Documente Academic
Documente Profesional
Documente Cultură
net/publication/279569968
CITATIONS READS
131 916
3 authors, including:
Mark G. Stewart
University of Newcastle
260 PUBLICATIONS 4,871 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Climate change effects and adaptation of civil infrastructure and buildings View project
All content following this page was uploaded by Mark G. Stewart on 27 November 2015.
John Mullard is a PhD student in the Center for Infrastructure Performance and EXPERIMENTAL DESIGN FOR
Reliability, School of Engineering, the University of Newcastle. He received a BEng ACCELERATED CORROSION TESTING
from the University of Newcastle in 2004. His research interests include corrosion-
induced cracking of concrete structures, spatial time-dependent reliability analysis and RC slab specimens
life-cycle cost optimization of maintenance, and repair of reinforced concrete structures. All specimens were RC 700 x 1000-mm rectangular slabs
with a thickness of 250 mm. The top mat of the slab
Table 1—Test variables for each specimen contained four steel reinforcing bars, which had a 1000 mm
exposed length to the concrete matrix (refer to Fig. 2). One
Concrete Mean fc, Mean splitting reinforcing bar with a shorter exposure length was placed in
Series Specimen cover, mm w/c MPa tensile strength
the middle of each specimen to study the cracking mecha-
I_1 25 0.5 20.0 3.06 nism of concrete cover over a smaller length. The middle bar
I_2 50 0.5 20.0 3.06 was covered with electroplating tape to give an exposed
I
I_3 25 0.5 43.0 4.16 (bare steel) length of 100 mm.
I_4 50 0.5 43.0 4.16 The purpose of the accelerated corrosion testing is to study
II_1 50 0.58 42.3 3.76 the relative influence of concrete cover and w/c on the time
II_2 25 0.58 42.3 3.76 to crack initiation and crack propagation. Hence, the variables
II
II_3 50 0.45 52.7 4.55 of interest were selected as follows:
II_4 25 0.45 52.7 4.55 • concrete cover (25 and 50 mm)
• w/c (0.45, 0.5, and 0.58)
Two series of four RC specimens were prepared. Refer to
Table 1 for a description of the test variables for all specimens.
In the first series (Series I), an oversight during fabrication
resulted in the mixtures being different resulting in different
concrete material properties for the same w/c. The specimens
were moist-cured for 28 days before testing. Standard test
cylinders were tested at 28 days to determine concrete
compressive and tensile (splitting) strengths (refer to Table 1).
The cement used for all specimens was ordinary portland
cement. The coarse and fine aggregates (20 and 10 mm,
respectively) were kept the same for all mixtures. The steel
reinforcing bars used for this study were round mild steel bars.
Three percent of calcium chloride (CaCl2) by weight of cement
Fig. 2—Specimen for accelerated corrosion testing. was added to the concrete mixture to induce corrosion along
the exposed length of reinforcing bars. This admixture had a
with existing crack initiation and propagation models. A new negligible effect on concrete strength properties.
empirical model is proposed to predict corrosion-induced
cracks up to 1 mm in width by considering w/c and cover as Accelerated corrosion test
influencing variables. A correction factor to account for To generate crack widths of up to 1.6 mm within a reasonable
change of cracking phenomena associated with high rates of time period, an accelerated corrosion rate of 100 µA/cm2
loading is developed to enable more accurate extrapolation was used in this study. The accelerated corrosion equipment
of accelerated results to practice. The effects of time- is shown in Fig. 3. The soffit of the specimen was immersed
invariant and time-variant corrosion rates are also included. in a 5% NaCl solution. The accelerated corrosion process
These models will provide essential information when was achieved by applying a constant electrical current to the
predicting time-dependent structural performance and reli- bars by a power supply via a current regulator. The current
ability of RC structures subjected to chloride-induced regulator kept the current constant over time. The steel bar
corrosion, such as the use of a random field (stochastic) acts as an anode, the stainless steel plate submerged in the
analysis to predict the likelihood and extent of cracking10,11 NaCl solution acts as the cathode, and the pore fluid in the
and selecting maintenance and repair strategies based on concrete is the electrolyte. The accelerated corrosion test is
optimizing life-cycle costs.12 considered to end when cracks propagate to crack widths of
1.0 to 1.5 mm.
RESEARCH SIGNIFICANCE
An accurate prediction of times to maintenance and repair Measurement of crack initiation and
of RC structures requires information on when severe crack propagation
corrosion-induced cracking occurs. In addition to robust The first appearance of cracking (crack initiation) on
corrosion initiation and propagation models, a need exists for concrete surfaces was verified by frequent daily visual