Unit
0 Name fo the floor Area Total Area

0.1 GF Floor sft 12870


0.2 1st Floor sft 12870
0.3 2nd Floor sft 12870 64350
0.4 3rd Floor sft 12870
0.5 4th Floor sft 12870
A. CIVIL WORKS :
SL Description of items Unit Quantity Rate
1 Layout making sft 12870.00 1.5
2 R.C.C works for pile, concrete having minimum cylinder
crushing strength (1:1.5:3) 3000 Psi at 28 days with
Bangladeshi cement, best quantity of Sylhet sand F.M
2.5) 20mm ( ¾” ) down graded shingles including
screening, centering, pile pointing or rod in position
mixing the aggregates with mixer machine casting etc
( excluding the cost of reinforcement and its fabrication)
(Min compressive strength of cement at 7 days = 62% ) .
Supplying fabrication and fixing to details as per design
deformed bar reinforcement in concrete with straightening
and cleaning rust, if any, bending and binding in position
with supply of G.I wires etc . complete in all respect in all
floors ( 60 grade )(BSRM/KSRM/AKS)all complete as per
structural drawing & structural note.

pile work rft 19920.00 1765.00

4 pile demolishing upto 3'-0 from pile top using hammer & cft 2346.78 12.00
cleaning the pile cap area & also transfar the broken
concrete as per site engineers decision

5 Earth work in excavation of all kinds of soils of foundation cft 63359 12.00
trenches including leveling ramming and preparing the
base, bailing out water and shoring if necessary providing
center line and bench mark pillars, removing the spoils etc.

Page 1
6 Sand filling from pile cap to EGL with fine local sand cft 33725 16.00
(F.M 0.8) in 12” layer watering & consolidation each layer
upto the finished level.

7 Sand filling from EGL to plinth with fine local sand (F.M cft 26780 16.00
0.8) in 12” layer watering & consolidation each layer upto
the finished level.

8 3” thick cement concrete (1:3:6) in flooring with cement cft 1570 320.00
best quality coarse sand (F.M 1.5) & picked jhama chips
(3/4” down graded) including breaking chips screening
mixing laying compacting and curing at least for 7 days
etc . all complete .

9 R.C.C works Ready mix concrete having minimum


cylinder crushing strength 4500Psi for pile cap, column
at 28 days with centering, steel shuttering should be used,
compacting by vibrator machine and curing at least for 28
days ( excluding the cost of reinforcement and its
fabrication) (Min compressive strength of cement at 7 days
= 62% ) all complete as per structural drawing &
structural note.

pile cap cft 26363.29 420.00


Column & shear wall below Ground level cft 1700.69 480.00
GF to 1st floor level column & shear wall cft 3515.26 480.00
1st to 2nd floor level column & shear wall upto cft 6347.42 480.00
2nd to 3rd floor level column & shear wall upto cft 4585.13 480.00
3rd to 4th floor level column & shear wall upto cft 9521.12 480.00
4th to roof floor level column & shear wall upto cft 9521.12 480.00
Roof floor level column & shear wall cft 928.97 480.00
Under Ground water reservoir cft 3333.66 420.00
Grade beam cft 4189.84 420.00
Tie beam total 7 level cft 11493.81 420.00
1st floor beam cft 4336.84 420.00
2nd floor beam cft 4336.84 420.00
3rd floor beam cft 4336.84 420.00
4th floor beam cft 4336.84 420.00
Roof floor beam cft 4336.84 420.00
Corbal ground floor cft 14.82 420.00
Ground floor Stair 738.0
cft 420.00
11'-6'' level Stair 654.5
cft 420.00
23'-0'' level Stair 654.5
cft 420.00
33'-0'' level Stair 654.5
cft 420.00
43'-0'' level Stair 654.5
cft 420.00
53'-0'' level Stair 654.5
cft 420.00
63'-0'' level Stair 654.5
cft 420.00
Page 2
73'-0'' level Stair 654.5
cft 420.00
83'-0'' level Stair 654.5
cft 420.00
93'-0'' level Stair 654.5
cft 420.00
103'-0'' level Stair 654.5
cft 420.00
114'-6'' level Stair 738.0
cft 420.00
Ground floor slab cft 7132.60 350.00
1st floor slab cft 7312.50 420.00
2nd floor slab
cft 7312.50 420.00
3rd floor slab cft 7312.50 420.00
4th floor slab cft 7312.50 420.00
Roof floor slab cft 7312.50 420.00
10 Supplying fabrication and fixing to details as per design
deformed bar reinforcement in concrete with straightening
and cleaning rust, if any, bending and binding in position
with supply of G.I wires etc . complete in all respect in all
floors ( 60 grade 500W)(BSRM/KSRM/AKS)

Pile cap kg 50981.4 73.00


kg 23575.1 73.00
Below GF column & shear wall
kg 60949.2 73.00
GF TO 1st Floor column & shear wall
kg 51310.4 73.00
1st to 2nd Floor column & shear wall
kg 68039.8 73.00
2nd to 3rd Floor column & shear wall
kg 62450.3 73.00
3rd to 4th Floor column & shear wall
kg 48075.6 73.00
4th to Roof Floor column & shear wall
kg 5494.4 73.00
Roof Floor column & shear wall
kg 9341.8 73.00
Under Ground water reservoir
Ground floor Stair kg 2456.7 73.00
11'-6'' level Stair kg 2346.2 73.00
23'-0'' level Stair kg 2346.2 73.00
33'-0'' level Stair kg 2346.2 73.00
43'-0'' level Stair kg 2346.2 73.00
53'-0'' level Stair kg 2346.2 73.00
63'-0'' level Stair kg 2346.2 73.00
73'-0'' level Stair kg 2346.2 73.00
83'-0'' level Stair kg 2346.2 73.00
93'-0'' level Stair kg 2346.2 73.00
103'-0'' level Stair kg 2346.2 73.00
114'-6'' level Stair kg 2456.7 73.00
Grade beam kg 23788.0 73.00
1st floor beam kg 42053.0 73.00

Page 3
2nd floor beam kg 42053.0 73.00
3rd floor beam kg 42053.0 73.00
4th floor beam kg 42053.0 73.00
roof floor beam kg 42053.0 73.00
kg 65062.1 73.00
Tie beam total 7 level
Corbal ground floor kg 1380.63 73.00
Ground floor slab kg 15698.0 73.00
1st floor slab kg 34844.6 73.00
2nd floor slab kg 34844.6 73.00
3rd floor slab kg 34844.6 73.00
4th floor slab kg 34844.6 73.00
roof floor slab kg 34844.6 73.00
Over head water tank kg 34844.6 73.00
11 1'' thick artifical patent stone flooring 1:1.5:3 with 1/2'' sft 77220.0 45.00
down graded stone chips finishing, curring all complete
total 6 floor

11 Gf floor hardener thickness 1-2mm sft 12870.0 35.00


1st floor hardener thickness 1-2mm sft 12870.0 35.00
2nd floor hardener thickness 1-2mm sft 12870.0 35.00
3rd floor hardener thickness 1-2mm sft 12870.0 35.00
4th floor hardener thickness 1-2mm sft 12870.0 35.00
Roof floor hardener thickness 1-2mm sft 12870.0 35.00

Total Civil works A: Tk.

Page 4
OPOSED 5-STORIED FACTORY BUILDING
ETTI BANGLADESH LTD.
AT
AKBARI, ASHULIA, SAVAR, DHAKA

2,774.18

Amount
19,305.00

35,158,800.00

28,161.30

760,306.45

Page 5
539,596.32

428,480.00

502,438.55

11,072,582.63
816,330.34
1,687,326.00
3,046,759.68
2,200,860.00
4,570,139.52
4,570,139.52
445,906.60
1,400,137.20
1,759,732.58
4,827,399.15
1,821,470.83
1,821,470.83
1,821,470.83
1,821,470.83
1,821,470.83
6,226.45
309,942.68
274,869.82
274,869.82
274,869.82
274,869.82
274,869.82
274,869.82

Page 6
274,869.82
274,869.82
274,869.82
274,869.82
309,942.68

2,496,410.71
3,071,250.00
3,071,250.00
3,071,250.00
3,071,250.00
3,071,250.00

3,721,642.99
1,720,980.84
4,449,291.01
3,745,660.14
4,966,903.47
4,558,874.60
3,509,518.55
401,089.04
681,951.91
179,342.55
171,270.62
171,270.62
171,270.62
171,270.62
171,270.62
171,270.62
171,270.62
171,270.62
171,270.62
171,270.62
179,342.55
1,736,526.10
3,069,868.87

Page 7
3,069,868.87
3,069,868.87
3,069,868.87
3,069,868.87
4,749,535.85

100,785.78
1,145,951.84
2,543,657.09
2,543,657.09
2,543,657.09
2,543,657.09
2,543,657.09
2,543,657.09
3,474,900.00

450,450.00
450,450.00
450,450.00
450,450.00
450,450.00
450,450.00

178,518,216.02

Page 8
Dia of Bar length width Height spacing Number
Item Name Nos bar length (ft) with lap (ft) (ft) (ft) (in) of bar Unit weight total weight Unit
Pile Cap Work
PC1
long span bottom bar
(13'-8'') 1 25 29.67 31.17 13.67 3.5 48 1.17 1751.25 kg
long span bottom bar
(10'-0'') 1 25 29.67 31.17 10 3.5 35 1.17 1290.91 kg
short span bottom bar
(23'-8'') 1 25 23.67 25.17 23.67 3.5 82 1.17 2427.02 kg
short span bottom bar
(6'-0'') 1 25 13.67 15.17 6 3.5 22 1.17 384.08 kg
long span top bar
(13'-8'') 1 20 29.67 31.17 13.67 4 42 0.75 983.63 kg
long span top bar
(10'-0'') 1 20 23.67 25.17 10 4 31 0.75 586.12 kg
short span top bar
(13'-8'') 1 20 23.67 25.17 23.67 4 72 0.75 1361.50 kg
short span top bar
(10'-0'') 1 20 13.67 15.17 6 4 19 0.75 216.51 kg
binder 1 12 106.68 106.18 1 0.27 28.71 kg
chair 1 20 14 14 26 0.75 273.43 kg
PC2-5 nos

long span bottom bar 5 20 8.67 10.17 8.17 3.5 29 0.75 1108.15 kg

short span bottom bar 5 20 8.67 10.17 8.17 3.5 29 0.75 1108.15 kg
binder 5 12 34.68 34.68 1 0.27 46.89 kg

PC3-3 nos

long span bottom bar 3 25 10.75 12.25 10.25 4 32 1.17 1369.50 kg

short span bottom bar 3 25 10.75 12.25 10.25 4 32 1.17 1369.50 kg


Dia of Bar length width Height spacing Number
Item Name Nos bar length (ft) with lap (ft) (ft) (ft) (in) of bar Unit weight total weight Unit

binder 3 12 43 43 1 0.27 34.88 kg


PC4-3 nos

long span bottom bar 1 25 13.67 15.17 8.17 5 21 1.17 366.93 kg

short span bottom bar 1 25 8.67 10.17 13.17 5.5 30 1.17 354.93 kg
binder 1 12 44.68 44.68 1 0.27 12.08 kg
PC5-1 nos
long span bottom bar
(4'-3'') 2 25 11 12.5 4.25 5 11 1.17 328.64 kg
long span bottom bar
(3'-8'') 1 25 13.67 15.17 3.67 5 10 1.17 174.63 kg
short span bottom bar
(3'-0'') 2 25 8.67 10.17 2.92 5 8 1.17 191.18 kg
short span bottom bar
(8'-0'') 1 25 8.67 10.17 8 5 20 1.17 241.12 kg
binder 1 12 51.68 51.68 1 0.27 13.98 kg

PC6-3 nos

long span bottom bar 3 25 13.67 15.17 13.17 4.5 36 1.17 1929.37 kg

short span bottom bar 3 25 13.67 15.17 13.17 4.5 36 1.17 1929.37 kg
binder 3 12 54.68 54.68 1 0.27 44.36 kg
PC7-1 nos

long span bottom bar 1 25 13.67 15.17 13.17 4.5 36 1.17 643.12 kg

short span bottom bar 1 25 13.67 15.17 13.17 4.5 36 1.17 643.12 kg
binder 1 12 54.68 54.68 1 0.27 14.79 kg
PC8-3 nos

long span bottom bar 3 25 18.67 20.17 13.17 3.5 46 1.17 3277.93 kg
Dia of Bar length width Height spacing Number
Item Name Nos bar length (ft) with lap (ft) (ft) (ft) (in) of bar Unit weight total weight Unit

short span bottom bar 3 25 13.67 15.17 18.17 3.5 63 1.17 3381.05 kg
binder 3 12 62.68 62.68 1 0.27 50.85 kg
PC9-4 nos

long span bottom bar 4 25 18.67 20.17 13.17 3.5 46 1.17 4370.57 kg

short span bottom bar 4 25 13.67 15.17 18.17 3.5 63 1.17 4508.06 kg
binder 4 12 62.68 62.68 1 0.27 67.80 kg
PC10-1 nos

long span bottom bar 1 25 23.67 25.17 18.67 3.5 65 1.17 1920.58 kg
long span top bar 1 20 23.67 25.17 18.67 4 57 0.75 1077.89 kg

short span bottom bar 1 25 18.67 20.17 23.67 3.5 82 1.17 1944.90 kg
short span top bar 1 20 18.67 20.17 23.67 4 72 0.75 1091.04 kg
binder 2 12 84.68 84.68 1 0.27 45.80 kg
chair 1 20 14 14 26 0.75 273.43 kg

PC11-1 nos
long span bottom bar 1 25 23.67 25.17 23.17 3.5 80 1.17 2376.38 kg
long span top bar 1 20 23.67 25.17 23.17 4 71 0.75 1333.14 kg

short span bottom bar 1 25 23.67 25.17 23.17 3.5 80 1.17 2376.38 kg
short span top bar 1 20 23.67 25.17 23.17 4 71 0.75 1333.14 kg
binder 2 12 94.68 94.68 1 0.27 51.21 kg
chair 1 20 14 14 26 0.75 273.43 kg
50981.41 kg
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
Pile casting 249 78 2 61016.16 cft
Total 61016.16 cft

Pile head demolished


work 249 3 2 2346.78 cft

Earth filling 1 33724.77 cft


Sand filling 1 13390 2 26780.00 cft
Pile Cap work Earth
Excavation
PC1 for (13'-8'') 1 31.67 15.67 7.5 3722.02 cft
PC1 for (10'-0'') 1 23.67 11 7.5 1952.78 cft
PC2 5 10.67 10.67 7.5 4269.33 cft
PC3 3 12.75 12.75 7.5 3657.66 cft
PC4 1 15.67 10.67 7.5 1253.99 cft
PC5(3'-8'') 1 15.67 4.67 7.5 548.84 cft
PC5 (2x4'-3'') 1 15.67 9.5 7.5 1116.49 cft
PC6 3 15.67 15.67 7.5 5524.85 cft
PC7 1 15.67 15.67 7.5 1841.62 cft
PC8 3 20.67 15.67 7.5 7287.73 cft
PC9 4 20.67 15.67 7.5 9716.97 cft
PC10 1 25.67 20.67 7.5 3979.49 cft
PC11 1 25.67 25.67 7.5 4942.12 cft
UGWR 1 63 20 10.75 13545.0 cft
Total 63358.87 cft
Pile Cap work C.C
PC1 for (13'-8'') 1 29.67 13.67 0.25 101.40 cft
PC1 for (10'-0'') 1 23.67 10 0.25 59.18 cft
PC2 5 8.67 8.67 0.25 93.96 cft
PC3 3 10.75 10.75 0.25 86.67 cft
PC4 1 13.67 8.67 0.25 29.63 cft
PC5(3'-8'') 1 13.67 3.67 0.25 12.54 cft
PC5 (2x4'-3'') 1 13.67 8.25 0.25 28.19 cft
PC6 3 13.67 13.67 0.25 140.15 cft
PC7 1 13.67 13.67 0.25 46.72 cft
PC8 3 18.67 13.67 0.25 191.41 cft
PC9 4 18.67 13.67 0.25 255.22 cft
PC10 1 23.67 18.67 0.25 110.48 cft
PC11 1 23.67 23.67 0.25 140.07 cft
UGWR C.C 1 61 18 0.25 274.5 cft
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
Total 1570.12 cft
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
Pile Cap work R.C.C
PC1 for (13'-8'') 1 29.67 13.67 5.5 2230.74 cft
PC1 for (10'-0'') 1 23.67 10 5.5 1301.85 cft
PC2 5 8.67 8.67 3.5 1315.46 cft
PC3 3 10.75 10.75 3.5 1213.41 cft
PC4 1 13.67 8.67 3.67 434.96 cft
PC5(3'-8'') 2 13.67 3.67 4.17 418.41 cft
PC5 (2x4'-3'') 2 13.67 8.25 4.17 940.56 cft
PC6 3 13.67 13.67 4.33 2427.43 cft
PC7 1 13.67 13.67 4.67 872.68 cft
PC8 3 18.67 13.67 5.33 4080.95 cft
PC9 4 18.67 13.67 5.5 5614.82 cft
PC10 1 23.67 18.67 5.5 2430.55 cft
PC11 1 23.67 23.67 5.5 3081.48 cft
Total 26363.29 cft

Column base to GB
C1 6 2.33 1.92 4 107.4 cft
C2 6 2.75 1.92 4 126.7 cft
C3 1 3.58 1.92 4 27.5 cft
C4 4 2.33 2.33 4 86.9 cft
C5 5 2.75 2.75 3 113.4 cft
C5A 1 2.75 2.75 3 22.7 cft
C6 7 3.58 2.75 3 206.7 cft
Shear Wall-1 2 53.5 1.25 5 668.8 cft
Shear Wall-2 1 54.5 1.25 5 340.6 cft
total 1700.7 cft
Column GB to 1st
floor
C1 6 2.08 1.67 23 479.4 cft
C2 6 2.5 1.67 23 576.2 cft
C3 1 3.33 1.67 23 127.9 cft
C4 4 2.08 2.08 23 398.0 cft
C5 5 2.5 2.5 23 718.8 cft
C5A 1 2.5 2.5 23 143.8 cft
C6 7 3.33 2.5 23 1340.3 cft
3784.3
Shear Wall-1 2 37.82 1.25 23 2174.7 cft
Shear Wall-2 1 46.63 1.25 23 1340.6 cft
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
total 3515.3 cft
Column 1st to 2nd
floor
C1 6 2.08 1.67 20 416.8 cft
C2 6 2.5 1.67 20 501.0 cft
C3 1 3.33 1.67 20 111.2 cft
C4 4 2.08 2.08 20 346.1 cft
C5 5 2.5 2.5 20 625.0 cft
C5A 1 2.5 2.5 20 125.0 cft
C6 7 3.33 2.5 20 1165.5 cft
Shear Wall-1 2 37.82 1.25 20 1891.0 cft
Shear Wall-2 1 46.63 1.25 20 1165.8 cft
total 6347.4 cft
Column 2nd to 3rd
floor
C1 6 2.08 1.67 30 625.2 cft
C2 6 2.5 1.67 30 751.5 cft
C3 1 3.33 1.67 30 166.8 cft
C4 4 2.08 2.08 30 519.2 cft
C5 5 2.5 2.5 30 937.5 cft
C5A 1 2.5 2.5 30 187.5 cft
C6 7 3.33 2.5 30 1748.3 cft
4936.0
Shear Wall-1 2 37.82 1.25 30 2836.5 cft
Shear Wall-2 1 46.63 1.25 30 1748.6 cft
total 4585.1 cft
Column 3rd to 4th
floor
C1 6 2.08 1.67 30 625.2 cft
C2 6 2.5 1.67 30 751.5 cft
C3 1 3.33 1.67 30 166.8 cft
C4 4 2.08 2.08 30 519.2 cft
C5 5 2.5 2.5 30 937.5 cft
C5A 1 2.5 2.5 30 187.5 cft
C6 7 3.33 2.5 30 1748.3 cft
Shear Wall-1 2 37.82 1.25 30 2836.5 cft
Shear Wall-2 1 46.63 1.25 30 1748.6 cft
Total 9521.1 cft
Column 3rd to 4th
floor
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
C1 6 2.08 1.67 23 479.4 cft
C2 6 2.5 1.67 23 576.2 cft
C3 1 3.33 1.67 23 127.9 cft
C4 4 2.08 2.08 23 398.0 cft
C5 5 2.5 2.5 23 718.8 cft
C5A 1 2.5 2.5 23 143.8 cft
C6 7 3.33 2.5 23 1340.3 cft
Shear Wall-1 2 37.82 1.25 23 2174.7 cft
Shear Wall-2 1 46.63 1.25 23 1340.6 cft
Total 7299.5 cft
Column roof floor
C1 1 2.08 1.67 13.25 46.0 cft
C2 2 2.5 1.67 13.25 110.6 cft
Shear Wall-2 1 46.63 1.25 13.25 772.3 cft
Total 929.0 cft

Grade beam
GB1 1 40.08 2.08 3.33 277.6 cft
GB2 1 40.08 2.08 3.33 277.6 cft
GB3 1 14.25 1.25 2.08 37.1 cft
GB4 1 40.08 2.08 3.33 277.6 cft
GB5 1 29.92 1.25 2.08 77.8 cft
GB6 1 14.67 1.25 2.08 38.1 cft
GB7 1 27.67 1.25 2.08 71.9 cft
GB8 1 40.08 2.08 3.33 277.6 cft
GB9 1 55.67 1.25 2.08 144.7 cft
GB10 1 40.08 2.08 3.33 277.6 cft
GB11 1 56.5 1.25 2.08 146.9 cft
GB12 1 13.33 2.08 3.33 92.3 cft
GB13 1 28 1.25 2.08 72.8 cft
GB14 1 32 1.25 2.08 83.2 cft
GB15 1 161.25 1.25 2.08 419.3 cft
GB16 1 150 1.25 2.08 390.0 cft
GB17 1 164 1.25 2.08 426.4 cft
GB18 1 88 1.25 2.08 228.8 cft
GB19 1 63.25 1.25 2.08 164.5 cft
GB20 1 9.75 1.25 2.08 25.4 cft
GB21 1 102.17 1.25 2.08 265.6 cft
GB22 1 12 1.25 2.08 31.2 cft
GB23 1 28 1.25 2.08 72.8 cft
GB24 1 5 1.25 2.08 13.0 cft
Total 4189.8 cft
Typical floor beam
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
FB1 1 42.58 1.67 1.875 133.3 cft
FB2 2 53 1.25 1.875 248.4 cft
FB3 1 52.75 1.67 1.875 165.2 cft
FB4 1 40.08 1.67 1.875 125.5 cft
FB5 1 29 1.25 1.875 68.0 cft
FB6 1 24.17 1.25 1.875 56.6 cft
FB7 1 13.5 1.25 1.17 19.7 cft
FB8 1 67.33 1.25 1.875 157.8 cft
FB9 1 28.67 1.67 1.875 89.8 cft
FB10 1 94.25 1.67 1.875 295.1 cft
FB11 1 94.17 1.25 1.875 220.7 cft
FB12 1 95.08 1.67 1.875 297.7 cft
FB13 1 12.08 1.25 1.875 28.3 cft
FB14 2 13.5 1.25 1.17 39.5 cft
FB15 1 33.75 1.25 1.875 79.1 cft
FB15A 1 14.67 1.25 1.875 34.4 cft
FB15B 2 13.5 1.25 1.17 39.5 cft
FB16 1 12 1.25 1.875 28.1 cft
FB17 1 13.5 1.25 1.875 31.6 cft
FB17A 1 32 1.67 1.875 100.2 cft
FB18 1 168.25 1 1.42 238.9 cft
FB19 1 154 1.67 1.875 482.2 cft
FB20 1 19.75 1.25 1.875 46.3 cft
FB21 1 164.25 1.67 1.875 514.3 cft
FB22 1 20.75 1.25 1.875 48.6 cft
FB23 1 89 1.67 1.875 278.7 cft
FB24 1 61.17 1.67 1.875 191.5 cft
FB25 1 12 1.25 1.875 28.1 cft
FB26 1 79.67 1.67 1.875 249.5 cft
Total 4336.8 cft
TIE BEAM -01 1 445.33 1 2 890.7 cft
TIE BEAM -02 1 195.33 1.25 2.5 610.4 cft
TIE BEAM -03 1 67.5 1.25 1.67 140.9 cft
1642.0 cft

UGWR R.C.C
BASE 1 61 18 1 1098.0 cft
SIDE WALL 1 162 10.5 1 1701.0 cft
top slab 1 57 14 0.67 534.7 cft
3333.7 cft

Stair-1 1 st flight
Waist slab 1 22.25 7.5 10 139.1 cft
length width Height/ Thickness
Item Name Nos (ft) (ft) Dia (ft) (in) Volume Unit
step 18 7.5 0.83 6 28.0 cft
Stair-1 2nd flight
Waist slab 1 19.02 7.5 9 107.0 cft
step 6 7.5 0.83 6 9.3 cft
Total 283.4 cft
Stair-2 1 st flight
Waist slab 1 18.33 7.5 9 103.1 cft
step 12 7.5 0.83 6 18.7 cft
Stair-2 2nd flight
Waist slab 1 19.5 7.5 9 109.7 cft
step 12 7.5 0.83 6 18.7 cft
Total 250.1 cft
Stair-3 1 st flight
Waist slab 1 23.58 5.5 7 75.7 cft
step 14 5.5 0.83 6 16.0 cft
Stair-3 2nd flight
Waist slab 1 21.57 5.83 6.5 68.1 cft
step 10 5.5 0.83 6 11.4 cft
Total 171.2 cft
Stair-3 3rd flight
Waist slab 1 22.73 5.5 6 62.5 cft
step 11 5.5 0.83 6 12.6 cft
Stair-3 4th flight
Waist slab 1 22.83 5.83 6 66.5 cft
step 11 5.5 0.83 6 12.6 cft
Total 154.2 cft
Over Head water
reservoir
Side wall 1 80 8 10 533.3 cft
top & bottom wall 1 80 8 10 533.3 cft

Ground floor slab


slab 1 164.25 52.75 8 5776.1 cft
slab 1 102.17 39.83 8 1356.5 cft
7132.6 cft
LIFT Machine room 3 24.17 13.5 12 978.9 cft
Thickness
Item Name Nos length Unit (in) Volume Unit

1ST Floor 11700 sft 7.5 7313 cft