Documente Academic
Documente Profesional
Documente Cultură
of concrete
retaining walls
Newer concrete retaining wall systems can
cut the cost of cast-in-place walls in half
Soil nailing
Soil-nailed retaining walls are de-
signed like MSE walls but construct-
ed like ground-anchored walls. Like
MSE, nailed soil acts as one coher-
ent gravity mass. Long steel rebars
are inserted in the ground at close
enough spacing to make the soil
more self-supporting. The rebars re-
inforce the soil in the same way MSE
reinforcements do, only they are in-
stalled in natural unexcavated soil,
not select compacted backfill.
Like ground anchors, these rebars
are inserted into drilled holes and
Grouted steel tendons tie the concrete face of a ground-anchored wall to the grouted. But unlike ground anchors,
unexcavated soil behind the wall.
the full length of each rebar is bond-
ed to the soil, not just the end. Be-
then the grouted ground anchors heads are covered with a cast-in- cause they don’t have to resist high
are post-tensioned. The anchors place, precast, or shotcrete facing. lateral earth loads pressing against
must be long enough so the grouted The concrete facing of a ground- the wall, the rebars are not post-ten-
ends rest behind the critical failure anchored wall is thinner than a can- sioned as ground anchors are.
surface in stable soil or rock. The tilever wall, which means it also re- Nailed soil, like MSE, exerts much
soil behind the wall is not removed. quires less excavation. A less pressure on the concrete facing.
Because specialty contractors g ro u n d - a n c h o red wall with a 7- Consequently, the precast, cast-in-
have developed most ground an- inch-thick concrete face can sup- place, or shotcrete face can be as
chors, many of the techniques are port a 40-foot-high cut. Because the thin as 5 to 8 inches.
p ro p ri e t a ry. Howe ve r, construction soil behind the wall is not exc a va t- In 1985, the FHWA sponsored the
usually begins by installing columns ed, anchored walls do not require construction of a soil-nailed wall for
or soldier beams. wide aboveground construction a tunnel portal at the Cumberland
Workers drive or drill the soldier easements. This makes them espe- Gap. After making a 5- to 6-foot-
beams into the ground. The soldier cially suited for constructing de- deep cut with a bulldozer, workers
beams serve as vertical strongbacks pressed highways next to roadways, placed vertical strips of drainage
for the wall. Then the workers exca- as is common at interstate under- fabric over the soil every 15 feet (5-
vate the earth in front of the soldier passes in cities. Because the wall foot spacings are now recommend-
beams as deep as the first row of can be constructed from the top ed). Then they sprayed shotcrete
ground anchors. After installing the down, traffic on adjacent roadways over the cut and allowed it to cure
first row of ground anchors, they ex- does not have to be interrupted. for 1 day. Next, they drilled 41⁄2-inch-
cavate to the next row. At each step Ground-anchored walls eliminate diameter holes into the cut on a 5-
in the excavation, they place wood large footings and foundation piles foot grid. The holes were 20 to 30
lagging between the soldier beams under the wall, too. feet deep and 15° from the hori zo n-
to temporarily retain the wall. This Ground-anchored walls do have tal. They inserted #8 and #11 rebars
process is repeated until the full limitations, howe ve r. They cannot in the holes and grouted them with
height of the wall is exposed. After be used in soft cohesive soils be- neat cement grout. After the grout
completing the excavation and in- cause of excessive creep. Existing set, tightening a nut at the end of
stalling the ground anchors, the sol- utilities, subways, or other under- each bar applied a slight torque to it.
dier beams, lagging, and anchor ground structures may prohibit the Then the workers applied a second
increase the safety factor of a slope
without removing the sliding soil.
Or, as at the Cumberland Gap, it can
stabilize a cut hillside in a landslide-
prone area without using temporary
shoring. Soil nailing usually requires
less underground easement than
ground-anchored walls do.
Soil-nailed walls also can support
e xc a vations for building founda-
tions. At least 100 of these tempo-
rary walls have been built in the
United States.
Reference
1. Leary, Robert M., and Gary L.
Klinedinst, “Retaining Wall Alternates,”
Federal Highway Administration, No-
vember 9, 1983.
Editor’s note
Part II of this article will appear in Au-
gust. Several precast systems will be
described, including crib, bin, can-
tilever, counterfort, and small block
walls.