Sunteți pe pagina 1din 6

-

~"".,.
~..

CABLE ERECTION TEST A T PYLON SADDLE FOR


SPATIAL SUSPENSION BRIDGE

By Heungbae GiI,l Member, ASCE, an<LYopngjae Choi2

ABSTRACT: :rhis paper presents the results of mock-up cable erection tests for the Yong long Grand Bridge,
¡nchoo, Korea. The Grand Bridge iocIudes the world's firsLself-anchored spatial suspension bridge whose maio
cable planes are inclined io tbe transversedirectioo. Cable erection problems were ex~ted to occur at -the
pylon saddle and the splay band due to the self-anchored.cable system and the difference between theerection
and completed layout of the maio cable. The mock-up tests were performed prior to actual cable erection.
Through the tests, cable erection problems at the saddle, lateral displacement, and -bending of the wires inside
the saddle were identificd, and measures to deal with the problems were devised and .tested. The tested measures
were successfully implemented for the construction of the bridge.

INTRODUCTION shoe and dead load of the neighboring truss bridges. Tbe self-
anchored suspension brióge typically has limited space fer the
The Yong long Grand Bridge is located at the west coast main cable anchorage, which is located at the stiffening truss,
of Korea, and was constructed to connecNhe new international so the air -spinning method, which can contain more wires per
airport at Yong long Island, Inchon, and the mainland. The strand than the parallel wire strand method, is employed to
bridge is 4.4 km loóg and is composed of three different bridge erect the main cables.
types-asuspension bridge (550 m), a truss bridge (2,250 m), The main cables of the sl\spension bridge have 14 strands,
and ste.elbox bridges. TheGrand-Bric:1ge (Gil and Cho 1998) which are arranged in a hexagonal form at the 'pylon saddle,
has double decks; it \\1mCllrrysix highway lanes 00 the upper as shown in Fig. 2. Each strand is composed of 480 galvanized
decJe,and four highway lanes and Qual tracks of a railway on parallel wires. The diameter and tensile strength of the wires
tlie lower deck. The approach trussbri<1ges are double-deck, . are 5.1 mm and 1,570 N/mm2 (160 kgf/mm2), respectively.
Warren truss type bridges. The truss bridges are Utree-spán The pylon saddles as shown in Fig. 2 have five channels to '
cOAtinuouswith a leogth of 125 m for eaoh span. The width aouse strands, and each channel is separated by a spacer
of the truss bridge is 36.1 m. . (thickness of 12 mm). To accommodate inclined cable planes,
The main feature of the Grand Bridge is the three-span con- saddles as shown in Fig. 3 areplaced with an angle of 12.59°
tinuous self-anchored suspension bridge. The 550 m long sus- in Úle transverse direction.
pension bridge, as shown in Fig. 1, has.a main span of 300 m In the construction of the typical eartb-anch9red suspension.
and side spans of 125 m. The main cables of the suspension bridge, the stiffening truss is constrocted after the erection of
bridge take a spatial, three-dimensional shape; that is, the main the main cables and hangers (suspenders). On the contrary, the
cable planes are inclined. In the plan view, the distance be- stiffening truss of the self-anchored suspension bridge is
tweeo the main cables is changing along the bridge axis. The erected on pylons and temporary supports before the spinning
distance is shortest at the pylon saddles, andois longest at the of the main cables. In fue Grand Bridge, the stiffening truss
center of the main span and the anchorage. When compared was divided into eight blocks and erected using a 3,000 ton
to traditional suspension bridges with a vertical cable plane, floating crane. As the hangers tbat link the máin cables and
the suspension bridge with spatial cable system (Gimsing the stiffening truss are attached,the main cables of the Grand
1994) has a strong torsional stiffness but poses a cable erection Bridge wiU be transformed into a three-dimensional shape. Af-
problem. The typical earth-anchored suspension bridge has ter the attachment of the hangers, the "temporary supports for
massive concrete anchorages, which carry reactions from the the stiffening truss are removed.
main cables to foundations but take quite a lot of timt; 10build. Mock-up tests -..verecarried out to identify the expected ca-
The self-anchored suspension bridge has the main cable an- ble erection problems associated withthe spatial suspension
chorage in the stiffening gitder of the-bridge-so that the forces bridge. In addition, methods to effectively arrange the wires
from the maio cable are transfetred tothe bridge itself. The duriag cable erection at the pyion saddles and the splay bands
self-anchored suspension bridge has been rarely constructed were devised and tried. The workability at the splay bands and
due to constructional difticulties (Ochsendorf and Billington the pylon saddles will dictate the workability of the entire
1999). Konohana Bridge in Osaka, lapan, pedestrian bridges cable erection process. A real scale mock-up specimen of the
in Germany, and the recentIy proposed OakIand Bay Bridge saddle and the splay band was fabricated and used at the tests.
are a few examples of self-anchored su!!pensionbridges in the This paper presents the results of the mock-up cable erection
world.In the suspension bridge of the Grand Bridge, the hor- test at the pylon saddle. The results of the mock-up at the splay
izontal component of the cable force iscarried by the stiff- band will be presented later.
ening tnlss, and the vertical component is resisted by a link
Problem Descriptions
'Chf. Res., Inchon Aitport E¡c;prcssway Constr. Ofc., Korea Hwy.
Corp., 531--7, Kyeongseo-dong, Seo-ku, lnchon, Korea, 404-170. E-mail:
Erection problems, which -llave not been observed in typical
two-dimensional suspension bridges, are expected to arise at
h_fl@hanmai1.net
Asst. Mgr., Samsung Corp., 531-7, Kyeongseo-dong, Seo-ku, Inchon. the pylon saddle and the splay bands due to the spatial cable
Korea, 404-170. layout and the main cable anchorage. As shown in Fig. 4, the
Note. Discussion open until November 1,2001. To extend the closing main cable layout during erection is signifioantly different
date one month, a written rcquest must be filed with the ASCE.Manager from the final layout. Main cab1es in the maiR span are parallel
of Journals. The manuscript fur this paper was submitted for review and
possible publication on March 10, 2000; rcvised August 22, 2000. This
to each other in a horizontal plane during the cable spinning.
. paper is part of the Joumal o/ Bridge Engineering, Vol. 6, No. 3, Mayl phase 1 shown in Fig. 4, but those will beJ:ome parabolic,
June, 2001. CASCE, ISSN 1084-070210110003-0183-0188/$8.00 + $.50 phase 2, as the hangers are attached. So, during the cable spin-
per page. Paper No. 22205. ning, the wires .at the saddle toward the main .span will unduly
JOURNALOF BRIDGEENGINEERING/ MAY/JUNE2001/183
-
, "..
"'. ,- mM
!

~
I I I

~ . .!
~ ,"

FIG. 1.
'~
7"
Genera! View of Suspension Bridge
.,
"'.
170mm move into the side of the channel and are piled up. Thus, the
Filler arrangement of the wires at the saddle is almost impossible
unless special means ar'e devised to keep the erected wires in
position. Fig. 5 shows the disarranged wires at a mock-up i
saddle channel during the test.

Bending of Wires toward Main Span


The saddles are installed with the vertical angle of 12.59° ~
and the wires of the side spans are erected with the angle of
7.96° in a horizontal planeo As a result, the angular difference
'. between the cables of the main span and the side span is about
FlG. 2. Strand Árrangement at the Pylon Saddle
4.63°, and severe bending of the side span wires near the sad-
dIe is not expected. However, the wires of the main span are f
expected to show undue bending and localized damage, even ,
though the edges of the saddle and the vertical spacers be-
tween the strands are rounded.

Wire Coating Damage


After the completion of cable spinning, the cables in the
Cable Direction at Completed Stale
Cable Direction During Cable Spinning
main span are transversely transferred as they are linked to the
stiffening truss by hangers. During the transfer, the bottom-
FIG. 3. Inclined Saddle Placement layer wires may lose a zinc coating due to friction with the
sadd1e base.
. ADchorage

~ \
7.96' TEST SETUP ANO PROCEOURE
The mock-up te~t was performed using the full-scale model
~ r to fully understand the nature of the erection problerns. The
test setup shown in Fig. 6 is composed of a mock-up strand
shoe on the left. a tower with the mock-up saddle channel in
10.74' 9.66'

~
~
(b)
=G.:" .\1ain Cable Layout: (a) Erection State (Phase 1); (b) Con ,.
=.: ~ (Phase 2)

:-.:=:-..;
1 .:ertain degree and laterally move due to the angular
-'-~--es. During the layout change from parallel to para-
:-.::.:.:.:=iction between the saddle base and the wires is ex-
~ :o occur. Detailed descriptions of the erection problems
= ;:"~ below.
70: ::isplacements
::-ur:ng cable erection, the angular difference at the saddle
~ ~ the wires and the main span and the ones of the side
~:s about 7.96° in a horizontal planeo As discussed earlier,
~ ~ ion saddles are also installed with the angle of 12.59°
= - .~cal planeoDue to these two factors, the wires tend to FIG. 5. Disarranged Wires at the Saddle

--;;:;. .CURNAL OF BRIDGE ENGINEERING I MAY/JUNE 2001


--

Moc:k.U
Siñiid

SIDE EUW ATION

~}96'~
~
PLAN VIEW
FIG. 6. TestSetup

moc}e..uptests. The wires were looped around the mock-up


strand shoe and the ends of the wire were anchored to the
anchor plate in the anchorage. Thus, two wires were laid on
the saddle channel at<atime when one wire was erected. ¡\fter
the wire was tensioned to 441.5 N (45 kgf) corresponding to
the wire tension of the main cable during cable spinning. it
was anchored to the anchor plate using a wedge.
In the mock-up test, the degree oí lateral displacements and
bending of the wires was first evaluated' After that, altemative
'proposals to arrange the wites were devised and tried. Finally,
the loss of zinc coating due to friction was evaluated using a
uniformity test (Korean standard).
TEST RESULTS
Measurement of Wlre Displacements
Thé displacements of the first-Iayer and second-Iayer wires
at the saddle channel were measured. During the cable erec-
tion, the spinning wheel carries the wires from anchorage to
anchorage. The lower wires of the spinning wheel. which are
\.SM I.5M linked to.the strand shoe, are called dead 'Yires. while the
O.41MI I IO.47M
SIDE ELEVATlON upper wires of fue spinning wheel, which are 'unreeled from a
wire recl. are called live wires. The wires in the channel saddle
FlG. 7. Mock-up Saddle ChanneJ are arranged inlive-dead-live-dead wire groups as shown in
Fig. 8. and each group contains five wires. The numbers in
the middle, and wire anchorage on the right. The height oí.the the circle in Fig. 8 represent the erection order of the wires.
tower and the mock-up saddle, and the length .of the wires During the test. two wires, one dead wire and one live wire,
were detennined to simulate the cable layoutofthc-realbridge. werelaid in the saddle channel at a time. In the first layer. six
As shown in Fig. 6, the main cables have vertíéal angles of wires. three live wires and three dead wIres. were erected. and
41.0° and 39.00, respectively, at the pylon topoDuring the cree. the vertical and horizontal displacements were measured. After
tion of the bridge. the wites at the side spans. are sp~. with a the first-layer wires were forcefully arranged inside the saddle
horizontal angle of 7.96°. To simulate the cablC"Jayoutat'tbc!'
side spans. the mock-up strand shoes at the left of the tow.er ~Dino:IiaG
were placed with an angle of 7.96°.
In the test, only one mock-up saddle c~1 was fabricated
f.Il.IL
and used because the inclined angle of the pylon saddles and
the bend angle of all of the strands are the same. ibe. pylon
saddle for the mock-up tests has the spape of the curved chan-
nel (in a vertical plane), as shown in Fig. 7. The vertical angle
of the mock-up saddle channel can be adjusted usÍllg two tum-
bucldes. Initially. the saddle .channel was set 8112:59°. , Liw Ya I DoId WinI I Do8it.Ya I LiwY... I
Each strand is composed of 480 wires, but only 100 wires
(20 wires per layer times five layers) were erected during the FIG. 8. W'&nILayout ud Displacemeat DircctiOD

JOUANAL OF BRIDGE ENGINEERING / MAY/JUNE 2001/185


.. TABLE 2. Wire Displacement: Second Layer (mm)
c1 AlTanged

~ ~SideWall
SaddleBase
Wire
number a
Coordinate
b
Shifted Coordinate
a b
S-R-6D 51.0 7.0 23.0 12.8
FIG. 9. Wire Displacement S-R-6L 5.1 7.0 2.6 12.8

channel, two wires, one live wire and one dead wire, were
Side Wall Detail A
erected for the second layer, and the displacements of those
wires were measured. The designations of the tested wires are ~ First Layer

.::F -.r::= ~ ... \ treS


illustrated in Fig. 8. F-L-1L represents the first layer-left side-
first live wire, and S-R-6D represents the second layer-right
side-sixth dead wire.
The arranged and shifted positions of the wires were mea-
sured by fue distance from the center of the wire to the side-
sOmm 1= ~~e

~ @ DetaiIA

wall of the channel, a, and to the saddle base, b, as shown in FIG. 10. Wire Bending Test
Fig. 9. The measured coordinates (a, b) of the arranged (orig-
inal) position and shifted position are compared in Tables 1
and 2. lt shows that almost all of the wires moved horizontally Wood
to a side and some of the wires mol'ed verticaUy to the above Wedge
layers. It was concluded that the lateral displacement of the
wires was so severe that a special means would be needed to
arrange the wires ¡nside the pylon saddle.

Wlre Bendlng FIG. 11. Wood Wedge


As discussed earlier, the pylon saddles are installed inclined
to account for the spatial cable layout, while the wires of the Proposal 1- Wood Wedge Employment
main span are spun parallel to each other (two-dimensional
cable layout). This causes bending of th~ wires at the pylon The simplest way to keep the desired distance between the
sadd1e'.In the mock-up test, the actual bending angle of the wires and prevent shifting (displacements) of ihe wires would
wires was decided to determine whether this bending caused be the employment of wedges. The wedges made of wood had
any damage to the wires. The possibility of tangling with a certain width as shown in Fig. 11 and were inserted between
neighboring strands was a1soconsidered during the test. the wires. The widths of the wood wedges were changed from
The bend angle shown in Fig. 10 was measUred as 6.340 at 40.8 rom, which is equal to the distance between the first live
the end of the spacer. The spacer (sidewall in the mock-up wire and the OOt dead wire, to 10.2 mm, which is equal 10 !
saddle channel) that divides the strands does not extend to the the distance between the fourth live wire and the fourth dead
wire.
full length of the saddle, as shown in Fig. lO, and its edge
was rounded to prevent damage of the wires. Due to the The wedges initially enables the arrangement of wires by
rounded edges of the spacer and the small bending angle, the keeping the desired distance between the wires. However,
when several wires were erected and shifted together, the shift-
wires did not show severe damage.
ing force of the wires was so big that it was hard to hold the
i
i
If the distance, D, between the strand and the exterior of
the mock-up saddle channel shown in Fig. 10 is not large wedges at a fixed position and arrange the wires. Furthermore, !
the insertion of the wedges between the wires was almost im- !
enough, the strand will interfere with the neighboring strands.
The thickness of the mock-up saddle channel sidewall is 50 possible due to the lateral shifting force. Thus, it was con-
rom, while the thickness of the actual saddle spacer is 12 mm. cluded that the use of wood wedges was not an effective
Therefore, if the distance is larger than 38 mm (50 mm minus means to arrange the wires at the pylon saddle. .

( ~
12 mm), the interference will n~ happen. D was measured to
be 39 mm. It was conc1uded that the problem of interference Proposal 2- Wire Clamp
would not occur during the cable spinning at the saddle. The rectangular wire clamp shown in Fig. 12 was devised
Wire Arrangement to help the arrangement of the wires. The wire clamp was
composed oí two bal15at each end and two steel bars with an
A few proposals to arrange the wires inside the pylon saddle attached rubber pad. The upper bar can be moved up and
were devised and tried until the most feasible one was se- down, dependiog 00 the height of the erected wires. It was
lected. A detailed description of the proposals is given below. thought that the wire clamp would oot allow the horizontal

TABLE 1. Wire Displacement:First Layer (mm)


FIRST TEST SECONDTEST THIRD TEST
Arranged Shifted Arranged Shifted Arranged Shifted
Wire Coordinate Coordinate Coordinate Coordinate Coordinate Coordinate
number a b a b a b a b a b a b
F-R-ID 48.5 2.6 2.6 2.6 48.5 2.6 2.6 2.6 48.S 2.6 2.6 2.6
F-R-IL 2.6 2.6 2.6 7.7 2.6 2.6 2.6 7.7 2.6 2.6 2.6 7.7
F-L-lD 53.6 2.6 7.7 2.6 53.6 2.6 7.7 2.6
F-L-IL 99.5 2.6 12.8 2.6 99.5 2.6 28.2 2.6
F-R-2D 43.4 2.6 2.6 7.7
F-R-2L 7.7 2.6 2.6 12.8

1861 JOURNAL OF BRIDGE ENGINEERING 1MAY/JUNE 2001


..
-
BoIt
"

Wíre Formcr -
.. r Wir.

Steel
Bar .1.

. , ..
FIG. 15. Wire Fonner Location
IOSmm

FIG. 12. Wire Clamp to occur beyond the wire forroers. Fig. 14 shows arranged
wires using the wire forroer during the mock-up test. Tests
also showed fuat it could reduce the required time for fue
and vertical movement of fue wires by squeezing them be-
tween steel bars. arrangement of fue wires and the number of workers. In actual
cal:11eerection, the wire former was removed after the erection
During the mock-up tests, two wire clamps were placed at of a strand and reinstalied for the next strand.
the outside of the saddle channel. The two wire clamps were
The placement ,of the wire fonner in the loagitudinal and
opened (released) and closed in tum; that is, one wire clamp transverse direction was determined by tests. In fue transverse
was released and the wires were arranged at the desired po- direction, two locations were tried. One 10cationcorresponded
sition while the other clamp was lockedand held the wires in
to the erection state, phase 1 shown in Fig. 4, and the other
position.
corresponded to the completed state, phase 2. When the wire
The two wire clamp system tumed out to be an ineffective
forroer was placed in fue direction of the main cable's final
method to deal with the cable erection problerns. It was found
(completed) S'tate,the horizontal component of a strand force
that the clamp enabled the arrangementat the clamp; however,
was so big that fue wire fonner cOlildoot be aachored. It was
the wire clamps as well as the erected wires laterally shifted,
and this shift disturbed the wire arrangement outside the wire
decided to place fue wire forroer in the direction corresponding
to the erection state, phase 1, of the main cable, as shown in
clamps.
Fig. 15.lt reduced the horizontal force, but the arrangement
of the strand was still impossible because live wire number ¡
Proposal 3- ~VireFormer of me fust layer tended to be dislocated..'The inclined place-
The "wire forroer," which looks like a comb, is a stec;lbar ment of the saddle andthe lateral shifting force of the strand
cómbined with the rounded comers of the channel wall caused
with inserted piano wires (diameter of 1.2 rnm) and is shown
in Fig. 13. It was placed at a certain distance from the saddle the dislocation and uplift of live wire number 1 inside the
end and had 20 slots to house the wires. As explained earlier, saddle. To -hold the number 1 wire in position, a small clamp
each layer of fue strand has 20 wires. During the test, the wires was placed neat the ends of the mock-up saddle channel. This
were placed at fue specified slot of the wire forroer and 'kept dislocation phenomenon is expected to arise at strand number
in position. The wire forroer enabled the arrangement of the 4 (Fig. 2) in the real pylon saddle and will be prevented by a
similar means.
wires inside the pylon saddle by allowing wire eatanglement
The location of the wire fonner in the longitudinal direction
was decided based on two factors-the wide arrangement in-
side the saddle channel and the size of the scaffolding at the
pylon top. The wires insitte the saddle.shouldbe arranged side
llllilUill! by side without a 'gap betweenthern. However, when the wire
fonner was placed too close to the pylon saddle, the wires
ncar tbe saddle.e~ds were separated too much due !o the piano
wires df the wire forroer, and' they could not be arranged.
When it was placed too far froro the saddle, the \/viresinside
FIG. 13. Wire Former the saddle cb.annel were .easily disarranged. Tbe pylon top
scaffolding to perf0111lwork at the saddle was rather small, so
the fonner needed to be placed close to the saddle. After re-
view and tests, it was decided to place the forroers at a distance
of 350 rnm from the saddle end.

Zinc Coatlng Damage


As the main cables are linked to the stiffening girder by the
hangers, the main cables' geometry of the main span changes
from phasel (during constroction) to phase 2 (as completed),
as shown in Fig. 4. Duringthis change, the wires oear the
saddle end move laterallyas much as 25.6 rnm, and friction
is expected to occur between fue first layer of the strands and
the saddl.e base. This frictiODwould damage the zinc coating
of the wires. lB the rnock-up test, thelateral movement of the
wires was simulated and,the damage level was measured. Tbis
test was performed tbree times.
During the test, the wires in teosion were moved laterally
by rotating the mock-up saddle channel in the transverse di.
rection. The damage fey~t'of-me'zinc éoating was measured
FIG. 14. Arranged Wires Using the Wire Fonner using a uniforroity test (Korean standard) that evaluates the
JOCRNAl OF BRIDGE ENGINEERING 1MAY/JUNE 2001/187
. ~

. o~ was observed that bending of the wires was not severe and
unifonnity and quality of the zinc coating. In the unifonnity
test, the wire specimens are cleaned and then dipped three did not cause damage to the wires. Lateral displacements of
times into a standard solution of copper sulfate (temperature the wires inside the saddle channel made the arrangement of
of 115°C)oEach dip lasted 1 min and, after each dip, the spec- the wires almost impossible. After a few trials. the wire fonner
imens were rinsed in clean running water. After the final rins- that looks like a comb was devised and effectively imple-
ing and wiping, the specimens should not show any adherent mented for the wire arrangement. Tests also showed that the
red deposit of metallic copper on the base metal if there is no friction between the bottom layer of the strand and the saddle
problem with the zinc coating. The three damaged specimens base did not cause severe damage to the zinc coating of the
were subjected to the unifonnity tests and did not show any wires. The results of these mock-up tests were successful1y
red deposit until six dipso It was concluded that loss of the applied to the erection of the main cables of the Yong long
zinc coating was not severe enough to warrant additional mea- Grand Bridge, the first spatial self-anchored suspension bridge
sures to protect the zinc coating of the wires during the phase in the world.
shift of the main cables.
REFERENCES
CONCLUSION
Gil. H., and Cho. C. (1998). "Yong Jong Grand Suspension Bridge. Ko-
The cable erection problems at the pylon saddle due to a rea." Struct. Engrg. 1m.. Zurich. 8(2). 97-98.
Gimsing. N. J. (1994). "Suspended bridges with very long spans." 1m.
spatial, three-dimensional main cable layout were identified Conf on Cable-Stayed and Suspension Bridges, Association Francaise
through the mock-up tests The full-scale saddle channel was
o Pour la Construction, Deauvile. France. 489-504.
fabricated and used in the test. Lateral displacement and bend- Ochsendorf. J. A.. and Billington. D. P. (1999). "Self-anchored suspen-
ing of the wires at the pylon saddle were first evabiated. It sion bridges." Jo Bridge Engrg.. ASCE. 4(3). 151-156.

,___0'
<::
~- "o",, ",
I ;:>.:':; . .c '-' '\

t Ht:,:Ei;'~;~~:" ;:,:o.,:;,~;.:A \

1881 JOURNAL OF BRIDGE ENGINEERING 1 MAY/JUNE 2001

S-ar putea să vă placă și