Sunteți pe pagina 1din 1

SCHEDULE DIRECT HIRE

PT. INWHA INDONESIA


Engineering & Construction

Date : 19 Sept 2013


Rev. : 00
Sept 13 Oct 13 Nov 13
No Description
W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 Remarks

5 5 5 5 Man Power
1 ADMIN BUILDING

Painting and Finishing

4 4 Man Power
2 PDB

Pouring Floor and Coating

Painting

24 24 10 10 Man Power
3 ROAD AND YARD

Road and Yard

8 8 12 12 12 8 8 8 Man Power
4 DRAINAGE

Drainage East

Drainage Infront Dispatch 1

Drainage Infront Cooling Tower

Drainage Other

5 STEEL STRUCTURE 19 19 19 19 19 19 Man Power

Canopy

Cooling Tower

Grating Machine Pit Fabrication

False Floor Fabrication

False Floor Installation

Platform

19 19 19 19 19 19 Man Power
6 EQUIPMENT

Upsetter

Mezzanine

Rake

Recovery

Furnace

Recycling

Feed Bar ramp

Quench Drum

8 8 10 10 10 10 Man Power
PIPING

1 Piping GA

2 Isometric

3 MTO

4 Procurement

5 Installation

Cooling Tower

Furnace

Compressed Air and Clean Water

Non Drinking Water

Fire Fighting

Small Bore

6 Test Package

87 87 75 75 60 56 8 8 0 0
TOTAL MAN POWER