STF PALONG TIMUR REV.00 RUN ALL BS 12.05.2018 341.0d 155.0d -136.0d 02-Oct-17 08:00 08-Nov-18 08:00 98.51% 60.7%
AM A AM
Milestone 341.0d 0.0d -136.0d 02-Oct-17 08:00 AM A
08-Nov-18 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -136.0d 08-Nov-18 08:00 AM08-Nov-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
External Finishes 18.0d 18.0d -58.0d 09-Jun-18 08:00 AM 28-Jun-18 05:00 PM 100% 0%
A1350 External plastering & painting 18.0d 18.0d -58.0d 09-Jun-18 08:00 AM 28-Jun-18 05:00 PM 100% 0%
Internal Floor & Wall Finishes 18.0d 18.0d -58.0d 09-Jun-18 08:00 AM 28-Jun-18 05:00 PM 100% 0%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 18.0d -58.0d 09-Jun-18 08:00 AM 28-Jun-18 05:00 PM 100% 0%
Ceiling Finishes 18.0d 18.0d -58.0d 30-Jun-18 08:00 AM 19-Jul-18 05:00 PM 100% 0%
A1370 Install frame, ceiling & painting 18.0d 18.0d -58.0d 30-Jun-18 08:00 AM 19-Jul-18 05:00 PM 100% 0%
Pipeworks 166.0d 48.0d -46.0d 20-Dec-17 08:00 AM05-Jul-18
A 05:00 PM 100% 82.5%
A1550 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -40.0d 16-Jun-18 08:00 AM 28-Jun-18 05:00 PM 100% 0%
Existing Sedimentation Tank 178.0d 48.0d -46.0d 06-Dec-17 08:00 AM05-Jul-18
A 05:00 PM 100% 65.22%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM30-Mar-18
A 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
Installation 48.0d 48.0d -46.0d 13-May-18 08:00 AM05-Jul-18 05:00 PM 100% 0%
A1580 Submersible Sludge Pump 24.0d 24.0d -46.0d 13-May-18 08:00 AM07-Jun-18 05:00 PM 100% 0%
A1590 Pipes, Fittings & Valves 24.0d 24.0d -46.0d 09-Jun-18 08:00 AM 05-Jul-18 05:00 PM 100% 0%
Polymer Plant 262.0d 132.0d -130.0d 06-Dec-17 08:00 AM11-Oct-18
A 05:00 PM 98.56% 41.03%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 60.0d -70.0d 06-Dec-17 08:00 AM19-Jul-18
A 05:00 PM 100% 70%
A1610 Metering Pumps (Diaphragm type) 60.0d 60.0d -130.0d 06-Dec-17 08:00 AM19-Jul-18
A 05:00 PM 100% 70%
A1620 Crane / Lifting Equipment 30.0d 30.0d -40.0d 06-Dec-17 08:00 AM14-Jun-18
A 05:00 PM 100% 70%
A1630 Static Mixer & Sludge Blender 30.0d 30.0d -40.0d 06-Dec-17 08:00 AM14-Jun-18
A 05:00 PM 100% 70%
Fabrication 36.0d 36.0d -106.0d 02-May-18 08:00 AM30-Aug-18
A 05:00 PM 100% 40%
A1640 Mixing & Service Tank 36.0d 36.0d -130.0d 02-May-18 08:00 AM30-Aug-18
A 05:00 PM 100% 40%
A1650 Hopper, Feeder & Pump Skid 36.0d 36.0d -130.0d 02-May-18 08:00 AM30-Aug-18
A 05:00 PM 100% 40%
A1660 Local Control Panel 30.0d 30.0d -100.0d 02-May-18 08:00 AM23-Aug-18
A 05:00 PM 100% 40%
Installation 36.0d 36.0d -130.0d 01-Sep-18 08:00 AM11-Oct-18 05:00 PM 94.44% 0%
A1670 Mixing & Service Tank 24.0d 24.0d -130.0d 01-Sep-18 08:00 AM27-Sep-18 05:00 PM 100% 0%
A1680 Hopper, Feeder & Pump Skid 24.0d 24.0d -130.0d 01-Sep-18 08:00 AM27-Sep-18 05:00 PM 100% 0%
A1690 Dosing Pipeworks 24.0d 24.0d -130.0d 01-Sep-18 08:00 AM27-Sep-18 05:00 PM 100% 0%
A1700 Local Control Panel 12.0d 12.0d -130.0d 29-Sep-18 08:00 AM11-Oct-18 05:00 PM 83.33% 0%
A1710 Crane / Lifting Equipment 12.0d 12.0d -130.0d 29-Sep-18 08:00 AM11-Oct-18 05:00 PM 83.33% 0%
A1720 Static Mixer & Sludge Blender 12.0d 12.0d -130.0d 29-Sep-18 08:00 AM11-Oct-18 05:00 PM 83.33% 0%
Pipeworks 172.0d 30.0d -35.0d 20-Dec-17 08:00 AM12-Jul-18
A 05:00 PM 100% 30.77%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
A1730 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
Installation 24.0d 24.0d -46.0d 09-Jun-18 08:00 AM 05-Jul-18 05:00 PM 100% 0%
A1740 Excavation & backfilling works 24.0d 24.0d -46.0d 09-Jun-18 08:00 AM 05-Jul-18 05:00 PM 100% 0%
A1750 Pipe laying & jointing 24.0d 24.0d -46.0d 09-Jun-18 08:00 AM 05-Jul-18 05:00 PM 100% 0%
Testing 6.0d 6.0d -35.0d 07-Jul-18 08:00 AM 12-Jul-18 05:00 PM 100% 0%
A1760 Cleaning & testing works 6.0d 6.0d -35.0d 07-Jul-18 08:00 AM 12-Jul-18 05:00 PM 100% 0%
Miscellaneous Works 208.0d 90.0d -88.0d 20-Dec-17 08:00 AM23-Aug-18
A 05:00 PM 100% 63.56%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
Procurement 61.0d 60.0d -97.0d 13-Jan-18 08:00 AM 1
A9-Jul-18 05:00 PM 100% 85.28%
A1780 Booster Pump 30.0d 30.0d -97.0d 13-Jan-18 08:00 AM 1
A4-Jun-18 05:00 PM 100% 70%
A1790 Air Compressor Set 30.0d 0.0d 13-Jan-18 08:00 AM 0
A3-May-18 05:00 PM A 100% 100%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 30.0d -97.0d 13-Jan-18 08:00 AM 1
A4-Jun-18 05:00 PM 100% 90%
A1810 Portable Water jet 12.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Apr-18 05:00 PM A 100% 100%
A1820 Penstock & Valves 60.0d 60.0d -97.0d 13-Jan-18 08:00 AM 1
A9-Jul-18 05:00 PM 100% 80%
A1830 FAT Penstock / Valves 1.0d 0.0d 26-Mar-18 08:00 AM26-Mar-18
A 05:00 PM A 100% 100%
Installation 60.0d 60.0d -88.0d 16-Jun-18 08:00 AM 23-Aug-18 05:00 PM 100% 0%
A1840 Booster Pump Set 18.0d 18.0d -76.0d 16-Jun-18 08:00 AM 05-Jul-18 05:00 PM 100% 0%
A1850 Air Compressor Set 18.0d 18.0d -76.0d 16-Jun-18 08:00 AM 05-Jul-18 05:00 PM 100% 0%
A1860 Penstock / Valves 30.0d 30.0d -88.0d 21-Jul-18 08:00 AM 23-Aug-18 05:00 PM 100% 0%
Electrical Works 253.0d 138.0d -136.0d 08-Nov-17 08:00 AM18-Oct-18
A 05:00 PM 100% 62.02%
Training, Testing, Commissioning & Maintenance 17.0d 17.0d -136.0d 20-Oct-18 08:00 AM 07-Nov-18 05:00 PM 0% 0%
A2070 Preparation of testing & report 12.0d 12.0d -136.0d 20-Oct-18 08:00 AM 01-Nov-18 05:00 PM 0% 0%
A2080 Pre-commissioning 6.0d 6.0d -136.0d 20-Oct-18 08:00 AM 25-Oct-18 05:00 PM 0% 0%
A2090 Setting to work 3.0d 3.0d -136.0d 27-Oct-18 08:00 AM 29-Oct-18 05:00 PM 0% 0%
A2100 Commissioning & training 7.0d 7.0d -136.0d 30-Oct-18 08:00 AM 06-Nov-18 05:00 PM 0% 0%
A2110 Handing over to Client 1.0d 1.0d -136.0d 07-Nov-18 08:00 AM07-Nov-18 05:00 PM 0% 0%