Documente Academic
Documente Profesional
Documente Cultură
[Project Name]
[Company]
[Project Manager] Tuesday, August 14, 2018
Duraton
WBS Task Names Resource Names Start
03-Mar-2014 12
Task Category 1 [name] 03-Mar-2014 12
Sub Task Level 2
Level 3 Task [name] 03-Mar-2014 3
Level 4 task [name] 06-Mar-2014 4
Sub Task Level 2 [name] 06-Mar-2014 10
Level 3 Task
Level 3 Task
Milestone 1 17-Mar-2014
Page 1
Gantt Chart
How To Use
INSERT LINES:
Insert the required number of lines: click the line number and drag down
From the template, copy the required section or just one line
INPUT DATA:
WBS: to itemize the WBS copy and past the required level from the template
Enter a Task and Resource Names
Enter a [Start] date and a [Duration] (working days); The Due date is calculated and the task bar shows the task's
Or: Enter a [Start] and [Due] dates; The [Duration] (working days) is calculated and the task bar shows the task's d
Enter a percentage in the [% Complete box]; the task bar shows a progress bar to indicate what percentage of the
Milestone: If you enter a start date without an end date, a milestone marker is displayed on the bar chart.
In Categories tasks (level 1) Start, Due, Duration and Percentage Complete values are calculated; however they ca
Holidays
1/1/14
3/4/14
4/18/14
4/20/14
4/25/14
5/1/14
6/10/14
8/15/14
12/8/14
12/25/14
Page 2
Gantt Chart
Page 3
Gantt Chart
60%
10 11
Days Completed
Days Remaining
Calendar days
Mar-14
Finish % Complete
19-Mar-2014 60% 17 03 04 05 06 07 08 09 10 11 12 13 14 15 16
19-Mar-2014 71% 17 8 9
06-Mar-2014 100% 4 3 0
11-Mar-2014 50% 6 2 2
19-Mar-2014 33% 14 3 7
12-Mar-2014 59% 10 4 4
06-Mar-2014 75% 4 2 1
12-Mar-2014 50% 7 2 3
10-Mar-2014 64% 8 4 3
07-Mar-2014 75% 5 3 1
10-Mar-2014 50% 5 1 2
Page 4
Gantt Chart
ated and the task bar shows the task's duration on calendar.
ated and the task bar shows the task's duration on calendar.
s bar to indicate what percentage of the task is complete.
er is displayed on the bar chart.
values are calculated; however they can be overwritten.
Page 5
Gantt Chart
12 13 14 15
Apr-14
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10
Page 6
Gantt Chart
16 17 18 19
May-14
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05
Page 7
Gantt Chart
20 21 22
06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Page 8
Gantt Chart
23 24 25 26
Jun-14
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Page 9
Gantt Chart
27 28 29
Jul-14
25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19
Page 10
Gantt Chart
30 31 32 33
Aug-14
20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13
Page 11
Gantt Chart
34 35
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Page 12