History ........................................................................................ 5
Mission 5
Storage ......................................................................................... 9
General 9
Rocket motors 9
Balloon preparation buildings ........................................................ 11
The “Chapel” building 11
The “Cathedral” building 11
The “Basilica” building 11
Instrumentation ........................................................................ 11
Telemetry 11
P-band Tracking Equipment 11
L/S-band Tracking Equipment 11
DLR L/S-band Tracking Equipment 12
S/X-band Tracking Equipment 12
Receivers 12
Data Extraction 12
Video switching 12
PCM Decommutation 12
Magnetic Tape Recording 12
Telescience 12
TV centre 12
Output Products 13
Digital Media 13
Analogue Tapes 13
Video Tapes 13
Frequency Plan 13
Trajectory Determination 13
DLR C-band Radar 13
Ranging System 13
Communications 13
Intercom System 13
GO/NOGO System 13
Video Message System 13
External Communications 13
Timing System 13
Time Code Signals 13
Reference Frequencies 14
Telecommand System for Sounding Rockets 14
ESC-Antenna 14
Telecommand System For Balloons 14
Modulating Signals 14
Specifications ................................................................................. 15
P-band Tracking Equipment 15
L/S-band Tracking Equipment 15
DLR L/S-band Tracking Equipment 15
S/X-band Tracking Equipment 15
Receivers 15
Video Characteristics 15
Diversity Combiner, Microdyne 3200-PC 15
Microdyne Mod. 700 MR 15
Video Characteristics 16
Diversity Combiner, Microdyne 1620-PC 16
Microdyne Mod. 700 MRB 16
Video Characteristics 16
Diversity Combiner, Microdyne 1620-PCB 16
Cortex RTR receiver and combiner 16
Video Characteristics Combiner and Receiver 16
Video Characteristics Bit synchronizer 16
SSC-C1000 16
Video characteristics 16
PCM Video Switching 16
PCM Decommutation 16
FM Discrimination 17
Subcarrier Discriminator, Astrodata 404 17
Tunable Discriminator, EMR Model 229 17
Magnetic Tape Recording 17
Frequency Plan 17
DLR C-band Radar 18
Ranging System 18
Timing System 18
Telecommand System 18
ESC-Antenna 18
Telecommand System 18
Modulating Signals 18
Homing Beacon 19
Safety ........................................................................................ 20
General 20
Scheduling 20
Operational Support 20
Recovery of Rockets and Payloads 20
Safety Organization 20
Restricted Areas 20
Rocket Launching Area 20
Balloon Launching Area 21
Radar Stations 21
Operations Centre and Scientific Centre 21
Rocket Flight Safety 21
Acceptance of New Rocket Types 21
Nominal Impact Point 21
Balloon Flight Safety 21
Explosives 21
Dangerous Equipment 21
Operational support for Sounding rocket and balloon 21
Approval to Use the Range 22
History regions and location of ground based instrumenta-
tion.
In March, 1964, ESRO - the European Space Re- Arena Arctica is a very large hangar at Kiruna Air-
search Organisation - was founded by Belgium, port. The main purpose of the hangar is to support
Denmark, France, the Netherlands, Italy, Swit- scientific measurements by aircraft.
zerland, Spain, the United Kingdom, Sweden and
Germany. The aim was to establish a co-ordinated Range Area
programme for peaceful space research, combined The Esrange premises are located in an area of 20
with advanced research technological development, km2 about 40 km east of Kiruna. The Main Build-
and to support European industry in the mem- ing area is located in the Vittangi river valley and
ber countries. Esrange Space Center was built by comprises the Main Building, the Telecom building,
ESRO and inaugurated in 1966. A great number of Hotel Aurora and garages. Close to the main build-
rocket projects were executed between November ing area is the area for balloon launchings including
1966 and June 1972, mainly by ESRO. However, three buildings for operations control and payload
the member states of ESRO also carried out rocket preparation.
projects from Esrange on a national basis.
Further east is the launching area for rockets, which
Since July 1, 1972, Esrange has been managed includes a blockhouse, rocket and payload prepara-
by the SSC. The rocket and balloon activities are tion halls, chemical laboratories and launch pads.
co-ordinated and financed by the Esrange Andøya The satellite receiving station and a GPS reference
Special Project (EASP) within ESA (European Space station are situated on top of a hill 2 km southwest
Agency). The member states of ESA/EASP are to- of the Main Building. A ground observation station,
day (1999) France, Germany, Switzerland, Norway KEOPS (Kiruna Esrange Optical Platform System),
and Sweden. In 1974 Esrange completed a launch- is located on another hilltop about 1 km further
ing facility for scientific balloons. This facility has west.
been continuously upgraded to enable launchings of
1,000,000 m3 balloons. Esrange plays, since 1978,
an important role in various satellite projects. A
number of ground segments for the support of na-
tional and international spacecraft programmes are
now in operation.
Mission
The assigned missions of Esrange, for sounding
rockets and balloons are:
-Support of the sounding rocket and balloon pro-
grammes of the member states of ESA/EASP. Non-
members can use the facilities on a second priority
basis.
-Operation of ground based scientific instrumenta-
tion.
loads. Zone C is not allowed for use during the pe- ing your leisure time very pleasant. For instance,
riod May 1 - September 15. The nominal impact you can watch satellite TV, play billiards, table ten-
point normally chosen is situated 75 km north of nis or darts, and have a sauna bath. For outdoor
the launch pads. The impact area for balloons cov- activities like hiking, fishing, or cross-country ski-
ers the northern parts of Sweden, Norway, Finland, ing, all necessary equipment can be borrowed from
Russia, Canada and Alaska. Esrange. During winter, a 3.5 km specially prepared
cross-country ski track is available.
Central Complex
The Main Building was erected in 1964-65. It has Conference rooms
four storeys with a total floor area of 3,930 m2. The There are four conference rooms in the main build-
ground floor houses offices for Esrange administra- ing and two in the hotel. They are all equipped with
tion and technical facilities, a front desk, a switch- data video projection and one of the conference
board, a canteen, two conference rooms for 15 and rooms has world-wide video conferencing.
30 persons and a lounge. The conference rooms hold seats from 12 up to 70
persons.
The first floor has offices for operational staff, the
operations centre for sounding rockets and rooms Environmental Conditions
for timing, telemetry and scientific instruments
(Scientific Centre). In an annex on the same floor Climatology
there are offices. The top floor (second floor) has Esrange has a typical continental climate with cold
a large conference room for about 70 persons, winters and relatively warm summers. The precipi-
and offices. The Main Building area also includes a tation and humidity are relatively low all year. Snow
warehouse with a total area of 490 m2, warm and begins to fall by late September, and normally by
cold garages for cars and accommodation, a Hotel mid-October the ground is covered and the lakes
with 59 single rooms and 20 double rooms, sauna, are frozen. The 24 hour average temperature falls
training facilities and kitchens. below 0° C in early October and stays below until
the beginning of May. During the coldest months,
Staying at Esrange December, January and February, the average
temperature is normally around -15°C. However,
The central complex includes all facilities that are a low of - 48° C has been recorded. During winter
necessary for a pleasant stay at Esrange. the temperature at the radar hill is generally 10°C
higher than in the valley.
Accommodation
Hotel rooms are located close to the Main Building By the end of May the snow and ice disappear. Sum-
where most people meet. Users and visitors are mer temperatures are in the 10° to 18° C range,
kindly requested to inform Esrange well in advance rising occasionally to 30°C. Mosquitoes are preva-
about their preferences regarding accommodation. lent throughout the summer and the use of repel-
lents is advisable. From a medical point of view
Restaurant the arctic mosquitoes are harmless as they do not
The restaurant has good quality and service. It spread any diseases.
is open during normal working hours and during
the launching operations. In addition to breakfast, The number of clear days varies during the year.
lunch and - during campaigns or upon special re- The probability of a clear sky or very few clouds
quests - dinner, our restaurant offers various kinds is highest (about 50 %) in January through March
and lowest in September through November (about
20 %). Fog can occur in the Vittangi valley before
the river freezes in October - November, otherwise
fog is rarely seen. More detailed weather statistics
are available at Esrange.
Rocket facilities
The rocket facilities are located in an area 1000 m
east of the Main Building. All operations that are
required from storage to preparation, assembly, in-
tegration, testing and launch of rockets with com-
plicated payloads are performed in this area. Due
to launch operations or other hazardous operations
the road to the area can be closed, and only a lim-
of beverages, including beer, wine and liquors. ited number of personnel are allowed to work there
Special requirements regarding the opening hours, during these operations. From November 1966
special dishes, etc, can normally be fulfilled. more than 500 rockets have been launched from
Esrange.
Recreation
Within Esrange, there are many possibilities of mak-
Work areas and equipment and telephone are available.
Two surface tables of the accuracy ± 30 microns,
Offices each 2 m by 1.5 m, level with respect to each other
Three offices in the laboratory annex are available are installed. The distance between the tables is
to the users. They are situated in close connec- 3 m. The access door is 4.05 m high and 4.52 m
tion to the payload assembly hall. Three more of- wide.
fices are available in the main entrance corridor.
Each office is equipped with standard furniture, tel- Gantry crane:
ephone and Internet access. There is also a small Max. load: 2000 kg
common space and lavatories in both areas. Near Hoist speeds: 100 mm/sec and 10 mm/sec
the main entrance there is a well-equipped kitchen Max. height to the hook: 3.95 m
and a TV/Conferenceroom for convenience.
Laboratories
Payload assembly Apart from standard tools and instruments, a vari-
This hall has a floor area of 10.5 m by 20 m and ety of equipment for laboratory work, is available
a height of 3.9 m, except for the central portion, for use.
which has a higher ceiling to allow vertical assem- Four laboratories are available for advanced chemi-
bly long payloads. A single rail electric gantry crane cal work. They are all equipped with gas, warm and
is installed for payload handling. If required, the cold water, fume hoods, laminar air flow cupboards
area can be divided into sections by means of mov- - horizontal or vertical -, refrigerators, deepfreezes,
able screen-walls. The area is equipped with work- and lockable cupboards to store poisonous materi-
benches some with electric power outlets. Single als. One chemical laboratory is equipped with gas,
phase and three phase power and also two cold warm and cold water, and a fume hood. One elec-
water supplies are available. The main access door tronic laboratory is reserved for the launch crew.
to the hall is 4.08 m high and 3.81 m wide.
Equipment:
Electric power: • a high-temperature 3 litre oven. Thermo
230 V, 50 Hz single phase stat controlled up to 1,200° ± 1°C
110 V, 50 Hz single phase, • a vacuum medium-temperature 130
15 KVA 400 V and 200 V, 50 Hz three phase litre oven 1 mbar thermostat controlled up
to 250°C. (LeyboldHeraeus VT5050EK)
Gantry crane: • an oil-diffusion pump, 10-6 mbar (Edwards
Max. load: 1000 kg diffstak CR100/300M)
Hoist speeds: 100 mm/sec and 10 mm/sec. • a turbomolecular pump, 10-6 mbar (Balzer
Max. height to the hook: 7 m. TSU170)
• an ultrasonic cleaner, 5.5 litre (Bransonic
Rocket Assembly 32)
There are two motor assembly halls, referred to • Containers for liquid nitrogen
as “Centaure Assembly” and “Skylark Assembly” • Containers for liquid helium
respectively, in accordance with the motors which • a weighing-scale 0-1,200 g capacity, 0.1
were originally assembled therein. They can be, mg readability. (Satorius 1206 MP)
and are, of course, used for other motors. • a stereo-zoom microscope. Magnifiction
x30 to x210. Reflected light and cam
Centaure Assembly era adapter with 35 mm Contax camera
The hall is now mainly used as heated store for (F:1.7), Bausch & Lomb Stereo Zoom 7)
Esrange and customers equipment. This hall has a • Microscope Nikon, Diophot + accessories
total floor area of 32.4 m by 10 m and a height of • Microscope Nikon, SMZ-2B, 2 pcs
4.4 m. An electrically operated gantry crane can be • Microscope Nikon, SMZ-2T
used over the entire floor area. The temperature • Schott coldlight source, KL 1500, 3 pcs
is controlled and recording is possible, records are • Centrifuge Hettich Universal K2S + acces
only kept when motors are in the halls. The access sories
door is 3.98 m high and 3.00 m wide. • Deepfreezes Colora, UF85-110T
• Autoclave Denley BA 852
Gantry crane: • Magnetic Stirrer Nuova II, SP 18420-26
Max. load: 2000 kg • Vortex mixer Eckli 600
Hoist speeds: 100 mm/sec and 10 mm/sec • Distillation apparatus Schott 2481100
Max. height to the hook: 2.9 m. • Water demineralisation Seradest
S750/5200
Skylark Assembly • Transportbox Veba electronics, #378 37°C
This hall has a total floor area of 36.0 m by 10.5 m • Transportbox Veba electronics, #379 37°C
and a height of 4.5 m. Temperature control and re- • Transportbox Veba electronics, #833 4-
cording are the same as those of the Centaure As- 22°C
sembly hall. An electrically operated gantry crane • Transportbox Veba electronics, #832 4-
can be used over the entire floor area. Intercom 22°C
• Transportbox Veba electronics, #828
• Accu charger
• Accu 12 V/65AH, 2 pcs
• Nikon 801 + AF Nikon 50 mm
• Cleaner for laboratory glassware, Miele G
7733 automatic
• CO¨-incubator, Heraeus B 5061 EK-CO¨
• Conductometer, Knick type 600
• Electronic precision balance, range 3,000
g, readability 0.01 g, PAG Oerlicon, Precisa
3000 C
• Microscope illumination, Volpi type Intralux
5000
• Incubator, Memmert type BE 60
• Large shaker, GFL type 3020
• Magnetic stirrer, IKA-Werk type Ikamag
RCT
• pH-meter, Knick type 646
• Pipetting guide, Technomara type Pipetboy
• Reagent glass shaker, Heidolph type Reax
2000
• Shaking water bath, Julabo type SW-20 C
• Steam sterilizer, Heuss u. Partner, type
Varioklar 400 E
• Refrigerated centrifuge, Heraeus, type Om
nifuge 2.0 RS
• Refrigerated centrifuge, Sigma, type Sigma
3 K-1
• Ultracentrifuge, Kontron Instruments, type
TGA 55
• Water bath, GFL type 1013 event of a hold after the opening of the building it
• Water bath, Memmert type WU 600 can be closed and the temperature rapidly brought
• Intralux 5000 cold light source back to that desired, to protect the motor and pay-
load.
Workshops
One small mechanical and one electronic workshop The launcher elevation and azimuth and the build-
are available. ing roof and blast doors can be controlled locally or
remotely from the blockhouse. Azimuth and eleva-
Blockhouse Payload Control tion angles, roof and blast door positions and tower
To accommodate the large amount of ground check temperature are monitored on the launch console.
out equipment, mainly used for microgravity pay- Power outlets (some controlled remotely) are avail-
loads, a dedicated blockhouse is available (124 able at the payload platform.
B). Its roof and walls are reinforced to the same
standards as the main blockhouse. The floor area is Standard payload cabling consists of 10 screened
8.0 m by 7.5 m. Payload cabling from the MAXUS cables, each containing 41 wires, each 0.75 mm2.
building, the SKYLARK tower and the MRL launch- 16 twisted individually shielded pairs are available
er terminates in this room. The power supply in- as well as coaxial cables,16 cables 75 ohm and 4
cludes 30 KVA, 230 V, 50 Hz uninterruptible power cables 50 ohm. The cabling is terminated in the
(UPS). user’s blockhouse.
wires 0.75 mm2 area, resistance 4 ohm, 3 cables
each with 8 twisted pairs and 4 coaxial cables, 50
ohm. The cabling is terminated in the User’s block-
house.
MAXUS Launcher
This complex was originally built for the ARIES
sounding rocket. In 1990 it was rebuilt to facilitate
launches of the CASTOR 4B.
Motors up to the size of Castor 4B can be accom- Together, these scientific institutions can offer
modated. unique opportunities for co-ordinated studies.
Signal Display Facilities The entire launch field is covered with fine gravel.
All measured data are concentrated to the Scien- 100 m south of the Chapel building a cavity is lo-
tific Centre. The user is allocated a display console cated, containing electrical power, ground cable,
where experiment data and other data can be ac- “Public address” loudspeakers, and a telephone
cessed. The display console consists of intercom, line.
word selector/display, chart recorder, serial data
distributor, and power outlets. Five units are avail- As an improvement a major extension of the entire
able. Special equipment brought by the user can launch field was done during the summer 2004.
be installed. Today the total launch pad area is 250 000 m2.
The launch field is designed to launch balloons in
Scientific Instruments different directions, divided into six runways. The
Ground based instruments of many types are used directions are N, S, NW, NE, E and SE.
to support sounding rocket and balloon borne ex-
periments. The results are displayed in the Scien- Since the start in spring 2005, long duration bal-
tific Centre for immediate access by the user. loon flights in westerly stratospheric wind for land-
ing in Northern Canada or Alaska territories has
Two other major scientific facilities are located near taken part almost every year.
Esrange. The Swedish Institute of Space Physics is
a centre for magnetospheric studies. EISCAT (Eu-
ropean Incoherent Scatter Facility) is another in-
ternational association with headquarters and a
receiving station in Kiruna for ionospheric studies.
10
Balloon preparation buildings a crane, which has a lifting capability of 1000 kg
lifting to a maximum height of 3.35 m.
The “Chapel” building
This building holds 180 m2 of floor area. The bal- The southern part of the building is a two floor
area. The Operation office is situated on the top
loon payload assembly hall occupies 100 m2. To
floor, including telephone and Internet access. On
support pre-flight operations, a crane of 1000 kg
the ground floor area there are two User offices
lifting capability is running along the top of the
also equipped with Internet and telephones.
ceiling, also allowing loads to be carried 2 m out-
side the entrance door. One room is used as a prep-
aration room for EBASS. One room for E-Link 10
m2, One office 12 m2, is available to the User, both
with telephone and Internet access. A 30 m2 area
is used as storage for launch support equipment.
The Chapel building
11
located on the roof of the Main Building. An acqui- lized whenever possible. Frequency demodulators
sition aid feed minimizes the risk of losing track are standard, but various demodulators can be
of fast moving targets. Full coverage of the hemi- used for different demodulation requirements.
sphere ensures uninterrupted data acquisition from Wide bandwidth TV-signals can be received and
balloon-borne payloads. Polarization diversity com- demodulated. .
bining improves the quality of tracking and data
reception. Data Extraction
The received LeftHandCircular and RightHandCiru- Composite signals, output from receivers, are fur-
lar polarized RF signals are fed to the telemetry ther processed in FM or PCM equipment. Four sepa-
station for further distribution and demodulation. rate PCM signal systems are available.
Video switching
All PCM video signals are distributed within the te-
lemetry station over two 32×32 switching units,
with full fan switching capability. The switches are
configured for each mission by means of software.
Each mission set-up is stored in the memory of the
switch in order to enable fast change of the station
video set-up.
PCM Decommutation
High performance bit synchronizers are used to re-
generate and decommutate PCM data. Four inde-
pendent systems are available. The user will have
access to buffered outputs including data, clocks
and all necessary control signals.
Upon special agreements, Data can also be recorded on S-VHS media using
there is a possibility to use a configurable Avalon cassette recorder, which can
the DLR telemetry station record 1 or 3 analogue signals simultaneously at
that is equipped with a data rates up to 8 or 2 MHz. IRIG-B time code is
tracking antenna for telem- also recorded.
etry data acquisition. The There is also a HEIM Hard Disc recorder which is
station can receive, de- capable of recording signals after bit synchronisa-
modulate, process, record tion at data rates up to 30 Mbps.
and distribute the telem-
etry data. Telescience
Besides manipulating onboard experiments dur-
S/X-band Tracking Equipment ing flights from Esrange it is also possible to do so
Upon request there is a possibility to use the ETX from remote laboratories all over the world. Data,
satellite antenna for high altitude rocket flights. TV-video signals and Tele-commands can be trans-
The antenna can be controlled from the telemetry ferred between Esrange and remote sites by terres-
station. RF/IF signals are routed to the telemetry trial telecommunication links or broadband satellite
station over optical links. links which enables the real-time telescience.
Receivers TV centre
The receivers are flexible The two TM stations receive the transmitted TV sig-
and easy to set-up for spe- nals in two polarizations and distribute the video
cific tasks simply by alter- signals to the TV centre located in the Main Build-
ing configuration. Pre and ing. An operator chooses the best signals for re-
post-detection polarization cording and further distribution to the Blockhouse
diversity combining is uti- and the Scientific Centre. S-VHS video recorders
12
are used for recording. The nature of the activities and the geographical
The TV centre is a property of MBB/ERNO in Ger- layout of Esrange require high performance com-
many and can upon special agreement, be used for munication systems for voice and data. A general
TV selection and distribution during missions. public address system connected to loudspeakers
both indoors and outdoors is the primary voice
Output Products communication channel.
Post flight products can be generated. The user can
define several different types of media and con- Intercom System
tents. All stations involved in measurement activities are
equipped with at least one intercom unit. Each unit
Digital Media has a loudspeaker and a microphone or a headset.
Digital products from received data can be gener- There are eight separate communication “loops”
ated on media like CD-ROM, DAT or Internet FTP. dedicated for special purposes. Any of these loops
can be accessed by means of front panel switches.
Analogue Tapes If many loops must be monitored, special units are
Track allocation and recording parameters can be available which mix the sound from all selected
adapted to User specification. Special recordings loops into one loudspeaker.
may be produced in real time.
GO/NOGO System
Video Tapes As reports on status of the systems involved are
Video tapes in PAL or NTSC format can be gen- time critical, a light signal system is used. The Op-
erated from TV-video data and also some ground erations officer, who is responsible for the coordi-
instruments. Timing information can be mixed into nation of all activities, has an immediate survey of
the picture. Conversion from one format to another the current situation. Each station is equipped with
is also possible. a control panel where a red light corresponds to
NOGO, i.e. system failure or the equivalent. Con-
Frequency Plan versely a green light corresponds to GO, i.e. every-
The frequency plan for Esrange is based on a per- thing is under control.
mission issued by the Swedish authorities on a
yearly basis. For all transmitters that are to be Video Message System
used, all technical data including frequency, out- General information to all stations is distributed
put power and bandwidth must be submitted to via a local video system. A large number of video
Esrange at least two months before expected start monitors are installed within Esrange. The basic in-
of use. formation consists of Universal Time and Relative
Time (count-down time). In addition, short mes-
Trajectory Determination sages can be displayed.
Different systems are used to determine trajecto-
ries and payload impact locations. An efficient re- External Communications
covery organization is readily available. Dedicated communication to/from Esrange can be
arranged via the public telecommunication net-
DLR C-band Radar works using ISDN, Internet or other suitable meth-
Located at Esrange is ods. Users can bring their own PC to Esrange and
also the DLR RIR -774C. have access to Esrange Internet services provided
This system can, upon that:
special agreement, be
used for tracking of dif- • the User’s PC is configured for DHCP (Dy
ferent payloads. The namic Host Configuration Protocol).
system is capable of • the User provides the PC cable with RJ 45
tracking in skin and connector to connect to the Esrange
transponder mode. network.
13
to the user. All ground based and flight equipment
Reference Frequencies is field proven. The system includes all necessary
All frequencies that are generated are synchronized functions to perform GPS position determination,
to the station reference. cut-down on command, cut-down by timers, top
valve and ballast machine operations for balloon
Telecommand System for Sounding Rockets piloting.
A ground to space transmitter system is available.
This system is used mainly for the following pur- There are also three fully transparent bidirectional
poses: serial data channels available for the user. Adapt-
- Flight termination, in case a failure develops in ing user instruments can be realized using the
the rocket-borne guidance system. standard serial interfaces for linkage of user data
- Flight commanding and manoeuvring of payloads to ground.
flown on rockets or balloons.
- Termination of balloon flights over land
area, in case the payload must be recovered.
ESC-Antenna
A UHF antenna system for tele-command trans-
mission is available. Antenna pointing is performed
under computer control, to predicted angels or to E-Link airborne unit
actual angles delivered from tracking antennas. E-Link data link
The E-Link system can offer fully transparent bi-
Telecommand System For Balloons directional Ethernet, asynchronous RS 232/422 or
The tele-command system is installed at the Ra- synchronous data link between the payload and
dar hill. The modulators, amplifiers and antenna ground equipment. The user can simply connect
are remote controlled from the Esrange telemetry his/her equipment onboard using any of the inter-
station. faces types specified above and communicate with
the equipment from ground.
Modulating Signals
The payload command transmitter can be modulat- The system is capable of transferring up to 2 Mbps
ed with signals from the user’s ground equipment, of data on distances up to 500 km (TBC). The user
connected via the cable system to the modulator. can access his/hers instrument over the Ethernet
interface and the interface point can be extended
Flight Hardware for Balloons to locations outside Esrange premises.
14
real-time. Type of pointing: manual
The transponder units can also be equipped with Tracking speed: 5°/sec, nominal
switch ON/OFF functionality during flight using ei- Acceleration: 5°/sec2, nominal
ther barometric pressure sensors or via remote
command over a serial interface. L/S-band Tracking Equipment
Frequency range: L-band 1440 - 1790 MHz, S-band
Homing Beacon 2200 - 2400 MHz
It is recommended that homing beacons are used Antenna type: 2.4 m parabolic reflector
to support successful recovery operations. Special Tracking feed: prime focus, conical scanning horn
units are available that can be attached to the bal- Acq. aid feed: sequentially scanned dipole array
loon flight train. A unit consists of a styrofoam box Beamwidth: 3 dB: 4° and 30° respectively
containing a beacon transmitter, batteries and ex- Polarization: simultaneous RHCP and LHCP
ternal antenna. G/T:
L-band: 5.0 dB/°K
Power Supply S-band: 8.0 dB/°K
The power system at Esrange is a five-wire three- Tracking speed: 20°/sec min
phase 50 Hz system. The phase to phase voltage is Acceleration: 20°/sec2 min
400 VAC -6% +10%, 50Hz ±2Hz, phase to neutral
voltage is 230 VAC -6% +10%, 50Hz ± 2Hz. DLR L/S-band Tracking Equipment
Frequency range: S-band 2200-2400 MHz, L-band
The system neutral is separated from safety ground 1650-1750 MHz
in the local distribution systems. Neutral and safe- Antenna type: 5 m parabolic reflector
ty ground will be connected only at one point, the Tracking feed: Prime focus, Monopulse system
main power inlet. Beamwidth: S-band 1.8°, L-band 2.4°
Polarization: RHCP or LHCP
The system is designed to eliminate 50 Hz hum on G/T: S-band 14 dB/°K min
signal lines. It is important that all user equipment Tracking speed: 30°/sec
which shall be connected to the system is designed Acceleration: 30°/sec2 max
such that neutral is separated from safety ground
(chassis) and signal ground. Power transformers S/X-band Tracking Equipment
must have separate primary and secondary wind- Frequency range: S-Band 2200-2400 MHz, X-Band
ings. It is possible to supply 110 VAC 50 Hz power 8025-8400 MHz
at certain locations. Antenna type: 13 m parabolic reflector
Tracking feed: prime focus monopulse, five crossed
Back-up power is installed in the main building (800 dipoles
kVA), the launching area (300 kVA) and the radar Beamwidth, 3 dB: S-Band 0,7°, X-Band 0,18°
hill (300 kVA). No-break-power (UPS) is installed Polarization: S-Band simultaneous RHC and LHC,
in the main building 70 kVA; 20 minutes, launching X-Band switchable RHC and LHC
area 30 kVA; 20 minutes, and radar hill 5.0 kVA; G/T: S-Band: 23 dB/°K, X-Band: 33 dB/°K
20 minutes. Tracking speed: 4°/sec
Acceleration: 10°/sec2
Specifications
Receivers
P-band Tracking Equipment Microdyne Mod. 1100 AR
Antenna 1 Demodulation: FM intermediate/wide band
Frequency range: 215-260 MHz Second IF bandwidth: 300, 500, 750 kHz, switch
Tracking: Three channel monopulse system selectable, or 0.75, 1.5, 2.4 MHz, switch selecta-
Antenna type: Crossed dipole array with a common ble
ground plane
Gain: 18 dB over isotropic Video Characteristics
Polarization: RHCP Output impedance: 75 Ohm
Beamwidth: 18° Frequency response: 10 Hz- 2 MHz
First sidelobe: 20 dB Output voltage: 1-10 V p-p, 2.8 V p-p nominal
Type of pointing: Autotrack, manual Connectors: BNC
Tracking speed: 5°/sec, nominal
Acceleration: 5°/sec2, nominal Diversity Combiner, Microdyne 3200-PC
Type of combining: Simultaneous Pre-Detection
Antenna 2 and Post-Detection, Dual channel, AGC controlled
Frequency range: 395 - 405 MHz including an absolute value AM detector
Tracking: No tracking Output frequency range: 10 Hz to 5 MHz
Antenna type: Four stacked helical antennas. Output level: 0-8 V p-p, 2.8 V nominal
Gain: 14 dB over isotropic Connector: BNC
Polarization: RHCP
Beamwidth: 28° Microdyne Mod. 700 MR
15
Demodulation: FM, PM, BPSK, QPSK Demodulation: FM
Second IF bandwidth: 0.3, 0.5, 0.75, 1.5, 6.0 MHz, IF bandwidth: 10 or 20 MHz switch selectable.
switch selectable De-emphasis: CCIR 405.1 switch selectable.
16
• Frame synchronization Connector: BNC
• Format synchronization
• Serial-to-parallel conversion FM record/reproduce characteristics (4 tracks):
• Data capture Input level: 0.5 V p-p - 12 V p-p, 2.8 V p-p nomi-
• Single-channel binary/octal/hex/decimal nal
display Frequency response: IRIG WB 2
• Digital to analog conversion Output level: 0.7 V p-p - 2.0 V p-p into 75 Ohm for
normal record level
Input bit rate: 1 bps to 20 Mbps Connector: BNC
Word length: Up to 32 bits
Frame length: 1 to 8192 words The tape recorder is also compatible with IRIG
Format length: 2 to 4096 frames standards Intermediate and WB 1
Frame sync length: Up to 32 bits
Format sync types: ID counter or pattern Avalon AE 3840 HW
Tape: S-VHS cassette
Format sync. Recording time: 60 minutes
Pattern length: Up to 32 bits Frequency response: 1 channel 8 MHz or 3 chan-
Output serial data: NRZ-L, positive true nels 3 MHz
Timing pulses: Bit rate clocks, 1/4 bit wide, Word Output level: 1 Vpp
clock, 1 bit wide, Frame clock, 1 bit wide, Format
clock, 1 bit wide. Heim GSR120 HD recorder
120 Mbit/s maximum recording capacity
FM Discrimination Two DCM12 modules up to 20 Mbit/s each
Input type: RS422, TTL, 1V bi-phase, Data+Clock,
Subcarrier Discriminator, Astrodata 404 Data only, Bi-Phase
Demodulates FM subcarrier signals. The center fre- One MRG 12 module 4 channels with maxium 5
quency and deviation are determined by a plug- Mbit/s/channel or total maximum 12 Mbit/s
in channel selector. The intelligent frequency re- Input type: Data + Clock, Data only, Bi-phase
sponse is determined by a plug-in low-pass filter for
MI = 5, switchable CA or CO response. Video Recorder, Panasonic AG-7330
Tape: S-VHS 1/2 inch cassette
Subcarrier center frequencies: 400 Hz-165 kHz, Record/reproduce time: Max 180 min
IRIG propotional bandwidth standard Video signal system: CCIR/PAL/M-NTSC
Frequency deviation: ± 7.5 % and ± 15 % S/N ratio (B/W): 45 dB
Special low pass filters for the following frequen- Video input/output: 1.0 V p-p nominal
cies: 6.5 kHz, 8.5 kHz, 25 kHz and 50 kHz Impedance: 75 Ohm
Output voltage: Adjustable up to 10 V for full de- Connector: BNC (composite video) or 4P (S-VHS)
viation
Video Recorder, Panasonic NV-SD22
Tunable Discriminator, EMR Model 229 Tape: VHS 1/2 inch cassette
Subcarrier frequencies: 300 Hz to 300 kHz tuned Record/reproduce time: Max 180 min
by front panel switch and dial Video signal system: PAL
Frequency deviation: ± 7.5 % or ± 15 % S/N ratio (B/W): 45 dB
Deviation ratio: 1, 5, 10, 25, 50 or 100 Video input/output: 1.0 V p-p nominal
Data frequencies: 3 Hz to 30 kHz Impedance: 75 Ohm
Output voltage: Adjustable up to 10 V for full de- Connector: SCART
viation. Frequency increase gives negative going
voltage. DVD recorder, SONY
RDR-4X720
Magnetic Tape Recording Video signal system: PAL
The FM system operates in low band, intermediate Video input/output: 1.0 V p-p nominal
band or wideband I, selectable by internal strap- Impedance: 75 Ohm
ping. Nominal configuration is intermediate band. Connector: BNC/SCART
17
Frequency M a x i m u m Bandwidth Station reference frequency
band (MHz) output power (MHz) Frequency: 5 MHz
(W) Long term stability: 5 x 10-11 per month
Output level: 1 V RMS into 50 ohm load
400.0 - 405.0 2 0.500 Transformer coupled output
1425 - 1525 10 5
2200 – 2400 10 10 Secondary reference frequencies
(Recommend- Available frequencies: 1 Hz, 10 Hz, 100 Hz, 1 kHz,
ed > 2300) 10 kHz, 100 kHz, 1MHz
Opto coupled outputs, capable of driving TTL level
Telecommand transmissions: 448.00 MHz and into a 50 ohm load.
449.95 MHz
Frequency pairs for radar transponders: 5612/5662 Telecommand System
MHz and 5712/5762 MHz Flight Termination Transmitter For Sounding Rock-
ets
DLR C-band Radar Frequency: 448.00 MHz
Antenna Modulation: FM
Reflector: 2.4 m front - fed parabolic Max deviation: 125 kHz
Beam width: 1.4° Max modulating freq.: 50 kHz
Gain: 39 dB isotropic Input impedance: 50 ohm
Polarization: Vertical Antenna gain: 9 dBi
EIRP: + 30 dBW
Transmitter Antenna polarization: LHCP
Frequency: 5400-5900 MHz
Power Output: 650 kW Payload Telecommand Transmitter For Sounding
Pulse length: 0.25, 0.5, or 1.0 µs Rockets
PRF: 160, 320, or 640 pps Frequency: 449.95 MHz
Modulation: FM
Ranging System Max deviation: 125 kHz
Range measurement resolution: 1 m Max modulating frequency: 50 kHz
Angular measurement: Input impedance: 50 ohm
L/S-band auto tracking system Antenna gain: 9 dBi
Readout resolution: 0.1° EIRP: + 30 dBW s
Angular accuracy: 0.3° RMS Antenna polarization: LHCP
18
System modulation sensitivity: An input voltage of
± 1V produces, ± 10 kHz deviation of the transmit-
ted RF frequency
Max input voltage: ± 12 V
Input connector: BNC female
Input impedance: 10 k Ohm
GMSK Interface:
Bandwidth: 2 Hz - 200 kHz (3 dB points)
System modulation sensitivity: The input has ad-
justable deviation of the transmitted RF frequency
Max input voltage: 5 V
Input connector: BNC female
Input impedance: 10 K Ohm
Homing Beacon
Recommended recovery beacon specifications:
Frequency range: 240-260 MHz
Modulation type: CW or pulsed
Output power: min. 0.4 W
Battery lifetime at ambient temperature:
min. 48 h
Note! 121.5 MHz and 243.0 MHz are international
emergency frequencies and can NOT be used as
beacon frequency.
19
approving overall safety and security policies in the
company including the Esrange Safety Manual (ESM).
Safety The President of Science Services Division is re-
sponsible for implementing the range safety poli-
General
cies and criteria. He/she is responsible for approv-
As a general rule, Swedish safety regulations and
ing Flight Safety Plans and Ground Safety Plans.
laws apply for work at Esrange. The Work Envi-
ronment Act contains the basic provisions concern-
The Head of Sounding Rocket and Balloon Depart-
ing occupational safety and health questions in
ment is responsible for conducting operations in
Sweden. This act is a general act of law which is
accordance with the ESM and other complemen-
backed up by special rules and regulations in dif-
tary safety policies and regulations. He/she is also
ferent fields, for example Explosives, Inflammable
responsible for preparing Safety Plans and of ap-
materials, Toxic materials, Electrical facilities.
pointing a Flight Control Officer in a mission with a
The specific safety rules and regulations that apply
Flight Termination System.
for work at Esrange are defined in the document
Esrange Safety Manual, ESM, which is available on
The Esrange Project Manager is responsible for
site at Esrange. In the following, general safety in-
all contacts with customers and contractors when
formation is lined out.
planning, building up and conducting rocket and
balloon missions at Esrange. He/she is responsible
Scheduling
for coordination and delegation of responsibilities
Esrange provides launching opportunities any time
of campaign activities including all safety matters.
of the year, any time of day, within the measure
He/she shall superintend all safety and security
of Swedish Laws. The long-term scheduling of the
regulations and arrangements related to the mis-
Esrange launching programme is carried out by the
sion.
secretariat of the Programme Advisory Committee
(PAC) situated at ESA Headquarters in Paris. A re-
The Chief Security Officer is responsible for the
vised schedule is issued every second month.
overall planning of security matters at Esrange, in-
cluding supervision of the fulfilment of security reg-
Operational Support
ulations in the ESM and in the Esrange Föreskrifter
Assembly and preparation of rockets and balloons is
för Säkerhet och Skydd (EFSS) and other comple-
normally done by Esrange personnel. In the event
mentary safety and security policies and regula-
that the user teams do these operations, all work
tions.
must be performed in accordance with the ESM
regulations. Assembly, preparation and checkout of
The Range Safety Officer is responsible for the
payloads, which is normally executed by the range
overall planning of safety matters of launch op-
user, must likewise adhere to the ESM regulations.
erations at Esrange, including supervision of the
fulfilment of safety regulations in the ESM and in
Recovery of Rockets and Payloads
the Esrange Föreskrifter för Säkerhet och Skydd
Recovery of rockets and balloon payloads is stand-
(EFSS) and other complementary safety policies
ard procedure at the range. The land impact area
and regulations.
makes Esrange very suitable for all kinds of flights
where recovery is necessary. The open landscape
The Head of Operations and Flight Safety Section is
allows smooth payload landing contributing to a
responsible for performing safety analysis and de-
minimum of impact damage. After impact, the pay-
veloping safety plans or data packages for all bal-
loads seldom drag in the recovery parachute thanks
loon and sounding rocket missions. He/she is also
to the prevailing low winds. Balloon payloads are
responsible for preparing Campaign Documents
recovered all over northern Scandinavia and north-
and Rocket Introduction Documents to Swedish
ern Russia. Provided that payloads are equipped
authorities.
with proper homing devices, recovery operations
are very likely to be successful. All other parts,
The Head of Launch Team is responsible for the
without beacons, such as motor cases, nosecones,
ground safety in the launching areas.
etc., are recovered as soon as they have been lo-
cated. The excellent helicopter support from pilots
The Superintendent for Explosives is responsible
well acquainted with this uninhabited region of
for all handling of explosives at Esrange.
Scandinavia, makes it possible to maintain a very
high probability for successful recovery. The nec-
Restricted Areas
essary equipment to support recovery, ATC trans-
During operations, there are certain areas that
ponders and homing beacons, can be supplied by
must be closed for safety reasons. Only authorized
Esrange Instrumentation.
personnel will have access to such areas.
Safety Organization
Rocket Launching Area
The President and CEO of SSC is overall responsible
The road to the rocket launching area is closed near
for safety in the company. He/she is responsible for
the Main Building by means of a remotely control-
20
led road-block. Authorized personnel gain access
by using a special badge. Inside the launching area • The flight limits. These flight limits define
there are further restricted areas that require fur- the areas in which the vehicle under certain
ther authorization. conditions should be destroyed.
21
Operational support for Sounding rocket and Range User’s Requirements
balloon
Esrange appoints a Project Manager for every A range user must prepare a Flight Requirement
project that is planned to be carried out from Es- Plan which defines the mission requirements and
range. The Project Manager is the Esrange contact also the services to be provided by Esrange.
for the range User. He/She is responsible for the
campaign planning, co-ordination, countdown pro- It is recommended that the document is prepared
cedure, and operations at the range. All require- in co-operation with the Head of Launch Services
ments and correspondence should be addressed at Esrange such that the rules and regulations in
to the Project Manager. All operations, whatsoever, the Esrange Safety Manual are not violated, and
occur under the Laws of Sweden. Esrange officials that eventual difficulties can be eliminated at an
are responsible for flight control and flight safety of early stage.
all vehicles that are flown from Esrange.
The range user should submit at least two copies of
Approval to Use the Range the Flight Requirements Plan, arriving at Esrange
All projects, which will be carried out at the range, no later than three months prior to the scheduled
require approval by the President of Science Serv- start of the campaign.
ices Division. All plans for the use of Esrange should
be discussed with Head of Sounding Rocket and Based on this plan, permission from government
Balloon Department, such that all priority questions agencies can be applied, in the case it would be
can be settled and the long-term planning require- necessary.
ments be satisfied.
Should a balloon be supposed to fly over foreign
countries, an application must be made no later
than six months prior to the planned campaign.
_____________________________
22
Range User’s Requirements for all stages.
Flight Sequence
FLIGHT REQUIREMENT PLAN FORMAT A time table of all important events during flight.
This section describes the format of the contents
required in the Flight Requirements Plan. Trajectory
A preflight trajectory based on nominal launch
General Information angles.
Mission
A short description of the scientific objectives of Esrange Support
the project. Telemetry
An adequate description of the payload-borne
Organization telemetry instrumentation including the following
A description of the organization with responsible items:
persons and addresses, telephone and telex num- • Telemetry system including frequencies
bers of participating organizations. and power output
• Antenna configuration
Personnel • Polarization
A list of participating personnel including name, • Bandwidth, format, sync words and data
responsibility and position. rates
• Recording requirements
Operations
Launch Conditions Tracking
A brief description of scientific and meteorological A specification of tracking requirements and track-
conditions required for launch. ing systems in the payload.
23
Esrange Space Center
SSC
Esrange Space Center
Science Services Division
P.O. Box 802, SE-981 28 Kiruna, Sweden
Phone: +46 980 720 00
telefax: +46 980 128 90
www.sscspace.com
Ver. 2 2011-04-11