Estimate for the construction of 132 KV Sonebarsa-Simri Bakhtiyarpur DCSS

Transmission Line for Simri Bakhtiyarpur GSS

1. Line length = 25 Km
2. Total number of tower = 25x7/2 = 87.5 = 88 (approx.)
3. Weight of Mild Steel and Tension Steel.
Avg. Wt. Of mild steel per tower = 3.89 MT
Avg. Wt. Of tension steel per tower = (Avg. Wt. Of mild steel + 3) MT
Total number of Tension tower needed = 3x2 = 6.
Total steel including tower and stub with nut and bolt = (3.89x88 + 6x3) = 360.32 MT.

River crossing (major/minor)-Yes, 02 nos(minor),


(1)Near Tulsiyahi
(2) Near Lagma
NH/SH,Crossing-Yes,NH-107.

Total M.S wt (65%) = 234.208 MT


Total H.T steel (kg) = 108.096 MT
Total Hexagonal nut and bolt = 18.016 MT.

4. Tower type
No. of suspension tower (70%) = 62
 No. of single suspension fitting = 56
 No. of Double suspension fitting = 6
No. of High tension tower (30%) = 26
 No. of single H.T. fitting = 22
 No. of Double H.T. fitting = 4
5. Polymer Disc insulator 70 KN
Single Suspension fitting = 56 Tower x3 = 168.
Double suspension fitting = 6 Tower x 3x2 = 36
1 % of permitted extra consumption = 2
Total no.of Polymer Disc insulator = 168 + 36 + 2 = 206.

6. Polymer Disc insulator 90 KN


Single high tension fitting = 22 Tower x3x2 = 132.
Double high tension fitting = 4 Tower x 3x2x2 = 48
1 % of permitted extra consumption = 2
Total no. of Polymer Disc insulator = 182

7. Quantity of earth wire = 25 Km


1% of permitted extra consumption= 0.25 Km
Total earth wire quantity = 25 + 0.25 = 25.25 Km
8. Quantity of ACSR Panther Conductor = 75 Km
1% of permitted extra consumption= 0.75 Km
Total earth wire quantity = 75 + 0.75 = 75.75 Km

9. calculation sheet of reinforcement

Sl. Tower type QTY. Sl. No. Tower QTY. Remarks


No. type Total = 88
1 DA+0 44 DC+0 1 Towers
DA+3 16 DC+3 3 A = 61
DA+6 01 DC+6 NIL B = 18
DA+9 NIL C = 04
2. DB+0 13 DD+0 3 D = 05
DB+3 05 DD+3 1
DB+6 NIL DD+6 1
DD+9 NIL

Calculation Sheet of Reinforcement for proposed 132 KV S/C Sonebarsa-Simri Bakhtiyarpur


DCSS Transmission

Type of Unit wt. Of No of Total wt. Of reinforcement for


tower reinforcement tower for 88 tower. Remarks
88 tower

DA+0 475.34 44 20914.96


DA+3 483.184 16 7730.944
DA+6 483.184 1 483.184
DB+0 966.54 13 12565.02
DB+3 1118.58 5 5592.9
DC+0 1154.136 1 1154.136
DC+3 1257.808 3 3773.424
DD+0 1587.488 3 4762.464
DD+3 1667.332 1 1667.332
DD+6 1667.332 1 1667.332
88 60311.7

Unit wt. Of reinforcement is taken from technically sanctioned BSPTCL Estimate no


189/TC/DOS dt. 26/11/2014 for the construction of 132 KV S/C on D/C Bikramganj-Piro
Transmission line.
Type Unit Unit volume No of Net volume Net volume of Remarks
of volume of of M3 Wet tower in M3 dry(88 M3 Wet (88
tower)
tower M3 dry for 88 tower)
tower
DA+0 55.696 11.139 44 2450.624 490.116
DA+3 59.735 10.542 16 955.76 168.672
DA+6 59.735 10.542 1 59.735 10.542
DB+0 94.25 18.849 13 1225.25 245.037
DB+3 100.489 20.097 5 502.445 100.485
DC+0 115.6 23.12 1 115.6 23.12
DC+3 121.104 24.221 3 363.312 72.663
DD+0 137.641 27.528 3 412.923 82.584
DD+3 147.456 29.491 1 147.456 29.491
DD+6 147.456 29.491 1 147.456 29.491
88 6380.561 1252.201

Total Wet type in M3 = 1252.201


Total Dry type in M3 = 6380.561

The above data has been taken from approved PGCIL Ara (PG) – jagdishpur S/C on D/C
Tower Transmission line.

10. Calculation sheet of Concreting for proposed 132 KV S/C Sonebarsa-Simri Bakhtiyarpur
DCSS Transmission.

Type of Unit Volume M3 Unit Volume No of Net volume Net volume


tower M3 tower for M20 M10
88 tower
M-20 (1:1.5:3) M-10 (1:3:6)
DA+0 6.863 0.849 44 301.972 37.356
DA+3 7.261 0.899 16 116.176 14.384
DA+6 7.261 0.899 1 7.261 0.899
DB+0 11.011 1.535 13 143.143 19.955
DB+3 11.448 1.647 5 57.24 8.235
DC+0 13.715 1.992 1 13.715 1.992
DC+3 14.409 2.022 3 43.227 6.066
DD+0 16.32 2.33 3 48.96 6.99
DD+3 17.43 2.51 1 17.43 2.51
DD+6 17.43 2.51 1 17.43 2.51
Total 766.554 100.897

Total volume of M20 (1:1.5:3) concreting for towers in M3 = 766.554


Total volume of M10 (1:3:6) concreting for towers in M3 = 84.866
Above detail has been taken from technically sanctioned BSPTCL Estimate no 189/TC/DOS
dt. 26/11/2014 for the construction of 132 KV S/C on D/C Bikramganj-Piro Transmission
line.