JURNAL TEKNIK, (2013) 1-6 1

Design of Proposed Maintenance Task Based On the


Trade-Off Analysis between Reliability and Utility
(Case Study: Phonska I Plant – Pt Petrokimia Gresik)
Sofyan Fahmi, Yudha Prasetyawan
Industrial Engineering, Faculty of Industrial Technology, Institut Teknologi Sepuluh Nopember (ITS)
Jl. Arief Rahman Hakim, Surabaya 60111
E-mail: yudhaprase@yahoo.com, sofyan.fahmi96@yahoo.com

Abstract – In practice, maintenance for manufacture is Several companies, particularly the manufacturing
complex, either for plant even for every system. It requires companies has been attempting to optimize the maintenance
the proper proposed maintenance tasks. However, some activities in order to maintain their production activities.
companies have a problem for designing and implementing This aims to fulfill the determined target production. One of
maintenance management. In this case, Phonska I Plant PT the manufacturing companies implementing the
Petrokimia Gresik is selected as the observation object of maintenance activity with the purpose to meet the
this research because PT Petrokimia Gresik has not determined production target is PT Petrokimia Gresik.
implemented maintenance based on the reliability. Over the Over the years, PT Petrokimia Gresik has not been
years, Phonska I Plant had high number of unexpected executing the reliability calculation during the certain time
downtime days, and it caused the inability of Phonska I [R (t)] to all the machines and equipments in the plants. In
Plant to meet its production target. If this happens, there practice, reliability calculation should have been done by the
would be high amount of lost sale or profit loss. These Engineering Inspection Department. Nevertheless, reliability
problems have been solved by using the design of proposed calculation in PT Petrokimia Gresik has still been the
maintenance task, which is referred to the seven questions planning. Therefore, it can be concluded that PT Petrokimia
entailed by Reliability Centered Maintenance II Process and Gresik has not been executing the reliability system
Failure Mode & Effect Analysis Identification, relatively to each plant. The absence of reliability
Conventional Preventive Maintenance Scheduling with calculation in plant may cause the over-action and less-
trade-off between reliability and utility scenarios, and action maintenance or inefficiency in [2].
Maintenance Interval for Finding Failure. By using the One of many methods in maintenance task design is
Conventional Preventive Maintenance, the scenario with Reliability Centered Maintenance (RCM) II. RCM II is a
original MTTF results in 34.2 days of repair; the scenario process used to determine what to do in order each asset
with utility + 20% results in 29.33 days of repair; the may perform its function as its operational context. The
scenario with utility + 40% results in 25.08 days of repair; implementation of RCM II requires a big effort, which is the
and the scenario with utility + 50% results in 23.91 days of analysis of the components, machines, and failure
repair. With scenario original MTTF and utility + 20%, identification must be executed by using the Failure Mode
Phonska I Plant cannot meet the production target. With Effect Analysis (FMEA) structurally to maintain the
scenario utility + 40% and 50%, Phonska I Plant can meet performance of the system [3].
the production target. The Maintenance Interval for Finding Based on current maintenance activity, PT Petrokima
Failure Method is determined to get the early analysis of the Gresik needs an improvement of its maintenance system by
potential failure of a machine, so that the operator will get implementing RCM II to assist PT Petrokimia Gresik in
the precaution and direct preventive tasks to reduce the classifying the equipments and designing the maintenance
potential failure and get the plan for maintenance execution task of all the production unit in PT Petrokimia Gresik at
according to preventive maintenance schedule. once. Besides, PT Petrokimia Gresik needs to conduct the
reliability calculation of each equipments, machines, and
Keywords : Proposed Maintenance Task, Reliability components in order PT Petrokimia Gresik might have an
Centered Maintenance II, Conventional Preventive effective maintenance plan to assist PT Petrokimia Gresik in
Maintenance Scheduling, Trade-off Reliability & Utility, fulfilling the production target. In this case, the author select
Maintenance Interval for Finding Failure the Phonska I Plant of II A Department Production because
this plant has been operating since 2000, which means that
I. INTRODUCTION this plant has been operating for not too long time so that the

N owadays, the maintenance activity for machines and


equipment in manufacturing has been concerned to
support the companies in achieving their goals. In practice,
failure time since the first period is available.
In 2009, Phonska I Plant is stipulated as the official name
of the plant. The very first production capacity of Phonska I
maintenance activity in a manufacturing company is not is designed at 1000 tons / day or 300000 tons / year that has
easily done. It requires an effective planning and been upgraded recently to be 450000 tons / year since 2007.
management in order the maintenance activity can be The increasing of Phonska I production capacity was
implemented well and effective. To maintain the availability adjusted with its production target. The current capacity can
and the performance of the system, the effective be fulfilled only if the plant operates during 24 hours with
annually turn around [4].
maintenance task is required as well [1].
JURNAL TEKNIK, (2013) 1-6 2

From the upgrading of production capacity of Phonska I, under the production target, except in 2009. The inability of
PT Petrokimia Gresik ought to maintain the function of Phonska I Plant to meet the production target will cause the
every production unit and machine in the plant to avoid loss or it is known as the lost sale cost or profit loss. If the
downtime. By restarining the downtime, Phonska I may lost sale is converted into rupiah, the lost production should
increase the availabilty of machines in order the production be calculated by calculating the difference number of
capacity can be upgraded. This downtime of system is most targeted production and actual production.
affected by the major machine in the plant. The system fails Consequently, in this research, the author attempts to
when one or more major machine stops performing its develop or implement Reliability Centered Maintenance II,
function [5]. which describes and determines the required maintenance
Based on the Annual Production Report of Production tasks and activities in order every equipment and physical
Department 2A PT Petrokimia Gresik over 5 years from asset might maintain its operational function as expected.
2008 to 2012, the downtime of the Phonska I Plant is shown For the success of RCM II implementation, the author
by the graph below [6]. attempts to define the finction and functional failure of
system at first, then to define the mode and effects of its
Scheduled & Unscheduled DT of failure which is commonly known as Failure Mode Effect
Phonska I PT Petrokimia Gresik 2008 - 2012 Analysis (FMEA). At the end, the author attempts to define
61.21

the effective maintenance tasks, preventive schedule of


70
55.42

major machine of Phonska I Plant, and its maintenance


60 interval in Phonska I PT Petrokimia Gresik. RCM II may
44

overcome the problem of incomplete information of


37.25

50
41
34.14

31.56

equipment, machines, and components classification in


36
28.67
34
26.63
33
33

33
33

40
Phonska I. In order to reach the effective and efficient RCM
Days

20.38
24

16.26
15.72

30
22

II, especially in its maintennace interval, the reliability


20 calcualtion of the Phonska I production system and so the
mean life of each component will be unraveled as well. In
10
this research, the author will also combine the constraint of
0 production target which the determination will be analyzed
2008 2009 2010 2011 2012 using the reliability calculation and otherwise. This
Year determination will be the trade-off between reliability and
Scheduled DT (Target) Scheduled DT (Actual)
Unscheduled DT (Target) Unscheduled DT (Actual) the utility of the Phonska I plant. Through this reasearch, PT
Petrokimia Gresik will enable the implementation of RCM
II method to the whole plants to design the effective
Figure 1 Scheduled & Unscheduled Downtime of Phonska I PT Petrokimia maintenance task and meet the expected production target
Gresik 2008 – 2012 and reliability through the maximum utility of the
If the condition of the actual unexpected downtime is equipments and machines at the plants.
higher than the targeted unexpected downtime in a constant
production rate per day, it will certainly decrease the II. RESEARCH ELABORATION
production of the plant. As a result, it will evoke the lost
production that will be the first reason of the profit loss. A. Literature Study
Below is the graph that will describe and give the real 1) Reliability Centered Maintenance II
condition of the the actual and targeted production over five Reliability Centered Maintenance is the worldwide
years in the same years from 2008 to 2012: leading maintenance identification method and other
maintenance activities, which is required to be implemented
Targeted & Actual Production of Phonska I into the physical assets in order the assets is able to sustain
PT Petrokimia Gresik 2008 - 2012 the reliable performance. Reliability Centered Maintenance
487246
415639.39

(RCM) is a process used to determine what must be done in


453000

450000
430000
429000

425914

423507

order each physical asset is able to perform its function and


334601.44

500000
353423

continue to its function as the owner expects in its present


Production (Tons)

400000
operational context [3] [9].
Through the RCM application, each failure of
300000 an asset can be observed and traced by the interrelated seven
questions entailed by the RCM Process:
200000 - What are the functions and associated performance
100000
standards of the asset in its present operating context?
- How or in what ways does it fail to fulfill its functions?
0 - What are the modes or the causes of each functional
2008 2009 2010 2011 2012 failure?
Year - What will happen when each failure occurs?
Production (Target) Production (Actual)
- How or in what ways does each failure matter?
Figure 2 Target & Actual Annual Production of Phonska I PT Petrokimia - What can be done to predict or prevent each failure?
Gresik 2008-2012
- What should be done if a suitable proactive task cannot
From the Figure 2, it can be seen that the actual be identified?
production of Phonska I PT Petrokimia Gresik was always
JURNAL TEKNIK, (2013) 1-6 3

By implementing RCM II, the information of a production MTTF (when a component has reached its MTTF, then
unit can be summarized in the seven questions entailed by the value of its MTTR should be appeared in the
RCM Process. From that information, the evaluation of the column ‘Repair’ and the other components are not
function and functional failure can be executed so the repaired). In the stage 2, the formula of the ‘Start’ =
Failure Modes & Effects Analysis can be composed as well ‘Stop (Stage 1)’ + ‘Repair’ and the value of the ‘Repair’
to design the proposed maintenance task [3]. is filled by the same way as the stage 1. Each column of
the stage 3 until the end of the stage is calculated with
2) Reliability Distribution (Failure Rate Model) the same way as before,
Reliability Mathematical model starts by defining the 4. Checking the maintenance period for one year, and note
reliability quantitatively in terms of probability (PDF) and in which stage each component stops,
cumulative density function (CDF) for time-to-failure and 5. Adjusting the remaining MTTF by creating the
defining the failure rate and mean time to failure (MTTF). adjustment table below,
According to Lewis (1994), Reliability is the probability that 6. If any two or more components stop at the same time,
the system survives for a specified period. The specified which means that the reparation should be applied to
time or period may be expressed in terms of random those components, then the longest period of repair
variable x (time to failure) [5]. among those components will be used to update the
The time to failure of equipment is a random variable. In ‘Start’ column in the next stage,
advance of calculating the reliabilty of a machine or 7. The scheduling or staging will have to be discontinued
equipment, the failure distribution of each equipment need when all the components reach their MTTF at once at
to be unraveled statistically. There are two type of failure the same time because the pattern of this staging will be
rate models, where each type of failure rate models the identical to the first staging.
comprise various type of failure distributions. This method can be used to find the maintenance
The first failure rate model is Constant Failure Rate scheduling or interval for series component or parallel
Model. Constant Failure Rate Model is defined by the components. When the components are in the parallel
assumption that the rate at which the system fails is system, the algorithms above cannot be used. The
independent of its age. The constant failure rate algorithms above are used to find the scheduling
approximation is often quite adequate even though a system maintenance for series components of a machine. To find
or some of its components may exhibit moderate early the scheduling for parallel components for many machines,
failures or aging effects. The only one failure distribustion the algorithms number 3 to 7 are not applicable. If the
of the constant failure rate is the Exponential Distributions. components are parallel and they are independent each
Meanwhile, the another model of failure rate is Time- other, the reparation will be applied for each component
Dependent Failure Rate Model. The Time-Dependent independently. By definition, when a component fails and
Failure Rate Model is used when there are variety of the reparation is applied, the other components do not need
situations in which the explicit treatment of early failurer or to be stop. Consequently, the column of ‘Repair’ will be
aging effect, or both applied to the system. The time- filled with the MTTR of each component [8].
dependent falure rate model comprise the Normal Finding failure task is executed when the proactive task
Distributions, the Lognormal Distributions, and the Weibull cannot even be executed to reduce the multiple failure of the
Distributions [7]. related hidden failure up to the tolerated lower limit of
multiple failure. Finding failure task comprises the hidden
3) Scheduling and Maintenance Interval function checks to detect the failure of an equipment. This is
The calculation for obtaining the optimum maintenance known as the functional check [3].
interval can be found by using many methods and many According to Mobray (1997), proposed interval
formulas. The methods for calculating the maintenance for finding failure task is calculated as below:
interval has been developed by many reserachers and FFI = 2 × Utive × Mtive
approximation. The maintenance interval used to apply the Notes:
maintenance activity for the equipments or assets depends FFI : Failure Finding Interval
on the owner or company’s maintenance management. The Utive : Desired Unavailability of protective device
maintenance interval can be calculated by using the Mtive : MTBF of protective device
preventive maintenance scheduling and maintenance
interval for finding failure.
This maintenance scheduling method uses the data of B. Methodology
Mean Time To-Failure and data of the reparation activity or The methodology or steps of conducting this research are
Mean Time To-Repair of each components or machines. following this flowchart:
The algorithms of this method are below:
1. Sorting the components based on the MTTF from the
lowest to the highest,
2. Creating the column under the title ‘Start’, ‘Stop’, and
‘Repair’ in a row, as many as the operational hours
divided by the lowest MTTF (stage),
3. Formulating the relevant equation (excel function) of
each column in each stage. In the stage 1, the
formulation for ‘Stop’ column = ‘Start’ + MTTF; the
value of the ‘Start’ column is started from zero; the
value of the ‘Repair’ column depends on the lowest
JURNAL TEKNIK, (2013) 1-6 4

the components. Cleaning or dismantling the equipment is


Start the only way to fix this problem and replacing the
components can be executed as well.
Problem Identification From the RCM II Worksheet for Phonska I Plant, it is
found that the potential failure in Phonska I Plant is caused
Problem Formulation by operational problem and functional problem. The
functional problem consists of functional problem with
preventive task and without preventive tasks. So does with
Literature Review Observation the operational problem. All the problems that can cause the
downtime to the plant above can be recapped into a diagram.
The proportion of problems that can cause the downtime of
Scoping: Limitations and Assumptions
plant can be described by the diagram below:
Preparation
Phase Data Collection Proportion of Problems Causing Downtime in
Phonska I Plant

Functional Block Diagram Identification Functional Problems with


20% Preventive Tasks

Functional Problems
Identification Function and Functional Failure
Phase Identification of Phonska 1
48% without Preventive Tasks
12%
Operational Problems with
Preventive Tasks
FMEA Construction
20% Operaional Problems
without Preventive Tasks
Designing Proposed
Maintenance Task

Reliability Calculation Figure 4 Proportion of Problems Causing Downtime in Phonska I Plant

Utility Calculation and its From the diagram above, it can be seen that the downtime
PMT Designing
Phase Trade-off with Reliability of Phonska I Plant is most caused by the functional problem,
but in reality, the operational problems comes up frequently
Proposed Maintenance in the Phonska I Plant. Most of functional problems have the
Interval & Scheduling preventive tasks that can be done to prevent or reduce the
potential failure of the related equipment. Most of
Analysis and Data operational problems do not have the preventive tasks that
Interpretation can be done to prevent or reduce the potential failure. The
operational problems without preventive tasks are the most
Conclusion and
frequent problems that appear in the Phonska I Plant and
Recommendation
Conclusion &
causing downtime to Plant. This may cause the downtime
Recommendation End because most of operational problems are encountered by
Phase the important machines such as granulator, dryer, coater
drum and by material handling such as conveyor & elevator.
Figure 3 Flowchart of Research

C. Reliability Centered Maintenance II Work Sheet D. Machines’ Reliability


The Reliability Centered Maintenance II Worksheet that The reliability calculation of all the machines of Phonska
has been made in this research is only for the identified 24 I Plant is started by failure fitting distribution of all the
major or critical machines based on the downtime identified TTF of each machine. The failure fitting
information of the Phonska I Plant in 2012. This RCM II distribution of each machine is done by using the function of
Worksheet construction is based on the modified FMEA “Distribution Wizard” in Weibull ++ 6 Software. The failure
analysis, which is included into the seven questions entailed caused by the operational problem is considered as the time
by the RCM II Process. From identified 24 major or critical to failure. If all the failure distribution of the machines has
machines, some machines comprise the same components. been revealed, the reliability of the machines from time to
In this case, the similar causes of failure may happen to the time can be calculated by using the formula according to its
similar machine. distribution. The reliability from time to time of all the
The RCM II Worksheet of each major machine only machines is calculated until 1500 hours because the highest
contains the analysis of the major components. Some of TTF of a machine is 1322 hours.
failures do not have the preventive task. It means that, when Most of machines that encountered failure frequently
this causes of failure happens, there is no other way but during 2012 have a fast deterioration of reliability. The
shutting the unit down. This is done due to the preventive reliability of the machines that is used as the standard for
task cannot be done to reduce the potential failure while the maintenance is the reliability at time = MTTF. Most of
unit is still operating. The shutdown action must be taken machines that encounter frequent failure during 2012 have a
because some factors such as the dangerous while replacing lower MTTF and reliability at time = MTTF. The
JURNAL TEKNIK, (2013) 1-6 5

degradation of reliability from time to time of these machines is still above 0.1 and so the utility is increased
machines is extremely fast as well. As example, the again to be + 50%.
reliability at time = MTTF = 199 hours of M109 is only The maintenance scenario by using utility + 50% results
0.273, which is very low. This phenomenon may happen in 23.9167 days of repair. The estimated production that can
because M109 is the most frequent machine that be reached by using this scenario is 420513.62 tons, which
encountered the failure during 2012. In the other side, the is more than the target production. At the utility + 50%, no
reliability of Q102 is still 0.4999 at time = MTTF = 825 machines have reached the reliability under 0.1, which
hours, which is still very high. This happens because during indicates that this scenario is still possible to do although the
2012, the Q102 rarely encountered the failure. The probability of failure is getting higher.
reliability characteristic of each machine is most affected by The maintenance scenario is not continued to the increasing
the frequency of failure of the machine itself during its 60% of utility, because at utility + 60%, some machines has
operational life or production. This reliability calculation reached the reliability under 0.1 or excess the maximum
will be base for trade-off together with utility of the plant. TTF that has ever been encountered over the years. That is
why; the maintenance-scheduling scenario by using this
preventive maintenance is not continued to utility 60%.
E. Maintenance Scheduling using Trade-Off
To know the comparison of machines’ reliability in each
The maintenance scheduling of all the 24 major machines maintenance scenario, the graphic in Figure 5 and 6 will
of Phonska I Plant is made according to the Conventional show this comparison. If the reliability of 24 machines is
Preventive Maintenance Method. The maintenance by using recapped in one graphic, the graphic will be so crowded and
this method is done with four scenarios, they are original it is divided into two graphics, the reliability graphic of
utility trade-off, utility + 20%, + 40%, and + 50%. The material handling machines and processing machines
trade-off is stopped when there is one, more machines reach
the maximum TTF, or in other words, the reliability of the
machine is below 0.1, which is very low and the probability Reliability of Processing Machines
0.6
of failure of this machine is very high. B101 Normal
The maintenance scheduling by using original MTTF C107 Normal
0.5
results in 34.2 days of repair and so the plant will stop
C108 Weibull 2
operating as long as 34.2 days if this maintenance-
scheduling scenario is implemented. The consequence of 0.4 C109 Normal
Reliability

using this scenario is the repair action is more frequent and M108 Normal
the target production cannot be reached. The production 0.3
M109 Lognormal
target of the Phonska I Plant in 2013 is 415000 tons. With
the capacity 450000 per year, the capacity per day will be M110 Normal
0.2
1232.88 tons. By using this scenario maintenance, the M117 Weibull 3
estimated production that can be reached is 407825.23 tons, 0.1 P103 Weibull 3
which is less than 415000 tons. By using the maintenance
P107AB Normal
scenario of utility +20%, the MTTF of the machines will
0
increase as well. The original utility is increased 20% first Q101AB Normal
and the result of this utility of each machine is then Q102 Normal
conformed into the time to find the exact value of the MTTF
at utility +20%. With this scenario, the Phonska I Plant will Utility
spend 29.33 days for repair days, which means that the
Phonska I Plant should stop operating as long as 29.33 days Figure 5 Reliability of Processing Machine in Each Utility Scenario
to execute the maintenance. Apparently, the Phonska I Plant
is still unable to meet its production target with the Reliability of Material Handling Machines
maintenance scenario of utility +20%. The estimated
0.6
production that can be reached by the Phonska I Plant by M101 Normal
using this scenario is 413835.52 tons, which is still less than M106 Normal
0.5
450000 tons. The original utility of all the machines is then
M111 Weibull 3
increased 40%. All the utility of machine that has been
increased 40% is then conformed to time to find the exact 0.4 M114 Normal
Reliability

MTTF value at utility + 40%. In this increasing of utility, no M118 Weibull 3


machines have reached the reliability under 0.1 as well. 0.3
M120 Weibull 3
The maintenance scenario by using the utility + 40%
results in 25.08 days of repair, which means that the 0.2 M403 Normal
Phonska I Plant should stop operating during 25.08 days to M404 Normal
execute this maintenance scenario. By using this 0.1 M107 Weibull 2
maintenance scenario, the estimated production that can be
M112 Lognormal
reached is 419075.26 tons. This estimated production is 0
more than the production target. Therefore, this scenario is M113 Normal
recommended to execute in order Phonska I Plant may be M116 Weibull 2
able to meet its production target. This utility trade-off is not Utility
stopped yet. Because at utility 40%, the reliability of all the
Figure 6 Reliability of Processing Machine in Each Utility Scenario
JURNAL TEKNIK, (2013) 1-6 6

the modified Failure Mode and Effect Analysis (FMEA)


From Figure 5 & 6, it can be seen that the reliability of and analysis of 7 questions entailed by RCM II Process in
the machine at original utility has reached reliability above the RCM II Worksheet.
0.5, which is very low. The time of each machine at the 3. The maintenance tasks of each major machines of Phonska
utility scenario above is different. For example, the I PT Petrokimia Gresik has been made and included in the
reliability of M117 at original utility is 0.335 and the RCM II Information Worksheet. From this RCM II
reliability of M109 at its original utility is 0.273, but they Information Worksheet, it can be identified that the
are in the different time and different utility. The graphic operational problems and the functional problems are the
above only describes the reliability of the machines at each causes of the potential failure. The proportion of this
utility scenario. problem causing the failure is: 12% is operational
problems with preventive tasks; 20% is operational
problems without preventive tasks; 20% is the functional
F. Maintenance Interval for Finding Failure
problems withot preventive tasks; and 48% is the
The purpose of this Finding Failure Interval calculation is functional problems with preventive tasks.
to find the functional check in order to obtain the early 4. The scenario of preventive maintenance scheduling based
analysis for precaution of the potential failure. The early on the trade-off between reliability and utility is continued
analysis of potential failure may help the maintenance until the Phonska I Plant is able to fulfill its production
execution becomes more effective. The interval between a target and it is stopped when there is one or more
functional check with another is too short. This may machines reach its maximum historical TTF or reach
happens because the desired availability of the machines is reliability below 0.1, which means that the reliability of
high and the MTTF and MTTR of each machine is relative these machines are too low and the probability of failure is
low. too high. Most of machines that encountered failure
For further analysis and coherent application of this frequently during 2012 have a fast degradation of
research, the procedures of maintenance by using the reliability.
integration of the scenario Maintenance Interval for Finding 5. The maintennace scheduling is composed based on the
Failure, RCM II Worksheet, and Preventive Maintenance Conventional Preventive Maintennace and the functional
Scheduling are composed. Below are the brief procedures of check is made based on the Maintenance Interval for
maintenance scenario in this research: Finding Failure. By using the original MTTF and utility +
1. Checking the information of proactive tasks in RCM II 20%, the estimated production does not meet the target.
Worksheet is the first priority. The RCM II Worksheet By using the scenario utility + 40% and + 50%, the
of the 24 major machines contains the information estimated production meets the production target. Scenario
about the function, failure function, failure modes, utility + 60% is not composed because some machines
consequences, and effect of failure, proactive task that reach reliability under 0.1 at this scenario.
can be done to reduce the potential failure and the The improvement and the potential research that can be
corrective tasks if there is no proactive task. executed to be next research or to perfect this research is:
2. Deciding the Preventive Maintenance Scenario is the 1. The next research may develop or improve this research to
second step that has to be done in this procedure. find the optimal solution for scheduling. The next research
3. The Maintenance Interval for Finding Failure with the may complete this research with the optimal scenarios of
result of functional check schedule will help the maintenance with the optimal cost and optimal human
maintenance executor to get the pre-analysis from the resources. The next research may also develop the
symptom of the potential failure and so the precaution simulation model for this maintenance scenario or develop
of the failure can be prepared. If the operator finds the the program maintenance, which is packed in the effective
operational or functional problem with the preventive and coherent software interface.
tasks, the operator should do the preventive tasks
according to the RCM II Worksheet. If the problem is
the operational or functional problem without the REFERENCES
preventive tasks, the operator should do corrective task. [1] Tsai, Y. T., Wang, K. S., & Tsai, L. C. (2004). A study of
4. The identified problems from the functional check will availability-centered preventive maintenance for multi-component
be the consideration for Phonska I Plant to conduct the [2] sistems. Reliability Engineering and Sistem savety , 84, 261-262.
Smith, A. M., & Hinchcliffe, G. R. (2004). RCM-Gateway to World
maintenance activities at the schedules that has been Class Maintenance (2 edition ed.). Burlington, MA: Elsevier Inc.
made by using the Preventive Maintenance Scheduling. [3] Mobray, J. (1997). Reliability Centered Maintenance (RCM) II (2nd
ed.). New York: Industrial Press.
[4] PT Petrokimia Gresik. (2012). PT Petrokimia Gresik. Retrieved
III. CONCLUSION & SUGGESTION October 20, 2012, from Official Website of PT Petrokimia Gresik:
http://www.petrokimia-gresik.com/
The conclusions that can be summed based on the result [5] Lewis, E. E. (1994). Introduction to Reliability Engineering (Second
of this research to answer the purposes of this research are: ed.). New York: John Wiley & Sons, Inc.
[6] PT Petrokimia Gresik. (2008 -2012). Laporan Tahunan Produksi.
1. From the identified data downtime of Phonska I Plant PT Gresik: PT Petrokimia Gresik.
Petrokimia Gresik 2012 and also from the block diagram [7] Dhillon, B. S., & Reiche, H. (1985). Reliability and Maintainability
of Phonska I Production Process, there are 24 major Management. New York: Van Nonstrand Reinhold Company.
machines. These major machines play the important role [8] Prasetyawan, Y. (2011). Penjadwalan Pemeliharaan Sederhana
Berdasarkan Prinsip Preventive Maintenance. Prosiding Seminar
in the Production Process of Phonska I Plant because when Nasional Teknologi Industri XV. Surabaya: Fakultas Teknologi
these machines fail, the system will fails as well. Industri - ITS.
2. The function and the functional failure of 24 major [9] Igba, J., Alemzadeh, K., Ebo, I. A., Gibbons, P., & Friis, J. (2013). A
macines of Phonska I Plant has been identified by using Systems Approach towards Reliability-Centered Maintenance (RCM)
of Wind Turbines. Procedia Computer Science 16 , 814 – 823.