – VIEW FROM NORTHEAST
perkinswill.com 88
RENDERINGS – VIEW FROM SOUTHEAST
perkinswill.com 99
RENDERINGS – VIEW FROM SOUTHWEST
perkinswill.com 1010
RENDERINGS – INTERIOR AT ENTRY
perkinswill.com 1111
RENDERINGS – INTERIOR AT LEVEL 02 ELEVATOR
perkinswill.com 1212
RENDERINGS – INTERIOR AT LEVEL 03 BRIDGE
perkinswill.com 1313
RENDERINGS – VIEW FROM NORTH PLATFORM
perkinswill.com 1414
RENDERINGS – PLATFORM VIEW FACING WEST
perkinswill.com 1515
RENDERINGS – VIEW NORTH ON DAMEN
perkinswill.com 1616
RENDERINGS – AERIAL SOUTHEAST
perkinswill.com 1717
RENDERINGS – BUS STOP – FACING EAST
perkinswill.com 1818
RENDERINGS – BUS STOP
KEY SCHEDULE ITEMS: Damen Transfer Girders / Caissons
Next Steps Construction: Q2 2018 – Q4 2018

Advance Foundations / Micropiles / Utility Relocation


Bid: Q3 2018
Construction: Q4: 2018 – Q2 2019

Station Facilities
Bid: Q1 2019
Construction: Q2 2019 – Q4 2020