Sunteți pe pagina 1din 10

BALANCE OF WORK

Location Activity
Road 1
1 Cutting of expansion gaps
2 Asphalt installation on expansion gaps
3 Lamp posts pedestals 6 units
4 Sidewalk - Right side
5 Curb and gutters
6 Wheel Stoppers
7 Plant boxes
8 Manhole cover
9 Concrete pavement
10 Parking area at the corner of Mcdo drive thru
11 SLEX exit - left corner
Road 2
11 Cutting of expansion gaps
12 Asphalt installation on expansion gaps
13 Lamp posts pedestal - 11 units
14 Sidewalk - 2 sides
15 Curb and gutters
16 Wheel Stoppers
17 Plant boxes
18 Manhole cover
19 Concrete pavement
Road 3
20 Cutting of expansion gaps
21 Asphalt installation on expansion gaps
22 Lamp post pedestal - 12 units
23 Sidewalk
24 Curb and gutters
25 Wheel Stoppers
26 Plant boxes
27 Manhole cover
28 Concrete pavement
Road 4
29 Cutting of expansion gaps
30 Asphalt installation on expansion gaps
31 Lamp post pedestal - 1 units
32 Sidewalk
33 Curb and gutters
34 Wheel Stoppers
37 Concrete pavement
BALANCE OF WORKS
Status

Completed
Ongoing; Awaiting delivery of materials
Completed; Ready to receive Lamp posts
Shakeys side ready to receive concrete; For grading and compaciton at Mcdo side
Completed 2 sides; Mcdo drive-thru area pending
Completed 1 side; Mcdo drive-thru area pending
Completed (corner of Road 2)
Galvanization in-progress, for delivery (1 unit)
Temporary access in between Shakey's and Mcdo for concreting upon completion of all areas
Curb, gutter & sidewalk construction is in-progress
For construction, pending approval of variation order and layout

Completed
Pending upon delivery of materials; Mcdo side completed
Completed; Ready to receive Lamp posts
Completed.
Completed 2 sides
Completed with paint
Completed corner of Road 1; For construction corner of Road 3
Sidewalk manhole covers completed/ installed.
Road 3 connection pending
Completed
Pending upon delivery of materials
For construction
For construction
Interior lot side along bus parking completed; Half portion of interior lot along billboard side completed; Remaining ready to receive concrete
For construction
For material request (bricks); for construction of wall footings
Galvanization in-progress, for delivery mid-January (3 units)
For grading and compaction

Completed
Pending upon delivery of materials
For construction
Pending upon approval of Variation Order and layout
Pending upon approval of Variation Order and layout
Pending upon approval of Variation Order and layout
For re-blocking at the end of existing road near drive thru area
Estimated Time of Completion (ETC) Remarks

TBD; Dependent on delivery schedule

Friday, December 29, 2017


Friday, January 12, 2018
Friday, January 12, 2018

Monday, January 15, 2018


Tuesday, February 14, 2017
Monday, January 15, 2018
Tuesday, February 14, 2017

TBD; Dependent on delivery schedule

Thursday, December 21, 2017


Thursday, December 21, 2017

Tuesday, February 14, 2017

Monday, January 15, 2018


TBD; Dependent on delivery schedule
Tuesday, February 14, 2017
Tuesday, February 14, 2017
Tuesday, February 14, 2017
Tuesday, February 14, 2017
Tuesday, February 14, 2017
Friday, January 12, 2018
Tuesday, February 14, 2017

TBD; Dependent on delivery schedule


For construction, pending upon layout

Friday, January 12, 2018


Item Location
Road 3
1 Roadway 1
2 Roadway 2
3 Bus Parking Bay 1
4 Bus Parking Bay 2
5 Bus Parking Bay 3
6 Roadway 3
7 Roadway 4
8 Car Park Right side
BALANCE OF WORKS
Status

For final grading and compaction on bus parking bay and roadway; ongoing final grading and elevation; concreted Roadway 11/15 and bus pa
FDT passed; For site preparation 11/18;
5m width x 28m length concreted 11/17
FDT passed; For site preparation 11/18;
FDT passed; For site preparation 11/18;
FDT passed; For site preparation 11/18;
For site preparation 11/18; FDT on Monday 11/20
FDT passed; For site preparation 11/18;
Estimated Time of Completion (ETC) Remarks

Tuesday, November 21, 2017 Concreted 3.075m width x 20m length; done 70%
Saturday, November 25, 2017 Done 35%
Wednesday, November 22, 2017 5m width x 28m length concreted 11/17 DONE
Thursday, November 23, 2017 Done
Friday, November 24, 2017 DONE
Thursday, November 23, 2017 CONCRETED 75%
Friday, November 24, 2017 CONCRETED 75%
Monday, November 20, 2017 DONE

S-ar putea să vă placă și