2 DOCUMENT EVALUATION Report of Documents Review Report of Documenst Review Minute of Meeting H H R*
3 EXTERNAL INSPECTION
a.Visual
- Ladders,Stairways,Platforms or Walkways Client Spec./Procedure Inspection Report/ Record P V -
- Foundation and Supports, Anchors API RP 572 P V -
- Level Glass, PSV, Press. &Temp. gauges ANSI-NB23 P V -
- Shell,Head,Nozzles,Flange Connections P V -
- Coating and Insulation P V -
- Grounding Connections
b. NDT ( as required ) NDT Procedure NDT Report P V S/W
c.Settlement Measurement P V -
d. Thicknees Measurement (*) P V -
4. INTERNAL INSPECTION ( IF ANY )
'- Visual Inspection Inspection Procedure Inspection Report / Record P V -
- Corrosion Mapping P V -
- Wall thickness Measurement P V -
- NDT (as required) P V -
itp-pv-existing baru
INSPECTION AND TEST PLAN
FOR EXISTING PRESSURE VESSEL
PROJECT :
USER :
LOCATION :
PJIT :
REMARK
R : ACTUAL INSPECTION P : PROVIDE S/W : SPOT WITHESS
V : VERIFICATION AR : APPROVAL REQUIRED
H : HOLD POINT W : WITHESS
6. FINAL EVALUATION Insp. Report Documents Insp. Report Documents Minute of Meeting H H -
7. REPORT
- Final Inspection Report AR P -
- Certificate of Inspection - P R
Note :
1. Reference Document : Code, Standard, Owner Spec.
2. Verified Document : Documents to be verified
3. Acceptance Criteria : Code, Standard, Owner Spec.
4. R* : If any Mejor Finding, needs Migas approval
5. Thickness Meansurement(*): If required instead of thickness meansurement of internal inspection