Documente Academic
Documente Profesional
Documente Cultură
SR hosfjaUT*
Clause Description Page
No. No.
2.19 Conservator 32
2.20 Cooling radiators 33
2.21 Valves 33
2.22 Pressure relief device 33
2.23 Breather 34
2.24 Earthing terminal 34
2.25 Gaskets and joints 34
2.26 Rating and diagram plates 34
2.27 Disconnecting link chambers 35
2.28 Cable boxes 36
2.29 SF6 tubing 36
2.30 Buchholz protection 37
2.31 Forced air cooling fans 37
i Marshalling kiosk
2.32 38
Instruments
r 2.33
2.34 Tender analysis
38
39
2.35 Transformer Fire protection 39
2.36 Transformer tails, oil filled 800 sq.mm, single core 132kV cable 39
2.37 Forced oil cooling 40
2.38 Current transformers 41
2.39 Neutral point isolating switches 41
2.40 Transformer neutral point lightning arrestors 42
2.41 Testing 42
3. Remote control and Relay boards 43
4. Protection 45
4.1 Circuits and protection 46
4.2 300KV underground Feeder protection 47
4.3 300KV overhead line protection 48
4.4 Power Transformer protection 50
4.5 300KV busbar zone protection 52
4.6 300KV bus-coupler and bus-section 54
4.7 Circuit breaker fail protection 54
4.8 Disturbance recorders 54
( 4.9 Synchronizing 56
4.10 General notes 56
Protection Engineer 57
('1
Ufa t ©r.«,XJ
1
TECHNICAL SPECIFICATIONS
300KV SWITCHGEAR & TRANSFORMERS
1. 300KV SWITCHGEAR:
1.1 General :
The switchgear shall be of the indoor compact type, fully metal clad suitable
for installation in brick built substation. The switchgear shall be sculpture
hexafluoride (SF6 ) insulated, designed in a modular type ensuring optimum
continuity and reliability of supply as well as safety to the operating staff.
The switchgear shall be of the segregated double busbar system and the
bays are lined up in one row enabling extension in future at both ends by the
addition of extra feeders, or transformer circuits without the necessity to
dismantle any major part of the equipment (such as C.Bs., V.Ts, cable
scaling boxes..etc) and without the interruption of supply to any circuit.
< V Tenderers are requested to attach with their offers the necessary drawings
r and folly detailed description of operations and the time consumed in each
step to carry out extension of one bay, and mention the safety precautions to
be taken.
Tenderers are requested to submit with their offers the internal arcing test
reports if available, if not, the tenderers has to attach with their offer
undertaking that such tests shall be carried out in the presence of MEW
Inspector/Engineer at the fault current and duration decided later, however,
these tests may also be carried out if the available reports with the tenderers
m
are not sufficient or unsatisfactory to the Purchaser. _
ihes earned out at no price.
2
For 300KV outdoor bushings (if applicable), the impulse withstand level
shallbe 1050 KV and having a minimum creepage distance of 10.8 mt,
Regarding the SF6 gas pressure this shall be as low as possible to reduce the
effect of gas leaks and securely prevent liquifying of gas at low
temperatures.
The design gas pressure and density must incorporate a sufficient margin
Ji above the minimum admissible operating pressure and especially taking
care of unavoidable gas losses to safely operate the switchgear for at least
(
The Tenderer shall also state the maximum guaranteed leakage current and
max. guaranteed charging current of one bay. Measurement at site of these
currents shalJ,not-excged the guaranteed valugs-by-mQre than 5%.
,c
( )
‘‘ J -- (':™
3
The design and physical arrangement of the busbar sections shall allow the
easy extension at a later stage without shutting down more than one busbar
section at a time. Gas section barriers including seals to the conductor and
enclosure to the wall should be capable to withstand the maximum pressure
differential that may occur i.e. with a vacuum drawn at one side and a gas
pressure on the other side at least equal to the operating pressure of the
relief device.
Means shall be provided to indicate without the dismantle of any switchgear
component, which is the section that suffered from internal flash-over to
enable the quick inspection, replacement of the damaged parts and
accordingly increase , of reliability. Chemical method using SF6 analysis
equipments may be accepted. However, every gas analyzer equipment
should be supplied with two dozen of detecting elements. This equipment
( V should be supplied for each substation.
r The busbars enclosures shall be of the single or three phase tubular non¬
magnetic steel or aluminium sheet metal with the whole construction being
sufficiently robust and stiff to form a self-supporting structure fully resistant
against all forces imposed during normal and fault conditions. The
conductors shall be supported at adequate positions by insulators of the cast
resin type or other approved material which shall be gas tight. Busbars and
enclosures should be supplied in a straight length to cover at least one unit
span. For longer busbars or in case of multispecies assemblies, expansion
pieces shall be provided at suitable intervals to take-up the forces due
thermal expansions and contractions. All other normal standing
compression, tension, or bending forces shall be taken up by external
fittings symmetrically spaced around the bus bar enclosures.
The metal enclosure shall be bonded throughout and a sufficient number of
defined earthing points are to be provided for.
'iy
toy
4
1.5 Bus-bars and Bus-bar Enclosures:
Bus bars shall be of either copper or aluminum tubes with diameter and
shape to prevent corona formation at any point under the worst operating
conditions. If copper busbars are provided these shall be of the high
conductivity electrolytic copper in accordance with B.S.S. 159 or at least
equivalent.
If material other than copper used for connections, these will be stated
clearly in the schedule of guarantees.
For main busbar connection, tulip type construction is preferred so that easy
and automatic connection obtained with the least difficulties in assembly
and erection. Design will compensate for errors in busbar dimensions as
well as expansion and contraction of the busbars, respectively branch
connections, due to temperature variations.
fpsr issr
5
iv) The gas density relays shall be of the three stage type alarm,
trip/inter-trip follows by lock-out and shall be arranged as follows:
i In the latter case, the successful tenderer will be required to carry out (or produce)
complete short circuit tests for the five duties, short time current, breaking of low
inductive currents, short line breaking, capacitive current, and any other test that
the Purchaser may find necessary to be carried out. The type test programme for
the various ratings shall be submitted well in advance to MEW for approval. The
tests will be carried out in accordance with BSS.162 or IEC56 at an
internationally recognized testing authority before dispatch of the first
consignment of the circuit breaker, such tests will be witnessed by the Purchaser’s
representatives and the Contractor shall offer all facilities and bear all cost arising
therefore. If the circuit breakers fail to pass the type test, the contractor shall
provide 300KV switchgear approved by MEW at no extra cost to the contract
price and any delay in completion of the substation that arise from shall be
penalized in accordance with the respective terms in the general conditions of the
contract.
-Aa Ul L~,y "N.
®r.0ÿJ
7
Further, tenderers should submit a type test certificate for inductive and
capacitive currents which the circuit breakers can interrupt. The circuit
breaker shall be capable of making and breaking capacitive currents not less
than 300 Amps.
Means shall be provided to allow easy access to the contracts for periodical
inspection and repair. Also special devices should be provided for filling
and re-pumping the gas into the gas receiver.
Also, oil pressure for smooth and definite operation should continuously be
checked through mano-meters mounted on the operating cubicle. A locking
device shall be provided so that in case of oil pressure drop it will lock-out
and give local and remote alarm signal.
Descriptive literature with full details of main features, and showing general
arrangement of the breakers should accompany the tender.
Means shall be provided for the manual operation of the circuit breakers for
maintenance purposes. All manually operating gear shall be so designed to
close or open the breaker by one movement. The drive mechanism can be
either charged spring, hydraulic or pneumatic type.
The driving system shall be designed to ensure and smooth operation of all
three phases but shall likewise permit singlepele-as*well as three-pole auto
re-closutÿgÿX -
8
Each circuit breaker shall be equipped with two shunt trip coils which shall
be electrically and mechanically independent from each other. Electrically (
closing devices shall operate satisfactorily between 80 percent below and
r 20% normal D.C. voltage with coils at 52°C.
For tripping the minimum operating voltage shall be 60%. The pulse
duration for operation (closing or tripping) shall be 50 m.s. minimum.
It should be noted that all the S/Stns, in Kuwait are un-attended type and are
controlled and supervised by National Control Centre. It is therefore
necessary that all relays and switches associated with the low tension A.C.
supply for drive mechanism (hydraulic, pneumatic or spring charge motors)
should re-set automatically as soon as A/C supply is restored after its failure
due to any reason. It should not be necessary to send engineers to each
Substation to re-set these relays manually.
\V\
9
1.6 Circuit Breakers: Cont’d
An emergency, mechanically actuated opening device shall be provided
mounted on the local operating cubicle.
1.7 ISOLATORS:
300KV isolators shall be of the sliding coaxial type, isolating switches shall
be so installed as to permit maintenance of any section of the equipment and
the switchgear plant when the reminder is alive. When the 300K.V circuit
breakers operating mechanism is of the hydraulic or pneumatic type, the
isolators operating mechanism can be of similar type.
C The gap between terminals of the same pole with the isolator in open
position shall be long enough to withstand a minimum impulse wave of 115
percent of the specified impulse rating to earth, or the initial discharge is
above the (BEL) breakdown insulation level.
Isolating switches shall be rated as specified in the schedule, and shall be
designed for live and off-load operation. Main contacts shall be of the high
pressure line type and shall be suitably screened to attain maximum
uniformity of electric field.
The short time current rating and mechanical construction must be such as
to withstand the thermal stresses and electromagnetic forces imposed to the
isolators during through fault conditions.
(.
The contacts of the isolators shall carry their rated loads without ever
heating or welding and shall be of such a design that would not call for
more frequent maintenance than one in five years.
The isolators shall be electrically interlocked with their respective breakers,
such that the isolators cannot be opened unless the associated breaker is
opened and the breaker cannot be closed unless the associated isolators are
in definite position, i.e. fully closed or fully open.
Operating mechanism of the isolators shall be of robust construction and
shall be capable of free operation unaffected by the climatic conditions at
site. The mechanism shall be complete with auxiliary switches, terminal
box and cable glands and the same shall be housed in weather- proof
m
enclosure
SK
c°frrxACTS*1
10
Provision shall be made for the remote indication of isolator in open and
closed positions on the 300KV control board and also at the Supervisory
Centre.
The isolators shall be motor operated and shall be electrically controlled
from the local control cubicle as well as remotely from the control hoard in
the control room. Also provision shall be made for local hand operation for
emergency cases, by means of a removable crank with the necessary
interlock provided betweenboth ways.
(a) Earthing switches shall be provided for each outgoing (O/H or U/G and
incoming circuit transformer). Positive means of interlocking between the
earthing switches of line and transformer isolators shall be provided.
(b) Busbar earthing switches shall also be provided, and for each B/B Section
r located in the bus-section or bus-coupler bays. These shall be fully
interlocked so that any busbar earthing switch cannot be closed unless all the
corresponding busbar selector isolators are in the open position.
(c) Earthing switches shall also be provided for earthing the 300KV cables of
transformers. These switches shall be interlocked with both the 300KV and
132KV isolators of the corresponding transformers.
(d) Each 300KV circuit breaker shall be provided with two earthing switches one
on each side of the circuit breaker, to permit maintenance of the circuit
breakers with the busbar alive. These isolators shall be fully mechanically
and/or electrically interlocked with the corresponding line isolator, busbar
selector isolators and circuit breaker.
The busbar, overhead lines, cables and transformers earthing switches shall be
capable of closing on full short circuit making current of 157 KA peak without
suffering from any damage due to thermal stress or electromagnetic forces and
without endangering operator. All tenderers shall confirm this in their offers
and shall submit evidence of tests carried out on the earthing switches for this
c purpose.
For circuit breaker earthing switches, these shall be suitable for a short time
current of 63KA for 3 seconds but not of the fast acting type.
x
11
The earthing switches for feeders (underground and O/H line circuits) shall
be additionally interlocked with the secondary voltage from voltage
transformers while the m.c.b. is in closed position and the 300KV V.T.
primary side isolator is closed so that these earthing switches cannot be
closed unless the corresponding feeder is de-energized. However, position
indication shall be provided locally on the local panel and remotely on the
300KV control board.
Circuit Breakers, isolators and earthing switches shall include all necessary
auxiliary switches, contactors and mechanism for remote indication,
protection, control, interlocking and such other services as specified. Not
less than four spare auxiliary contacts (two normally closed and two
normally open positions), shall be provided with each of the above
( ! switchgear apparatus. All auxiliary switches should be wired up to a
suitable terminal board in the operating mechanism cubicles.
r
The contacts for all auxiliary switches shall be strong and shall have a
positive wiping action while closing and shall be suitable for service under
climatic conditions specified. All auxiliary switches for use with the
Purchaser’s remote supervisory and control system shall be non-fleeting and
clean (potential free), or withholding time not less than 25 ms.
The current transformers shall be of the torridal core type. The ring and
secondary windings shall be embedded in cast resin or otherwise as
approved by MEW and installed in the earthed part of the circuit breaker
compartment where SF6 gas will form the insulation medium. Different
locations and arrangements shall be subject to the Purchaser’s approval.
Protective and instrument C.T.’s shall be in conformity with B.S. 3930 and
( 5 of suitable ratings for the protective scheme specified. Instrument current
transformers shall be Class “I” accuracy.
___
The current transformers primary conductor shall be capable of
withstanding short circuit ratings of the associated circuit breaker.
Secondary windings of the current transformers shall be a rated for 1A. For
metering current transfonners, secondary can be rated either 1 of 5 Amps to
suit the measuring transducers for remote metering at Supervisory Centre.
C.T’s shall be able to carry current 25% in excess of the rated current
continuously without injurious heating and the C.T.’s for protective purpose
shall have over current saturation factor not less than these obtained at the
design short circuit level of the system.
Since the C.T. forms a part of the composite single phase unit, means shall
be provided for easy changing in case of damage.
1.11 Voltage Transformers:
300KV voltage transformers shall be in sets of three single phase units.
The windings shall be embedded in cast resin otherwise as approved by the
Purchaser and encapsulated in SF6 gas filled enclosures.
For high voltage testing of cables from the remote end of the cable or
overhead line, an isolator shall be provided on the primary side of the
voltage transformer or any other arrangement so that this test can be carried
out without the necessity of removing any component of the switchgear
such as V.T’s, cable boxes, etc. Where such an isolator is provided, it shall
be operated manually, however, shall be interlocked with the line earthing
switch and shall have semaphore indications on the local panel. Protective
, J) voltage transformers shall have miniature circuit breakers in their (
secondary's, with auxiliary contacts to indicate V.T.’s secondary failure on
r the control board. Further, auxiliary clean (potential free) contacts shall be
provided for remote supervisory system. Voltage transformers supplied
under this contract shall be of robust construction and shall comply with
B.S.S. 3941 or at least equivalent to it. The voltage transformers shall be of
Class 3P and 150VA burden for each of Star and Delta Windings.
Two separate territory windings shall be provided in the V.T.’s for double
distance protection of the overhead line feeder circuits.
(a
13
The cable end sealing boxes shall be provided complete with cast resin
cones, flanges, clamps, packing material for gas, fixing bolts, and toher
fittings necessary including proper sized glands to suit cable sizes and any
other accessories shall be supplied under this contract and its cost shall be
included in the contract price.
For oil monitoring, the contact pressure switches, auxiliary oil piping with
intermediate insulating coupling, all be supplied and installed under 300KV
cable contract. However, the necessary control cabling wiring between the
300KV marshalling cabinet, (where alarm and trip signals are provided
from intermediate 300KV stop joints) and contact pressure gauges in the
Substation building or located in the oil tank pit both to the alarm/trip
auxiliary relay in the control panel is included in this tender.
These cables boxes should meet the requirements of the cable manufacturer
( V at no extra cost. Jointing materials such as oil, tapes..etc., will be supplied
by the cable contractor (when cables are supplied under separate contract)
r who will carry out the cable jointing. The contractor should fully co-operate
with the cable contractor.
Any material and/or accessories for complete jointing of all the 300KV to
the 300KV switchgears shall meet the requirements of the cable
manufacturer and the same together with any accessories or material that are
deemed necessary to be obtained from the cable manufacturers, shall be
supplied and included in the Tender Price.
1.13 300KV Cable End Sealing Boxes: contd
Suitable cover plates are to be provided as part of the switchgear for bolting
over and sealing each aperture to enable the switchgear to be completely
filled with SF6 gas, tested and operated even when a cable sealing and is not
fitted.
Tenderers are requested to indicate in their offers methods adopted to
compensate for the expansion and contraction of the Cable conductor.
At a suitable position between the cable box and the adjacent switchgear
component, a fully insulated testing jack is to be provided with a plug in
contact and a cover plate shall enable the insertion and fixation of a portable
H.V. testing bushing having a compatible system.
The same test jack is likewise to be provided at every bus-bar section which
can be isolated by means of the bus-bar section circuit breaker.
The physical location of the test jacks shall be such as to obtain sufficient
clearance between the air insulated end of the test bushing and the
surrounding walls, ceilings and metal structures being at least minimum
permissible striking distance for the pertinent voltage class.
The portable test bushing shall be of a resonable weight and designed for
outdoor use and stored in a suitable container. _
& f Ah \
A,
14
One sheet steel cabinet shall be provided in the 3O0KV switchgear room to
receive the 34-core pilot cables associated with the 300KV cables.
The cabinet shall be suitable for floor mounting with double lead lift-off
doors and reasonably dust, damp and vermin proof. 34-core terminal
blocks, three per feeder circuit including future feeder circuits shall be
provided inside the cabinet and arranged to receive the multi-insulated
bridging plugs. The plug shall be either color coded or numbered to
facilitate easy identification, and in this case arrangements shall be provided
to ensure continuity of solkor and inter-trip cores. Two additional 34-way
terminal blocks shall be provided for substation services and arranged to
permit routing of circuits selectively through pilot cables.
Provision shall be made for bottom entry of pilot cables and suitable brass
( gland of the compression type shall be provided. Similarly, suitable entries
shall be provided for control cable terminations from the switchgear, control
c board and other apparatus within the substation. Each terminal block shall
be clearly labeled,
All control cables and connections between marshalling cabinet and
substation equipment including oil tank pits are included in this contract.
For the outgoing circuits four cores control cable for each circuit should be
provided for oil tank pit, each cable about 60M long.
a) Solkor ‘R* Pilot Supendsion Equipment:
It is required to provide a D.C. system for Pilot Cable Supervision
with sending equipment at near end and receiving equipment at far
end to ensure that the pilot cable is healthy. It shall be continuously
monitored in order to bring up an alarm immediately when the cable
is damaged. An alarm will appear locally and remotely when the
D.C. system is interrupted on the cable is damaged. Also for
auxiliary supply used for this system, a Supervision relay will be
provided.
>i Pilot fault and supervision supply failure alarms shall be transmitted
to supervisory control centre. Necessary annunciators shall be
provided in the control room which shall be subject to the approval
of the Engineer.
The tender price shall include the cost of installing, testing and
commissioning these, relays at both ends including modification at
the remote end (if required) without any extra cost to the Purchaser.
Ai C
A ©r.,A,J
16
On the other hand the terminal blocks in the M/C, control cabling to
control room and inter-tripping relays for the far end substation
(where applicable ) shall be insulated for at least 15 KV.
The cost of supply and erection of the above shall be included in the
tender price, however, the arrangement shall be subject to the
Purchaser’s approval.
P 1.17 Overhead Line Take-off Gantries (if specified):
Take-off gantries to be provided for each double circuit O/H line. The
r gantry
shall consist of three columns, one horizontal girder extending over two
spans complete with three pinnacles to receive three overhead line
conductors. The gantry shall be of the steel lattice type made of hot-dipped
galvanized steel structures, and shall be complete with the necessary U-
shape steel devices for hooking the slack span insulator fittings, the design,
construction and arrangement shall meet the latest standard and shall be
subject to MEW approval.
The transmission line terminal tower shall be at a distance of up to 100 mt.
And the maximum tensile strength in the slack span of the line conductors,
2500 kg. Per conductor per phase (four conductors each of 427.7/55.6
sq.mm. A.C.S.R Zebra per phase) and that of each earth wire is 600 kg (50
sq.mm. - 19/2.36mm of each earth wire).
The clear phase - phase clearance shall be 4.5M minimum and phase to
>') earthed parts 2.75 mts. The gantry must be designed for a horizontal
...
(
deviation of the conductors of maximum ±30 °C and vertical of 1:4. The
c gantry shall be complete with the necessary tension insulators complete with
fittings, tension clamps, bimetallic clamps, jumper and dropper connections
...
arcing horns and rings etc., if these are specified in details of Equipment
Vol. m.
The gantries shall be designed for the above acting forces including wind
pressure, two erectors with tools etc. However, the following have to
be noted:-
Minimum height of live parts above yard level = 8 M.
Width of 4 - bundle conductor arrangement : 0.4 mtr.
The height of the bottom of the horizontal girder of gantry : 13 M
Min. wind pressure of gantry as 125 Kgm/sq.m.
iW ©r.„X-,
Vv
£
17
A wave trap of 1200 kg. Shall be suspended from the centre point at the
bottom of the beam, unless otherwise decided by MEW.
The contractor shall submit detailed calculation sheets based on the above
loads and under the worst temperature conditions and wind forces, this will
be submitted together with detailed construction drawings, views showing
arrangement and clearances, material list with dimensions and weights of
each member for approval by the Purchaser before start of manufacture.
The gantry shall be complete with insulators and arcing horns.
a) Three high voltage testing bushings. Suitable for direct current H.V.
site testing of 300KV power cables connected to the switchgear.
g) Special device for detecting and locating any SF6 gas leaks.
h) SF6 gas handling unit for extracting and pumping in SF6 gas
( *
'
complete with compressors, storage tanks, gauges, piping, vacuum
pumps..etc.
(
i) Compressed SF6 bottles sufficient for one cable feeder circuit and
one transformer circuit of the switchgear.
4s
19
a) Routine Tests:
( i> i) Operational tests for circuit breakers and isolators (as per BSS 166,
862 and 3078).
c ii) Millivolt drop test across the circuit breaker and isolator contacts
and between terminals.
iii) Power frequency high voltage test in accordance with BSS 5311,
862, 162, 861 and 3078 as applicable. This test will be applied on
the main H.V. circuits and auxiliary L.V. circuits.
iv) Partial discharge test to all insulated components upto 1.2 x rated
voltage.
v) Megger test for all auxiliary L.V. circuits.
vi) The dry power frequency spark-over test and standard lighting
voltage impulse spark-over tests will be carried out on the supplied
surge arrestors.
ii) Temperature rise test in accordance with BSS 5311 862, 861 and
3078 as applicable. This test shall be carried out on different
circuits comprising the main H.V. components i.e. main bus bars,
bus-section and/or bus-coupler circuit C.B., C.T’s and isolators,
feeder circuit C.B., C.T’s and isolators and transformer circuit
C.B., C.T’s and isolators in addition to the connection components
between bus bars and the rest of each bay apparatus.
iii) Short circuit test, short time current test, capacitive load and
inductive making and breaking test, power frequency test...etc.,
as described earlier, however , these tests cover the switchgear
components as applicable?
$
lv
Sfift
20
iv) For measuring and protection transformers, the determination of
accuracy class and displacement angle shall be carried out on
each unit with determination a knee point voltage and other data
suitable for the purpose.
v) The impulse voltage test will be carried out on a complete assembly
plants or parts thereof.
vi) One single phase of the surge arrestors will be tested as follows:
- Wet power frequency spark over test.
- Front of wave impulse spark over test.
- Switching surge spark over test.
- Residual voltage test.
- High current impulse test.
- Long duration impulse test
- Operating duty test.
- Pressure relief test with at least 77% rated voltage
(
N.B.: Type test certificates of similar arrestors with rated seal off
( voltage 90 to 110% of the test specimen will also be accepted.
1.21.2 Site Tests:
Provisions for testing at site the 300KV switchgear and the 300KV power
cables connected to it shall be provided and details of these shall be clearly
shown up on the drawings. The tests shall be carried out on site as detailed
in Part I.
The site high voltage testing on the 300KV switchgear shall comprise of the
following:-
s
21
iv) Secondary injection testing set, for relay check testing, and complete
with suitable timing device.
v) Earth resistance Meggar Tester.
vi) Any other necessary testing equipment and instruments.
The Contractors test Engineer shall cany out all commissioning tests in
cooperation with and to the satisfaction of the Purchaser’s Engineer who will take
part in all these tests.
1.22 License:
Equipment or parts thereof manufactured under license shall not be
included in the equipment covered by this specification.
N.B.: Tenderers are requested to attach with their offers, the following:-
rÿ
XavfRAc.ÿ
22
1.23.2.2 Conductor:
The conductor shall be formed from segmental copper strips or wires into
a compacted annular Milliken construction of cross-sectional area of 1600
sq.mm. The conductor shall incorporate a central oil duct of minimum
diameter 12 mm.
1.23.2.3 Conductor Screen:
The conductor screen shall consist of semi-conducting carbon paper tapes.
1.23.2.4 Insulation:
The insulation shall be designed to meet an impulse voltage level of 1425
KV peak and highest system voltage of 420KV. The insulation thickness
shall be not less than 15.3 mm.
1.23.2.5 Core Screen:
The core screen shall consist of semi-conducting carbon papers in
conjunction with a metalized paper tape. A copper woven fabric tape
shall be applied overall to give additional mechanical protection.
1.23.2.6 Sheathing:
(
The cable shall be sheathed with lead alloy 'AC material conforming to BS
r 801 or tellurium alloyed lead (kb-pb-Te 0.04) conforming to DIN 17640.
The minimum average thickness of the lead sheath shall be not less than
3.8 mm and the minimum thickness at any point shall be not less than
3.5mm. Tenderers shall confirm that their proposed lead sheath
construction is satisfactory for carrying in an earth fault current of 3 1.5
KA for 1 second and quote the temperature rise. The quality of extrusion
of the pressure retaining sheath shall be of the highest order so as to
exclude the possibility of any weakness. Aluminum sheathed cables will
not be accepted.
1.23.2.7 Serving and Bedding:
The following layers shall be over the lead alloy sheath.
1. Coating of waterproof insulation compound and suitable bedding.
2. Non-magnetic reinforcement which shall consist of two layers of 1% tin
bronze or stainless steel or hard copper tapes.
3. Outer serving of extruded black PVC sheath. The minimum average
hi thickness of this sheath shall be not less than 3.6 mm and the minimum
thickness at any point shall be not less than 2.96 mm. The PVC shall (
conform to BSS. 6746 and shall fulfill the test requirements for PVC-type
9 of Table 3 ofBSS 6746 as a minimum and shall be suitable for site
conditions stated under clause 3.4. The PVC sheath shall be embossed
with voltage designation (300KV) and the manufacturer's name and in the
same manner described in BSS: 6480 and ESI 09-5.
4. Grafite coating.
2. Power Transformers:
2.1 Rated design conditions and Data:
The mechanical and electrical design of the transformers and their accessories shall
strictly follow the IEC recommendations 76, 123, 137, 214 and shall be based on
the conditions and requirements:-
1) The ambient air temperature may rise in the transformer rooms up to 55°C .
However, the temperature rise of oil and winding shall not exceed 40°C and
50°C respectively, while the transformers are working under full load
conditions and with the tap-changer set on the extreme position but the
auxiliary means for cooling i.e. cooling blowers and oil pumps are running
with 80% of the full capacity.
2) The HV neutral point of the power transformers shall be protected by means
y of surge arrestors and connected to the grounding network in parallel with
r motor operated disconnecting switches. The LV neutral to be connected
c direct to earth with bolted links only.
3) The windings shall have the following insulation strengths:-
4) The transformers shall be of the outdoor type but installed in separate rooms of
adequate dimensions and with the front side provided with aluminum
decorative grill and the roof is made of steel and aluminum sections to form
with opening areas sufficient for ventilatjorrjrpcesÿ
24
5) Tenderers are requested to offer their proposal for provision to the transformers
with wheels and rails on the foundation plinths for mounting the transformer in
the room or withdrawal out for repair purpose. However, it is left to the choice
of the tenderers to offer their proposals but supported with sufficient and
detailed drawing and description of the method adopted for this work. MEW
reserves the right to change to any other method if MEW finds the tenderers
proposal not sound, whether during tender analysis or after contract but before
approval, however, this will not entitle the Contractor to any extra charges.
2.2 Type:
The transformer shall be of the three phase, three winding, core or shell, oil
immersed type suitable for outdoor installation and operating under the
climatic conditions referred to in Vol. I, clause 1.4. The two secondary
)> windings shall be. one star connected and the second shall be delta winding
for dual purpose i.e. for feeding a constant load of 45 MVAR shunt reactor . f
r Compensation for third harmonic current content, and shall be capable to
withstand the stresses arising from circulating current in this winding which
results from maximum short circuit current.
The transformers shall strictly comply with the I.E.C Standard unless
otherwise stated in this specification.
The transformer maximum continuous rating with 80% of cooling capacity shall
be based on the following simultaneous load combination (i.e. 80% of blowers
and 80% of Pumps running):-
•V a) The 132KV secondary winding shall have a maximum continuous {
load is 300MW at 0.95 lagging power factor.
S'Jj
-Jrm %’ÿ
rS
£
C°H >
25
If any transformers exceeds the above temperature rise limits on test it may
be rejected. All tenderers shall state in the schedule the equivalent B.S.S
continuous maximum rating for the transfonners offered.
The high voltage winding shall have tappings, arranged to give variations of
transformation ratio in steps, as specified in the Details of Equipment.
However, these tappings shall be arranged in the neutral point of the
V primary H.V. Winding.
(
/ 2.6 Impedance Voltage and Regulations:
With the transformer fully loaded the noise level at 3 meters distance shall
not under any circumstances exceed 80 db. Cladding of transformer room
walls with suitable material can be adopted to meet the above requirements.
(
2.9 Duty under Fault Conditions:
f
All the transformers shall be capable of withstanding without damage or
distress an external fault between phases for three (3) seconds with the
voltage on other side of the transformer maintained at its full normal rated
value. The delta winding shall be designed for the same condition.
However, the manufacture of these transformers should not be started prior
to the submission of the design calculations, which will be checked and
approved by the Purchaser.
c
7 ( $£& j
A <
27
2.14 Windings:
The designed maximum current density in the windings of the transformers
shall not exceed 3.4 amperes per sq.mm, at continuous maximum rating of
the transformer with normal voltage and frequency. This current density
also referred to 80% running of the blowers and oil pumps.
2.15 Core
The core shall be constmcted of the laminations of best quality low loss,
cold rolled, grain oriented silicon steel from burrs.
The flux density in any part of the core shall not exceed 19000 lines per net
square centimeter at normal frequency but a feeder voltage of 1.00 times
(
rated voltage and with higher harmonics are suppressed to the maximum
extent.
The core shall be provided with an ample number of cooling channels in
order to ensure its proper circulation of oil and efficient cooling.
All core plates shall be insulated from one another to reduce the core loss to
a minimum and the core shall be held together by bolts and clamping plates
to keep the magnetic noise at a minimum level. All bolts and clamps shall
be adequately insulated. The completed core shall be provided with lifting
eyes to facilitate its removal from transformers.
All steel sections used for supporting the core are to be thoroughly sand
blasted after cutting, drilling and welding. Design of supporting frame shall
take into consideration complete emptying of tank through a drain valve, the
avoidance of movement of the core relative to the tank during transport,
installation and operation.
Details of earthjng:of~the inactive part and screepingmf the core if applied to
2.16 Insulation:
All insulation of the transformers shall be class A in accordance with BSS
2757 (except where another class is specified). The windings shall be
insulated with best quality paper and treated to prevent the formation of acid
in the insulating oil. The transformers will be connected to a system which
is earthed as follows:
Over voltage can occur due to exposure of the system to lightening and
switching surges. The neutral shall be insulated for system phase voltage.
The oil in the chamber housing the tap changer selector switch may be in
i: communication with the oil in the main transformer tank, but the tap change
circuit making and breaking switch shall be accommodated in three separate
oil filled chambers separated from the main transformer tank. The duty
rating of the switches shall have a continuous maximum rating of the
transformer and shall give trouble- free operation under Kuwait conditions.
Limiting devices shall be provided to limit the operation of switches to the
range of tapping specified.
The tap-changer shall be of the fast resistor type and shall be continuously
rated for operation under Kuwait conditions.
The equipment shall be designed to ensure that, when a tap change has
commenced it shall be completed independently of the operating of the
control relays or switches. In the event of failure of auxiliary electrical
supply during a tap change or any other contingency, which would result in
the tap change not being completed, approved means sJÿalTbeÿprovided to
mk 0-80*90
vCo'VWAcnÿ v
29
1) The land gear operation of mechanism shall be interlocked to prevent the electrical
motor drive operation while to hand gear is in use.
3) Operation from any control switch shall cause one tap movement only unless the
control switch is returned to the off position betweensuccessive operations.
4) All electrical control switches and hand operating gear shall be clearly labelled to
indicate the direction of tap change.
( V 5) The local control switches and other apparatus shall be mounted inside the
( marshalling kiosks.
6) A mechanical tap position indicator shall be fitted on the transformer and shall be
visible from ground level. A device for registering the total number of tap change
operations and a hand reset register device for counting tap change operation
between periods of maintenance shall be fitted.
7) A remote indicating device shall be provided for installation in the control room.
The device shall indicate the tap positions and shall be scaled 1-21.
8) The tap change drive mechanism shall be provided with a separate contact row with
21 positions for remote supervisory indications. The contacts shall be potential free
and wired to the telemetry cabinet without the insertion of tap-position transducer or
resistance box, since the tap position are required to hs-steÿIedto the National
Control Centre as indigdUhnÿtodhrof as mpacnrpmPMt s $ t ...
si
30
The sensitivity of the relay shall be adjustable between ± 0.5% and ±3% either
variable or in steps.
10) In the event of the transformers forming a group and operating in parallel getting out
0 of step due to faulty tap change operation, a device shall be connected in the control
(
system to make in operative the automatic TAP CHANGE. This device shall send
(
on alarm to indicate the condition electrically at the control room. The device shall
be of the hand reset type.
The device should also be provided with additional clean set of auxiliary contacts
(Potential free) and wired to suitable terminal blocks in the control panel or tap
change control desk for use as an alarm to the “REMOTE SUPERVISORY AND
CONTROL CENTRE” of the Purchaser’s system.
12) Step-by-step description of operating sequence should be given for all automatic
tap-change control with the aid of a comprehensive schematic drawing.
13) A warning lamp and buzzar should be connected to the control system to indicate
V that tap-changing is in progress.
(
( 14) Tap-changing will be transmitted to the “Remote Supervisory and Control Centre”
of the Purchaser for “Data Logging Purposes”. This applies when transformers are
set on manual and either on individual or master in case of parallel with other
transformers. Details shall be subject to the Purchaser’s approval. All necessary
wiring for the above should be brought to a suitable terminal blocks in the control
panel.
15) The tap change driving mechanism shall be fully rated for the worst temperature
conditions in Kuwait. The summer sun temperature causes heating of surfaces
exposed to the direct-sun-shine as follows:-
A #5ÿ
31
Assume a cube with surfaces on the top, north, south, east and west sides:-
Top side maximum average temperature 70°C
All motors, contactors clutches and breaks shall be designed to give trouble free
operation and shall be of robust construction to prevent distortion due to
variations in temperatures that can occur in Kuwait during the year. The
contractors shall have silver plated contacts and where necessary shall be of the
V self-wiping type. The current carrying capacity shall be derated to 80% for
t Kuwait. All equipment and apparatus shall comply with the latest relevant
B.S.S. Tenderers shall state the B.S.S and Kuwait Ratings in their offers.
Similarly cables shall be derated to 70% of the B.S.S. Rating. to get size 2.5 mm the cable
must more 3.6
2.18 Main Tank:
The main tank shall be designed to house the transformer cores and windings and
arranged to prevent any movement of the core structure inside the tank.
Provision shall be made to enable the core to be lifted out with case for
maintenance and inspection (i.e. Bell type tank construction will not be accepted).
The tank shall be of heavy mild steel plate construction of adequate dimensions
braced and reinforced where necessary to prevent any distortion due to
transportation lifting, internal pressures, and temperature variations.
The top of tank shall have provisions to give access to terminations of windings,
( earthing points. ...etc. without completely draining the tank of oil.
Each transformer tank shall be fitted with suitable wheels for mounting on pre¬
pared concrete foundations provided with rails and fixing clamps unless otherwise
approved by the Purchaser. The transformer shall have upper flange tanks.
The whole of the tank and fittings shall be sand blasted inside and outside to
remove all scale and rust before painting. The inside of the tank shall be painted
with an approved oil resisting varnish. The tank shall be provided with hauling
lugs of adequate strength for withdrawal of the transformer in and out of the
transformer bay.
V
O-
»siu£j,n •C
Tf-A'C' -
32
All seams or joints other than those which may break shall be welded both inside
and outside to assure strong, leakproof joints.
Heavy structural steel members shall be welded to the bottom of the tank to form
a rigid ground supporting structure at which wheel carriages are attached to take
up the static load.
One set of the necessary steel ropes, slings, tackles, hydraulic jacks required for
lifting the core, coils, tank and/or tank cover, shall be provided.
The following moving and handling facilities shall be provided for each
transformer.
Four jacking lugs for raise/low whole transformer filled with oil-key by
means of hydraulic jacks.
)! (
Lugs for lifting the whole transformer.
f
Pulling eyes for moving the transformer in any direction.
2.19 CONSERVATOR:
A conservator tank shall be located conveniently on the top of the tank. Suitable
oil gauges shall be provided at each end which can be easily read from the ground
level. The temperature range to be expected under Kuwait’s condition in the open
is 6°C to 84°C. The capacity of the conservator shall allow the expansion of oil
from 0°C to 100°C.
The conservator tank shall be of two portions (one for main tank and the second
(
for the tap-changer) each is provided with filling cap, drain and oil sampling valve
/ device. Each portion shall be fitted with silica gel as dehydrate.
The pipe connections from the conservator to the main tank, the tap change
diverter switch chamber and the disconnecting link chambers shall be designed to
have smooth run without shaip bends.
All pipes connected to the conservator tank shall protrude at least five cm. above
the bottom of the tank.
The oil level gauges shall be of the magnetic type with contacts for local and
remote supervisory low oil level alarm indication.
£V
v'-
m 4
33
The banks of cooling radiators of the transformers shall be designed and arranged
so that they are detachable from the main tank for purposes of transport. Valves
shall be provided to shut off the oil leaving the main tank into the cooling tanks.
Air vent holes and drain plugs shall be provided on the banks to facilitate filling
and draining of the banks on site. The tube bank shall be connected to the main
tank through oil pumps for circulations of the oil pumps bottom connected to the
radiator where it is cooled by means of forced air draft.
The radiators shall be pressure tested to ensure liquid tightness, radiator headers,
if provided, shall be. sloped, so that they can completely be drained & vented
when filled. All portions of the equipment shall be accessible for inspection,
cleaning and painting.
(
The radiators shall be assembled, framed and braced in such a manner as to
provide mechanical protection to themselves and to prevent vibrations.
The oil inlet and outlet branches to suchradiators are to be provided with isolating
valves or dampers which would enable the removal of the pertinent radiator with
the transformer in service.
2.21 VALVES:
Drain valves shall be provided to completely drain the main tank, the conservator
tank, the tap change apparatus chambers, cooling tube banks and disconnecting
link chambers.
Set valves with clearly marked position indicators and padlocking facilities shall
be provided between.
a) The main tank and conservator.
b) The conservator and tap diverter switch chamber
c) The conservator and each cable disconnecting link chamber.
L_ d) Between main tank and each cooling tube bank.
e) Between radiator branches and mainheader.
Oil sampling valve device shall be provided at suitable points on the main tank,
tube banks and tap change diverter switch chamber, and the conservator.
Aluminum valves are not acceptable.
•« \
udh T7
7ÿ Vv
(**),.
34
2.23 BREATHER:
Each portion of the conservator vessel will be fitted with two Silica gel
Breather with replaceable elements. The breathers shall be arranged at
such a height that it may be readily accessible from ground level and
suitable observation window to be provided in the breather. The breathers
shall be provided with protected oil sealing bath.
•SJ,
O. b.» SO
35
Number of phases.
Frequency
Weight of oil
)
( Total weight of transformer
i
Year of manufacture
The plates shall not be less than 2.5mm thick and the marking shall be
engraved thereon and the background being filled in black.
On another plate or on the above plate a plan view of the transformer giving
the correct physical relationship of the terminals shall be engraved. In
addition to the location and function of all valves and air cocks or plugs,
warning to the operator to refer to maintenance instructions, before applying
vacuum treatment. Also the points of lifting and pulling as well as the
necessary dimensions of permitted angles of lifting repes have to be
;
v indicated.
Each chamber shall be provided with a draining plug and an air vent cock.
A suitable earth terminal shall be provided to enable either the transformer
winding or cable terminations to be earthed during high voltage tests.
The disconnecting chambers for high and low voltage sides shall be
completely separated from each other. The link chambers of the 275KV
and 132KV winding shall be separate for each phase and pipe connections
to the conservator shall have suitable valves and gas relays. Detailed
drawings shall be submitted for approval.
Where specified, SF6 tubing shall be supplied for connection between the
275KV switchgear and the disconnecting link chambers of the 275/132KV.
Transformer with separate tubing for each of the three phases.
The tubing shall be SF6 gas insulated complete with tubular bus-bar
conductors, connections between sections of bus bars separating cast resin
cones between adjacent compartments respectively the oil in the
disconnecting link chamber with safety measure for proper sealing between
oil and gas. Suitable gaskets preferably of the “0” ring type to be provided. (
t The tubing shall be complete with various types of enclosures to suit any
passage between the equipment and to be complete with flanges, bellows,
piping connection and valves and pressure switches for gas filling, gas
pressure monitoring. The necessary supporting structures and any other
fittings to render the work complete in every respect. It is to be noted that
separated SF6 tubing shall be provided for connection of the primary
winding neutral point to the earthing switch and the neutral SF6
encapsulated surge arrestors as will be mentioned later under details of
equipment Yol. in. Gas density relays or temperature compensated
pressure switches to be provided.
& 4~/
37
The buchholz device shall incorporate a test cock for testing purposes
f I' suitable for connection of foot operated pump with hose for testing of the
device.
All motors shall be of the totally enclosed, squirrel cage, fan cooled direct
starting type. The motors, control gear and an auxiliary apparatus shall be
of robust construction insulated with class “F” materials having degree of
protection of IP65 and in accordance with BSS 2613 including dimensional
standard where stated, unless otherwise specified herein. Arrangement of
the control gear for auto and manual starting, selection of fans for operation
will be entirely to the satisfaction of the Purchaser.
>
r@S
-
4§)
—=
"
38
2.33 INSTRUMENTS:
n a) Winding Temperature Indicator:
A dial type indicator calibrated to show the temperature of the
hottest region of the windings shall be provided. The device may be
of the type comprising a current transformer, heating oil, hot oil
pocket, temperature measuring and arranged to produce the desired
relationship between winding temperature and hot oil temperature
through mercury / liquid filled Bourden and Capillary tubes.
b) The indicator shall be fitted with two sets of fixed and moving
contacts, one for trip and one for alarm adjustable to close between
the range of 60°C to 120°C. These contacts shall be of the heavy
duty type mercury switch reopen when the temperature has fallen
down not more than 10°C. Two separate contact circuits, one for
"ALARM” and one for “TRIP” shall be provided for connection
between devices and control board. Facility for manual operation of
its mechanism movement for testing purposes should be provided in
any conventignakfotm, e.g. an outside projecting kjieb-having hand
access
39
The indicator shall be fitted with two separate sets of fixed and
moving contacts one for “ALARM” and one for “TRIP” adjustable
to close between the range of 60°C to 120°C. The contacts shall re¬
open when the temperature has fallen down not more than 10°C.
These contacts must be of the heavy duty type, mercury / liquid
switches and should be equipped (as in the case of winding
temperature indicator) with facility for manual operation of its
mechanism movement for testing purposes.
Two separate circuits shall be provided between the devices and the
control board. A maximum temperature pointer shall be provided to
show the highest temperature reached and shall be arranged for hand
resetting.
The cost of the transformers and their annual losses will be taken into
account for the determination of the successful offer.
( V
The capitalization will be based on the assumption as given in Volume I.
2.36 Transformer Tails, Oil filled 800 sq.mm. Single Core 132KV Cable:
These cables shall comply with Part 9 of VolumeIexcept as stated below:-
(i) Conductors:
The conductor shall be of stranded copper wires shaped into circular
core of a cross-sectional area 800 sq.mm, and formed with central
oil ducts of 12mm. diameter.
W
£
v \A-
lv
(Vfc)r.*ÿ,vn
\:C°-V7KAGX&S
40
(ii) Insulation:
(iii) Screening:
sip ‘Tv
v
41
The PVC sheath shall be embossed with voltage designation (132KV) and the
manufacturer’s name and with the same manner described in BSS. 6480 and
ESI Standards 09-4.
The power transformers shall have motor driven oil circulating pumps of the
glandless, submerged type. It shall be possible to remove the pump with
motor from the oil circuit without having to lower the oil level or to shut
down the transformer. 80% of the pumps shall be capable of dealing with
the maximum output and head which may occur in service and due to the
changes in viscosity of oil. Oil pumps are to be rated for 4 x 20% total
capacity in addition to one stand-by pump shall be provided to the number
required for maximum output.
The control, protection indications and alarms of these oil pumps shall be
installed partly in the marshalling box adjacent to the transformers.
However, the alarms of pumps trouble, oil flow trouble shall be shown
f 0 locally and signalled to N.C.C. At least three pumps shall start
automatically as soon as the transformer is energized. The rest of the pumps
will be controlled by oil/winding temperature.
JUS
3 v-
£ •osL'U
M
X'w* .
42
In order to limit the ground fault current of the system it shall be possible to
individually connect or disconnect the neutral points on H.V. side of the
transformer by means of motor operated isolating switches. They shall be
designed for outdoor use and to withstand the maximum prospective faults
current to be met in service when closed of being switched on to an existent
single-pole ground fault for at least 1 second. The voltage class shall be the
phase voltage of that side of the transformer where this particular switch is
connected. (
The motor drive shall be of the high speed type with a closing time of 1
second or less. Local and remote control as well as manual operation by a
mechanical gear must be possible. Auxiliary contacts are required for
remote position indication in the Control Room.
The above lightning arrestors shall be connected in parallel with the neutral
isolating switches mentioned under Clause 2.39 above as shown on the
attached drawing.
(ÿ)r
V J S 0. fc «x W
\;CoV7RACÿv/
43
2.41 Tests:
2.41.1 Transformers:
st>
5•
,
W-
wVw» *
44
(c) Hydraulic Pressure Tests:
The following test shall be carried out on one transformer or each size,
complete with its conservator tank, radiators and other fittings.
lit Cv
A (**),.
45
Test to prove the current canying capacity with the rated impulse
(peak asymmetrical short circuit ) current and the rated short time (1
sec.) current.
a) The 300KV switchgear shall be supplied with its own remote control
and relay boards which shall be equipped with the required control
equipment, instruments, relays and all other accessories as detailed in this
specification and outlined in the schedules. The control and relay boards
shall be similar to these specified in Volume Iand housed in the same
Control Room.
b) Measuring Instruments:
( The provided instruments shall be graded as follows:-
1. All ammeters should have proper size and calibration to read up to one
twentieth of the full scale from zero to maximum.
2. All 275KV voltmeters should be calibrated to read 5.0 rv difference from
240 KV to 300 KV.
3. All MV and MVAR meters shall be calibrated to read a difference of 10MW
or MVAR for the whole range, and should have zero centre scale so that
export or import of power can be read.
4. It is also essential to install all instruments and relays belonging to one circuit
in one panel, vertically below the circuit name label, with clear portion
between one panel and another.
mM& “•Eft*
% V J ®
46
2. Synchronizing Panel:
The synchronizing relay and the schemes proposed shall be subject to the
approval of the Purchaser.
4. Protection:
All relays shall have a set of clean contacts (potential-free), with holding
time not less than 25 ms. Which shall be connected to suitable terminal
block in the control panel, to be used for telesignalling to the “Remote
Supervisory and Control Centre”. These terminal blocks shall be wired to
the transfer terminal blocks cabinets mentioned later.
•'A
IP \ÿCnr' Sÿ'
r 0° V
47
The following descried protective relays against each item i.e. underground
feeder, overhead line feeder, etc. is mentioned to explain the function,
design data and settings of each type of protection. However, the required
relays will be supplied and installed as mentioned in the details of
equipment.
( f
r 4.2 300KV Underground Feeder Protection:
(This consists of Main 1 and Main 2 protection as detailed below):-
a. MAIN.l :
The distance between the two ends of circuits provided with the pilot
wire feeder protection may be assumed to vary between 2 Km. To 15
Km. means shall be provided for the adjustment and this shall be stated
in the tender.
The protection shall be stable for through fault currents up to full 3-phase
short circuit MVA level , and shall meet the requirements of M/s. A.
Reyrolle of England as given in their Pamphlet No. 1328.
prom%\ /&C5ÿT
48
c. MAIN.2:
This consists line relaying including static distance relay type LZ96
of M/s. BBC without re-closing and suitable for three directional
Xi steps and arranged in a permissive under-reaching scheme. {
f By means of transmitter/receiver unit and the existing pilot cable
core. The distance relay shall be provided with transient blocking
and power swinging blocking.
»ST
49
The reach of each zone shall be adjustable and the minimum and
maximum length of feeder that can be protected shall be given in the
data sheets.
With these relays, where carrier equipments are not provided by the
Purchaser, pilot wire cores between this substation and the far end
substations may be used together with the necessary inter-trip
sending and receiving units at both ends shall be supplied and
installed and the cost of such shall be included in the offer price.
The protection shall provide for automatic high speed time delayed
h single re-closure for any type of fault, selector switch to be provided
suitable for, 3 -phase re-closure or no-re-closure.
c Carrier current acceleration will be provided for inter-tripping the far
end C.B. having the fault occurring in their second zone.
Xs P. O.IHIM
50
A time chart should be provided to show minimum operational time
of various relays and contactors up to issue of trip signal.
The relay should be fitted with auxiliary relays for carrier signal
receiving, transmitting and blocking as the case may be cabling
between the protection and the carrier equipment is included in the
contract price.
MainI- BBC type LZX51, solid state relay complete with all
auxiliaries including under voltage stating relays,
transient blocking, power swing blocking, auto
reclosing, signal block....etc. and arranged in a
permissive over reaching (unlocking) scheme. This
also include sensitive E/F relay also of M/s. BBC
type PP x 401. The inter-trip circuit to be provided
from separate channel of PLC equipment.
(
f Each relay shall be provided with “Fault” “Locator” unit i.e. distance
measurement to the fault. For each distance relay one independent
fault locator will be provided.
b) Back-up Protection:
7 c) Main -II - BBC type L8b with all auxiliaries as above but arranged
in a permissive, under reaching (carrier acceleration) scheme. (
b) The neutral of high and low voltage sides are directly earthed. The
C.T. neutral for R.E.F. protection shallbe provided and shall be SF6
>) insulated for H.V. side and air insulation for L.V. side.
I
r c) In addition, the usual Buchholz, tap changer, winding and oil
temperature protection for these transformers shall be provided.
d) Back-up Protection:
The relays shall be of the induction disc type with inverse and
definite minimum time lag characteristic (I.D.M.T.L). The over
current units to have a current range from 50%-200% in stops of
25% and time setting adjustable from zero to 3 seconds at ten times
the current setting. For earth leakage unit the current range to be
from 10% to 40% in steps of 10% and time setting similar to that of
f) over current units having characteristics to BSS No. 142. The time
( multiplier settings shall be adjustable as per clause 4.2 (b) above.
ii) The low voltage side circuit breaker cannot be closed unless the high
voltage side circuit breaker is closed and the 132KV transformer
isolator and associated 132KV busbar selection isolator are fully
open or fully closed.
iii) The low voltage side circuit breaker shall trip when the high voltage
side C.B. is tripped or opened.
iv) If the interlock is defeated or faulty and the neutral isolator is opened
then the high voltage side and low voltage side circuit breakers shall
trip simultaneously.
The busbar zone protection scheme shall be stable and shall not be
influenced in case any fault occurs outside the busbar zone protection. The
stability of the scheme is to be proved at site by testing as well as by
technical design data.
Provision shall be made for supervisory relays necessary for checking the
healthy condition of C.T. secondary so that the busbar zone protection is
locked from operating in case of C.T. secondary faults to avoid mal-
operation. Necessary alarm shall be transmitted to National Control Centre
~
hd‘MWlk v7
53
A busbar zone protection panel/s shall be provided to accommodate the
following:-
One set of annunciator with sufficient number of windows.
Check busbar protection relays with accessories.
Supervisory relays for CT secondary circuit and trip circuit.
Discriminative busbar protection relays and/or contactors as
necessary.
The bus bar protection shall be of the fully static transistorized type
complete with means for periodical checking which are built in permanent
on the board.
...
On the chart, the date and time must be printed. Sufficient detailed
technical literature with explanatory notes showing the number of currents,
voltages events that can be recorded simultaneously shall be mentioned with
the stress on the mode of operation, installation etc. The Tenderer must
show how many recorders for all the circuits i.e. C/H, U/G and
transformers, B/C and B/S will be provided with very high member of
announcement inputs. The tenderer should clearly show the proposed
scheme and arrangement of the equipment. It should be noted that more
than 12 analog and corresponding events on 12” wide paper or 8 analog and
events of S’ÿffideÿpapeÿ should be recorded. The numJÿÿrÿGOTding units
/s (““'•» “Ji
55
The entire arrangement is however subject to Purchaser’s approval and any
additional requirements or changes will not entitle the tenderer for claim of
extra payment.
It is worthy to mention that events other than mentioned above such as
transformers devices alarms, AC and DC fail, drive mechanism troubles,
etc. may be required to record. The recorders must be supplied, preferably
of built- in type, test set for periodical checking.
It should be noted that currents, voltages and corresponding events of any
particular feeder circuit must be recorded on one recorder i.e. current of any
feeder on recorder ‘A’ and voltage on recorder ‘B’ will not be accepted.
The list of analog and events as a minimum are given below:- _
Current Voltage Events
Line Phase Phase Description
R R
Y Y
C/H B B = 1st main distance relay operation
N N 2nd main distance relay operation
c Directional CC/EF relay operation
Circuit Breaker failure relay operation
Circuit breaker status.
Pilot wire relay operation(if applicable)
Reclosing relay operation and
Sensitive E/F trip _
R Differential relay operation
Y Restricted earth fault relay operation
B Overcurrent relay operation
Transformer N Transformer internal fault
N1 Circuit breaker failure relay operation
N2 Circuit breaker status.
Buchholz relay operation (Transf.)
Buchholz relay operation (OLTC)
Winding temperature high _
R Over current relay operation
B/C Y Main ‘A’ bus bar relay operation
B Main ‘B’ bus bar relay operation
( And N Circuit breaker failure relay operation
R Circuit breaker status.
Y Overcurrent relay operation
B/S B Circuit breaker failure relay operation
N Circuit breaker status
R
Y Pilot wire relay operation
U/G B Distance relay operation
N Circuit Breaker failure relay operation
Circuit breaker status
4.9 Synchronizing:
Synchronizing facilities shall be provided across the circuit breakers and the
following requirements should be met:-
The synchronizing scheme should allow for the running voltage bus wires to be
always energized through auxiliary contacts of voltage selection relays from one
voltage transformer at a time. Provision shall be made to telemeter, the bus-bar
voltage from the running bus by means of voltmeter transducer. Also from this
auxiliaiy bus, the bus bar live signal shall be arranged to be tele-signalled to the
Supervisory Centre for each bus bar section. All the necessary relays,
contactors, wiring, etc. have to be provided.
/
57
Protection Engineer:
The above two months period can be extended for a further period of up to
six months if required by the Purchaser. For this extended period, the
Contractor will be paid for the services of the said Engineers at the rates as
given in the respective schedules. The Ministry reserves the right to collect
and keep the Passports of all the foreign erectors, testing engineers and
protection engineers in its custody and none of these are permitted to leave
without the consent of MEW.
( 0
U
r
%ÿ