Prepare an Approximate estimate for (G+4) R.C.C Building. Building consist
1 2. 10 M
of Six Flats on each floor and each flat has carpet area of 110 m Assume Area
occupied by wall and column as 10% of Built up area and area of circulation as
/ 2
20% of built up area. Assume cost of construction as Rs 10000 m

Item Quantity Unit


Data: Floors 5 Nos
No. of Flats 6 Nos
Carpet Area/Flat : 110 m2
Total Carpet area: (5x6x110) 3300 m2
Rate of Superstructure: 10000 Rs./ M2

Carpet Area + Horizontal Circulation Area + Vertical Circulation area


Plinth Area =
+Area Occupied by walls and columns

Horizontal Circulation Area: 15% Plinth Area


: 0.15 x P.A.
Vertical Circulation Area: 5% Plinth Area
: 0.05 x P.A.
Area occupied by walls and columns: 10% Plinth Area
0.10 x P.A.

1 PA: Carpet Area+ 0.15 x P.A. + 0.05 x P.A. + 0.10 x P.A.


0.7 PA: 3300
1 PA: 4714.286 m2

Avg. Cost of Construction of Superstructure: 4714.285714 x 10000


: 47,142,857.14 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 47,142,857.14
: 9,428,571.43 Rs/-
Cost of Construction = Cost of Construction of Sub Structure + Cost of Construction of Superstructure
Cost of Construction: 56,571,428.57 Rs/-

Add For Services


Water Supply 5% 2,828,571.43 Rs/-
Sanitation 5% 2,828,571.43 Rs/-
Electrification 9% 5,091,428.57 Rs/-
Architectural 1% 565,714.29 Rs/-
others 5% 2,828,571.43 Rs/-
Total cost for Services 14,142,857.14

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 70,714,285.71 Rs/-

Add for Contengency: 5% x 70,714,285.71


3,535,714.29 Rs/-

Work Charge Est: 10% x 70,714,285.71


7,071,428.57 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 81,321,428.57 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

4/6/14 Prepare an Approximate estimate for (G+10) Storeyed residential building to


be constructed in newly developing suburbs of Mumbai. The building
2 10 M
comprises of 5 flats per floor, each flat measuring 140 m2. Assume the Suitable
data.
2
Consider Rate of Superstructure: 8000/ M
Item Quantity Unit
Data: Floors 11 Nos
No. of Flats 5 Nos
2
Carpet Area/Flat : 140 m
2
Total Carpet area: (11x5x140) 7700 m
Rate of Superstructure: 8000 Rs./ M2

Carpet Area + Horizontal Circulation Area + Vertical Circulation area


Plinth Area =
+Area Occupied by walls and columns

Horizontal Circulation Area: 15% Plinth Area


: 0.15 x P.A.
Vertical Circulation Area: 5% Plinth Area
: 0.05 x P.A.
Area occupied by walls and columns: 10% Plinth Area
0.10 x P.A.
1 PA: Carpet Area+ 0.15 x P.A. + 0.05 x P.A. + 0.10 x P.A.
0.7 PA: 7700
1 PA: 11000 m2

Avg. Cost of Construction of Superstructure: 11000 x 8000


: 88,000,000.00 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 88,000,000.00
: 17,600,000.00 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Cost of Super Structure
Cost of Construction: 105,600,000.00 Rs/-

Add For Services


Water Supply 5% 5,280,000.00 Rs/-
Sanitation 5% 5,280,000.00 Rs/-
Electrification 9% 9,504,000.00 Rs/-
Architectural 1% 1,056,000.00 Rs/-
others 5% 5,280,000.00 Rs/-
Total cost for Services 26,400,000.00

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 132,000,000.00 Rs/-

Add for Contengency: 5% x 132,000,000.00


6,600,000.00 Rs/-

Work Charge Est: 10% x 132,000,000.00


13,200,000.00 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 151,800,000.00 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

11/12/13
Prepare an Approximate estimate for (G+1) Storeyed RCC Row house having
3 total carpet area of 90 m2./ floor. Consider cost of construction of 8M
superstructure = 7500/ m2.Assume the Suitable data.

Item Quantity Unit


Data: Floors 2 Nos
No. of Flats 1 Nos
2
Carpet Area/Flat : 90 m
2
Total Carpet area: (2x1x90) 180 m
2
Rate of Superstructure: 7500 Rs./ M

Carpet Area + Horizontal Circulation Area + Vertical Circulation area


Plinth Area =
+Area Occupied by walls and columns

Horizontal Circulation Area: 15% Plinth Area


: 0.15 x P.A.
Vertical Circulation Area: 5% Plinth Area
: 0.05 x P.A.
Area occupied by walls and columns: 10% Plinth Area
0.10 x P.A.
1 PA: Carpet Area+ 0.15 x P.A. + 0.05 x P.A. + 0.10 x P.A.
0.7 PA: 180.000
1 PA: 257.143 m2

Avg. Cost of Construction of Superstructure: 257.1428571 x 7500


: 1,928,571.43 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 1,928,571.43
: 385,714.29 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Cost of Super Structure
Total Cost of Construction: 2,314,285.71 Rs/-

Add For Services


Water Supply 5% 115,714.29 Rs/-
Sanitation 5% 115,714.29 Rs/-
Electrification 9% 208,285.71 Rs/-
Architectural 1% 23,142.86 Rs/-
others 5% 115,714.29 Rs/-
Total cost for Services 578,571.43 Rs/-

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 2,892,857.14 Rs/-

Add for Contengency: 5% x 2,892,857.14


144,642.86 Rs/-

Work Charge Est: 10% x 2,892,857.14


289,285.71 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 3,326,785.71 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

27/5/2013
Prepare an Approximate estimate for (G+3) RCC Framed residential building
4 to be constructed in Central Mumbai. The building comprises of 6 flats per 10 M
2.
floor havin carpet area 80 m Assume the Suitable data.

Consider Rate of Superstructure: 8000/ M2


Item Quantity Unit
Data: Floors 4 Nos
No. of Flats 6 Nos
2
Carpet Area/Flat : 80 m
Total Carpet area: (4x6x80) 1920 m2
Rate of Superstructure: 8000 Rs./ M2

Carpet Area + Horizontal Circulation Area + Vertical Circulation area


Plinth Area =
+Area Occupied by walls and columns

Horizontal Circulation Area: 15% Plinth Area


: 0.15 x P.A.
Vertical Circulation Area: 5% Plinth Area
: 0.05 x P.A.
Area occupied by walls and columns: 10% Plinth Area
0.10 x P.A.
1 PA: Carpet Area+ 0.15 x P.A. + 0.05 x P.A. + 0.10 x P.A.
0.7 PA: 1920
1 PA: 2742.857 m2

Avg. Cost of Construction of Superstructure: 2742.857143 x 8000


: 21,942,857.14 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 21,942,857.14
: 4,388,571.43 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Super Structure
Total Cost of Construction: 26,331,428.57 Rs/-

Add For Services


Water Supply 5% 1,316,571.43 Rs/-
Sanitation 5% 1,316,571.43 Rs/-
Electrification 9% 2,369,828.57 Rs/-
Architectural 1% 263,314.29 Rs/-
others 5% 1,316,571.43 Rs/-
Total cost for Services 6,582,857.14 Rs/-

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 32,914,285.71 Rs/-

Add for Contengency: 5% x 32,914,285.71


1,645,714.29 Rs/-

Work Charge Est: 10% x 32,914,285.71


3,291,428.57 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 37,851,428.57 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

Prepare an preliminary estimate for the student hostel (Load bearing


5 2.
Structure) with capacity of 500 Students having carpet area of 2 m / Student. 10 M
Assume the Suitable data.
2
Consider Rate of Superstructure: 6500/ M
Item Quantity Unit
Data: No of Students 500 Nos
Carpet Area/Student : 2 m2
Total Carpet area: (500x2) 1000 m2
Rate of Superstructure: 6500 Rs./ M2

Carpet Area + Horizontal Circulation Area + Vertical Circulation area


Plinth Area =
+Area Occupied by walls and columns

Horizontal Circulation Area: 15% Plinth Area


: 0.15 x P.A.
Vertical Circulation Area: 5% Plinth Area
: 0.05 x P.A.
Area occupied by walls and columns: 15% Plinth Area
0.15 x P.A.
1 PA: Carpet Area+ 0.15 x P.A. + 0.05 x P.A. + 0.15 x P.A.
0.65 PA: 1000.00
1 PA: 1538.46 m2

Avg. Cost of Construction of Superstructure: 1538.461538 x 6500


: 10,000,000.00 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 10,000,000.00
: 2,000,000.00 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Super Structure
Total Cost of Construction: 12,000,000.00 Rs/-

Add For Services


Water Supply 5% 600,000.00 Rs/-
Sanitation 5% 600,000.00 Rs/-
Electrification 9% 1,080,000.00 Rs/-
Architectural 1% 120,000.00 Rs/-
others 5% 600,000.00 Rs/-
Total cost for Services 3,000,000.00 Rs/-

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 15,000,000.00 Rs/-

Add for Contengency: 5% x 15,000,000.00


750,000.00 Rs/-

Work Charge Est: 10% x 15,000,000.00


1,500,000.00 Rs/-

Grand Total = Overall Cost + Contengencies + Work Charged Establishment


Grand Total: 17,250,000.00 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

Prepare an preliminary estimate for the School building (Load bearing


6 Structure) with capacity of 600 Students having carpet area of 1.2 m2./ 10 M
Student. Assume the Suitable data.
Consider Rate of Superstructure: 6500/ M2
Item Quantity Unit
Data: No of Students 600 Nos
2
Carpet Area/Student : 1.2 m
Total Carpet area: (600x1.2) 720 m2
2
Rate of Superstructure: 6500 Rs./ M

Carpet Area + Horizontal Circulation Area + Vertical Circulation area


Plinth Area =
+Area Occupied by walls and columns

Horizontal Circulation Area: 15% Plinth Area


: 0.15 x P.A.
Vertical Circulation Area: 5% Plinth Area
: 0.05 x P.A.
Area occupied by walls and columns: 15% Plinth Area
0.15 x P.A.
1 PA: Carpet Area+ 0.15 x P.A. + 0.05 x P.A. + 0.15 x P.A.
0.65 PA: 720.000
1 PA: 1107.692 m2

Avg. Cost of Construction of Superstructure: 1107.692308 x 6500


: 7,200,000.00 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 7,200,000.00
: 1,440,000.00 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Super Structure
Total Cost of Construction: 8,640,000.00 Rs/-

Add For Services


Water Supply 5% 432,000.00 Rs/-
Sanitation 5% 432,000.00 Rs/-
Electrification 9% 777,600.00 Rs/-
Architectural 1% 86,400.00 Rs/-
others 5% 432,000.00 Rs/-
Total cost for Services 2,160,000.00 Rs/-

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 10,800,000.00 Rs/-

Add for Contengency: 5% x 10,800,000.00


540,000.00 Rs/-

Work Charge Est: 10% x 10,800,000.00


1,080,000.00 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 12,420,000.00 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

7 Prepare an preliminary estimate for the R.C.C building with Plot Area 20m x 08 M
2
30 m. Plot has FSI of 2.5. Assume rate of construction as 7000 Rs/m .

Plot Area 20 x 30
Data: FSI 2.5
Rate of Superstructure: 7000 Rs/m2

F.S.I: Maximum Buildable area


Plot Area

2.5 : Maximum Buildable area


600

Maximum Buildable Area: 1500 m2

Avg. Cost of Construction of Superstructure: 1500 x 7000


: 10,500,000.00 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 10,500,000.00
: 2,100,000.00 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Super Structure
Total Cost of Construction: 12,600,000.00 Rs/-

Add For Services


Water Supply 5% 630,000.00 Rs/-
Sanitation 5% 630,000.00 Rs/-
Electrification 9% 1,134,000.00 Rs/-
Architectural 1% 126,000.00 Rs/-
others 5% 630,000.00 Rs/-
Total cost for Services 3,150,000.00 Rs/-

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 15,750,000.00 Rs/-

Add for Contengency: 5% x 15,750,000.00


787,500.00 Rs/-

Work Charge Est: 10% x 15,750,000.00


1,575,000.00 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 18,112,500.00 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate
Mr. Aditya Ahirwar Topic : Approximate Estimate
Quantity Survey Estimation and Valuation

Prepare an preliminary estimate for the R.C.C building with Plot Area 30m x
8 08 M
40 m. Plot has FSI of 2. Assume rate of construction as 7000 Rs/m2 .

Plot Area 30 x 40
Data: FSI 2
2
Rate of Superstructure: 7000 Rs/m

F.S.I: Maximum Buildable area


Plot Area

2: Maximum Buildable area


1200

2
Maximum Buildable Area: 2400 m

Avg. Cost of Construction of Superstructure: 2400 x 7000


: 16,800,000.00 Rs/-

Avg. Cost of Construction of Foundation: 20% x Cost of Superstructure


: 20% x 16,800,000.00
: 3,360,000.00 Rs/-
Cost of Construction : Cost of Construction of Super Structure + Super Structure
Total Cost of Construction: 20,160,000.00 Rs/-

Add For Services


Water Supply 5% 1,008,000.00 Rs/-
Sanitation 5% 1,008,000.00 Rs/-
Electrification 9% 1,814,400.00 Rs/-
Architectural 1% 201,600.00 Rs/-
others 5% 1,008,000.00 Rs/-
Total cost for Services 5,040,000.00 Rs/-

Overall cost = Cost of Construction + Cost for Services


Overall Cost of Building: 25,200,000.00 Rs/-

Add for Contengency: 5% x 25,200,000.00


1,260,000.00 Rs/-

Work Charge Est: 10% x 25,200,000.00


2,520,000.00 Rs/-
Grand Total = Overall Cost + Contengencies + Work Charged Establishment
Grand Total: 28,980,000.00 Rs/-

Mr. Aditya Ahirwar - Quantity Survey Estimation and Valuation Topic : Approximate Estimate

S-ar putea să vă placă și