Sunteți pe pagina 1din 3

Our ref: SIN1111514-13-3-25 05 FEBRUARY 2018

By email Themed Attractions Resorts & Hotels Sdn. Bhd


Level 8, Surian Tower
No. 1, Jaln PJU 7/3, Mutiara Damansara
47810 Petaling Jaya, Selangor Darul Ehsan
Malaysia

Attn: Mr. Mark Muhinder

Dear Sir,
RE: CADANGAN MEMBINA SEBUAH PUSAT PAMERAN BERSERTA
KEMUDAHAN BERKAITAN DAN TEMPAT LETAK KERETA DI LANTAI
ARAS BAWAH DI ATAS SEBAHAGIAN PTD 2486, PTD 2487, PTD 2488
DAN PTD 2489, MUKIM PANTAI TIMUR, DAERAH KOTA TINGGI, JOHOR
DARUL TAKZIM UNTUK TETUAN DESARU DEVELOPMENT
CORPORATION SDN BHD.

RECOMMENDATION FOR CONTRACTOR’S INTERIM PAYMENT


CERTIFICATE NO. 30

Reference to matter above, we would like to advise that the mechanical and electrical
works undertaken in MRCB’s Interim Payment Certificate No. 30 has been satisfactorily
completed in accordance to the contract drawings and specifications.

Your kind attention to this matters are highly appreciated. We trust all is in order.

Thank you.

Yours faithfully,

M C Kwang
Project Director
For WSP Ng Pte Ltd

MCK/lch

Enc

Cc: Mr. Megat / Hakim - TARH


Mr. Ahmad Fauzi - AJM
Mr. Wong YF / Mr. Fadli - BES
Mr. Zazali / Mr. Tuan Ikram - KPK
Mr. Chan / Mr. Shamudin - MRCB

WSP NG Pte. Ltd.


Co. Reg. No.199600928H
300 Beach Road
#05-00 The Concourse
Singapore 199555

T+ 65 6533-7333
F+ 65 6533-7707
www.wsp.com
WSP Consultancy Pte. Ltd.
Co. Reg. No.198403250N
300 Beach Road
#05-00 The Concourse
Singapore 199555

T+ 65 6533-7333
F+ 65 6533-7707
www.wsp.com

Notice of Valuation

To KPK Quantity Surveyors Sdn Bhd NOV No 1111514-CC-NOV25

Attention Mr Zazali Date 05 February 2018

From Mr M.C. Kwang Subject Contractor’s Interim Claim No.25 - M&E


PRO

Project The Conference Centre Project No SIN1111514


Contract Main Contract – M&E Services No. of pages 2
Copies TAR&H – Mr. Chew, Mr. Hakim, Mr. Megat

Statement of MRCB – Contractor Interim Claim No.30 (No.25-M&E) as of 25 January 2018


Extract from Prime Cost and Provisional Sums – Interim Claim No.25 (M&E)
Contract Amount Work Done Previous Current Total Claim
(RM) % (RM)

PRIME COST SUM


B Lift Services
462,330.00 90% 416,097.00 - 416,097.00
Profit 4,623.30 90% 4,160.97 - 4,160.97
Attendance 13,500.00 90% 12,150.00 - 12,150.00

Sub-Total for Item B 480,453.30 432,407.97 - 432,407.97

Interim Claim No. 25 (M&E) – Summary


Contract Amount Work Done Previous Current Total Claim
(RM) % (RM)

1 PC and Provisional Sum 20,358,250.00 2.12% 432,407.97 - 432,407.97

2 Main Summary of M&E Works 11,016,000.00 95.50% 10,090,962.52 428,866.14 10,519,828.66

3 Material on Site Incl. in item 2

Total Claims for M&E 10,952,236.63

MC Kwang
Project Leader’s Name Signature Date

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for its intended purpose. Any
unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly prohibited. If you have received this document in error or by any
means other than as authorised addressee, please notify us immediately and we will arrange for its return to us.
WSP Ng Assessment of Work Completed as at 25 January 2018
Under Prime Cost and Provisional Sums – Interim Claim No. 25
Contract Amount Work Done Previous Current Total Claim
(RM) % (RM)

PRIME COST SUM


B Lift Services
462,330.00 90% 416,097.00 - 416,097.00
Profit 4,623.30 90% 4,160.97 - 4,160.97
Attendance 13,500.00 90% 12,150.00 - 12,150.00

Sub-Total for Item B 480,453.30 432,407.97 - 432,407.97

Interim Claim No.25 – Summary


Contract Amount Work Previous Current Total Claim
(RM) Done % (RM)

1 PC and Provisional Sum 20,358,250.00 2.12% 432,407.97 - 432,407.97


2 Main Summary M&E Works 11,016,000.00 92.74% 10.047,515.22 168,210.12 10,215,725.34

Total Claims for M&E 10,648,133.31

Notes:
1. WSP Assessment excludes GST.

MC Kwang
Project Leader’s Name Signature Date

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for its intended purpose. Any
unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly prohibited. If you have received this document in error or by any
means other than as authorised addressee, please notify us immediately and we will arrange for its return to us.

S-ar putea să vă placă și