seabed-to-surface
BG Miskar
January 2011
Project Overview
BG Miskar The Miskar Field is a carbonate reservoir containing
some 1.1 tcf of recoverable gas, located in Gulf of Gabes,
Client approximately 122km off the coast of Tunisia.
BG Tunisia
Through 2 no. 10" x 2.8km 25% Chrome pipelines we
Location tied back two subsea wells, at a single drill centre to the
Offshore Tunisia Miskar 'A' Platform. Each well is produced through its own
dedicated pipeline. Acergy Falcon
Project Type
SURF Control and chemical injection was supplied by a single
umbilical from Miskar 'A' Platform to the drill centre location.
Date Awarded
A multiplexed electro-hydraulic control system was used
2006
to control the subsea tree valves and provide pressure and
temperature information.
Date Completed
2008
Vessels/Spoolbases
Utilised
Acergy Discovery
Acergy Falcon
Acergy Discovery
Pipelay initiation
www.subsea7.com
© Subsea 7, 2011. Information correct at time of going to press.