1. Definition
1. (Ref. 1.2) The Adjudicator of this contract is secretary to the Minister of Irrigation and
Water Management.
2. (Ref. 1.32) The start Date is the date that the contract is awarded. (……………- 2010)
3. (Ref. 1.7) The completion date is 365 days from the date of acceptance.
5. (Ref. 1.19) “Engineer” means the Deputy Project Director of Uma Oya Downstream
Development
6. (Ref. 1.9) “Contractor” means the Factory Engineer, Govt. Factory, Kolonnawa
The “Contractor’s representative” means the competent person that Contractor shall
employ to constantly oversee the Design works, Temporary works and Construction
works as the person in-charge and any instructions given to him by the Employer shall
be deemed have been issued to Contractor.
7. (Ref.1.16) Defect liability period - Defect liability period is 365 day from the date of
completion.
B-1
9. (Ref. 47) Price Adjustment - Price adjustment will be paid according to the
invoice for material submitted by the Contractor.
10. (Ref. 48) Retention - The proportion of payment retained is 10% of the
certified work done. The limit to the retention shall
be 5% of the initial contract price.
11. (Ref. 49) Liquidated Damages - The liquidated damages of the whole of the works
shall be 0.05% of the initial contract price per day.
The maximum amount of the liquidated damages for
the whole of the work is 5% of the initial contract
sum.
12. (Ref. 51) Advance Payment - Advance payment of 20% of the contract sum
excluding provisional sum, as stated in the letter of
award shall be paid without Guarantee.
13. (Ref. 52) Security - Since the Government Factory is a Govt. Institute,
no security bond shall be needed.