Sunteți pe pagina 1din 90

Geotechnical Investigation Report of Piers P1, P2,P3, P5,P6 ,P7 and

Abutment A2 of Bridge No.3

of

Dharam-Qazigund Section

of

USBRL Project Jammu and Kashmir

Forwarded to

HCC Limited

Forwarded to:

Hindustan Construction CoLtd

Space Engineers’ Consortium (P) Ltd.


Ist Floor, Alfarooq Building, Jawahar Nagar, Srinagar (J&K)-190008
CONTENTS

Page
Chapter
Description No
No

1.0 Introduction 01

2.0 Scope of Work 01-03

3.0 Location & Brief Details about Bridge Site 04-05

4.0 Field Investigation and Geological Studies 06-12

5.0 Geology of Bridge Area 13-14

6.0 Sub Surface Geology 14-27

7.0 Laboratory Tests Methodology for Soil/ Rock Samples 27-32

8.0 Geotechnical Assessment 32-40

9.0 Foundation Consideration 41-45

10.0 Conclusion and Recommendations 46-47

11.0 Annexure-I Bore log 48-62

12.0 Annexure II Photographs of Core Boxes 63-85

13.0 Annexure III Sample Calculation 86-88


Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Geotechnical Investigation Report of Piers P1, P2,P3 ,P5,P6 ,P7 and Abutment A2 of
Bridge No.3 Of Dharam-Qazigund Section Of USBRL Project
Jammu And Kashmir

1.0 Introduction.
The Hindustan Constructional Company Limited (hereinafter referred to as the HCC) has been
Entrusted with the construction of the proposed bridge No.3 across Dassa Nallah respectively
by M/S IRCON International Limited (hereinafter referred to as the IRCON) along Dharam-
Qazigund Section of USBRL Project, J&K (under package 2, 3, 4&5). M/S HCC have taken
the services of Space Engineers Consortium Pvt Ltd. for carrying out Geotechnical
Investigation for this proposed bridge site under Work order No HCC ENG 106 B 02 007
Dated 29th January 2018.The Investigation of 07 bore holes located at piers P1, P2, P3, P5,P6,
P7 and A2 of bridge No.3 have been completed during January 2018- May 2018.This report
includes results of geological logs of boreholes, Standard Penetration Test (SPT) besides
geological studies around the tunnel T-49 alignment area.

The objective of the investigation is to generate a report incorporating subsurface geological


data collected from different boreholes together with limited surface geological studies along
the alignment. This report deals with the data obtained during field and laboratory
Investigations and recommendations thereto.

Brief details
The tunnel T-49 is part of the USBRL railway line project in Northern India, in the state of
Jammu & Kashmir. Its length is approx. 10 km. Its section is typical for an Indian mountain
railway line: single track main tunnel with parallel escape tunnel. Its gradient is approx. 1%.
After the initial part of civil design and 3 years of supervision, the Client assigned the
electromechanical design to Lombardi. With the experience gathered in the neighboring tunnel
T-48, the E&M standard can be respected for an homogeneous design. Its length and its
gradient, with the portals on two different sides of a local ridge, the requirements are for a
dedicated ventilation concept in case of current operation

2.0 Scope of work.


i) Drilling of 07 bore holes at pier location P1, P2,P3, P5 ,P6 ,P7 and abutment A2 of bridge
No 3. The depth of bore hole achieved at site is 43m, 40m, 73m,78m , 63m ,61m and 27 m
depth respectively. These locations have been specified by the Engineer In-Charge of HCC at
site.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |1
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

ii) Conducting Standard Penetration Test at specified intervals, wherever applicable.


iii) Collection of undisturbed samples/rock core samples as per B.I.S code of practice.
iv) Marking of water table position, if available.
v) Conducting laboratory tests as per B.I.S code of practice.
vi) Conducting In-situ permeability test (Falling head method).
vii) Submission of detailed Geo technical report.

Item
Item Description Unit Qty.
No.
Mobilization
Mobilization of necessary equipment, drilling rigs,
tools and tackles, men and materials to the site and
all services and demobilization on completion of the Lump
1 1
work (Sufficient Hydraulic rigs in working condition sum
shall be mobilized to complete the Drilling within
specified time period)
Per Borehole
2 Shifting and setting of Drilling rig at Bore hole location 21
location
Drilling of Nx size (76mm diameter) boreholes in all
types of Soil and overburden strata / Soft Ground
3 Rm 216
without core recovery inclusive of driving of
casing up to the overburden depth
a NGL up to 20m Rm. 179

b Beyond 20m Rm 37
Drilling of Nx size (76mm diameter) boreholes in all
types of Soil and overburden strata / Soft Ground
4 Rm. 216
with core recovery and inclusive of driving of
casing up to the overburden

a NGL up to 20m Rm 180

b Beyond 20m Rm 36
c Conducting Permeability test Falling head method Nos. 25

d Conducting SPT in all types of Soil/ Soft Ground Nos. 25

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |2
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Drilling Nx Size bore holes without core recovery


5 Rm. 243
(76mm diameter) in all types of Rock Strata
a NGL up to 20m Rm. 33

b Beyond 20m Rm. 210


Drilling Nx Size bore holes with core recovery (76mm
6 Rm. 243
diameter) in all types of Rock Strata
a NGL up to 20m Rm. 34

b Beyond 20m Rm. 209

c Conducting Permeability test by Packer Method Nos. 21

7 Laboratory Testing In Rock

a Bulk and dry density Nos. 10

b Water absorption & Porosity Nos. 10

c Specific gravity Nos. 10


Uniaxial compressive strength test (saturated & dry
d Nos. 10
condition)
e Point load test Nos. 20

8 Report Preparation
Preparation and submission of 03 copies of
Lump
a Geotechnical Investigation Report. Combined report 1
sum
for Bridge No. 2 and Bridge No. 3.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |3
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

3.0 Location and Brief Details about Bridge site

3.1 The proposed Bridge No 3 across Dassa Nallah is located at Sumbar village along
Dharam-Qazigund Section of USBRL Project in Ramban District of Jammu province of
J&K State. The proposed Bridge No3 is approximately 326.4mtrs in length supported on
7 piers and 02 abutments each with a span of 40.8m .The Nallahs passes through the
mountainous terrains and the Bridges passes at an elevation of around 1416mtrs. Refer to
Plate-I for sectional view of the proposed Bridge No 3 site.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |4
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Plate I sectional view of borelogs of bridge No 3


SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |5
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

4.0 Field Investigation and Geological Studies

4.1 Borehole Locations

The details of borehole locations marked on ground by the Engineer In-charge of HCC are
given in Plate-I and Table 1.

Table 1(Borehole location Details)

Location
Bore Depth of Collar
Bridge.
No
Hole Bore hole elevation(m) R.L(m)
No (m) Easting Northing

P1 43 1391.717 5111079.245 3684672.283 1391.617

P2 40 1393.538 511096.700 3684709.815 1393.438

P3 73 1397.255 511109.883 3684750.919 1397.155


Remarks

3 P5 78 1394.853 511142.848 3684821.760 1394.753

P6 63 1408.096 510603.993 3684197.451 1407.996

P7 61 1402.201 511174.039 3684896.849 1402.101

A2 27 1416.931 511192.349 3684934.573 1416.831

4.2 Methodology Of Field Work

The investigation was planned to obtain the subsurface stratification in the proposed project
site and collect overburden / bed rock samples for laboratory testing to determine the
engineering properties besides engineering classification of the subsurface stratum.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |6
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

4.3 Drill Holes


For Geotechnical investigation work, drilling rigs was installed at the specified drill hole
locations. Stability of rig was ensured by making platforms. Rotary Drilling machines were
deployed and drilling carried out with Nx diamond tipped drill bits or impregnated diamond
bits depending on the type of rock encountered. Suitable core catchers were used where ever
necessary.

4.4 Procedure of Drilling

a) The drilling fluid used was clean water to avoid contamination. Circulation of drilling fluid
was used before the core barrel reached to the bottom of the hole to prevent cuttings or sludge
from entering the core barrel at the start of coring. In order to collect the sludge / rock cuttings,
drilling fluid were circulated continuously down the hollow rods.

b) Specific procedure was adopted to reduce water circulation as and when


soft/weathered/fractured rock, were encountered to avoid shattering/breaking of core.

c) The rotational speed of the bit (spindle speed), the amount of downward pressure applied on
the bit (bit pressure) and water pressure were suitably adjusted and properly monitored so that
the core is collected with least disturbance and to avoid shearing of the core from its base.

d) As per the drilling schedule the minimum drill run should be 0.75m and maximum. 1.5min
length provided the core recovery observed is more than 80% in two successive 0.75m drill
runs. When core recovery is less than 20% then SPT shall be per formed before commencing
the next drill run .This procedure was strictly adhered to on the approval from the site
engineer.

e) If at any time blocking of the bit or grinding of the core was observed, the core barrel was
immediately withdrawn from the drill hole regardless of the length of drill run completed.

4.5 Observations during Drilling

a) During drilling operations, the colour of return water was regularly monitored and sediments
carried were keenly observed so as to determine change in the lithology and physical
properties of formations.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |7
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

b) The depth & rate of penetration was monitored to ascertain the depth at which marked change
in rate of penetration or sudden fall of drill rod occurred, the depth at which any blockage of
drill bit causing core loss if any was encountered.

c) Any heavy vibration or torque noticed during drilling was recorded together with the depth of
occurrence.

d) Special conditions like the depth at which grouting was done during drilling, presence of
artesian conditions, loss of drilling fluid, observation of gas discharge with return water etc
were also monitored

e) During drilling operation, observation on return water, rate of penetration etc shall be
recorded.

4.6 Standard Penetration Tests (SPT)

Standard Penetration Tests (SPT) prescribed as per IS specifications. SPT split spoon sampler
of standard dimensions is to be driven into the overburden from the drill hole bottom using
63.5 kg Hammer falling from 75 cm height. The SPT weight is mechanically lifted to the
specified height and allowed to fall freely on the anvil with the use of cat-head winch with one
to one and half turn of the drum. Blow counts for the penetration of every 15 cm are recorded
and the N is reported as the blow counts for 30 cm penetration of the sampler leaving the first
15 cm penetration as seating drive.

When the number of blows exceeded 50 to penetrate the first or second 15 cms length of the
sampler, the SPT N is regarded as more than 100. The test is terminated in such case and a
record of penetration of the sampler under 50 blows or more is made. SPT refusal is recorded
when there is no penetration of the sampler at any stage and also when a rebound of the
sounding system is recorded.

SPT ‘N’ values are correlated with relative density of non-cohesive stratum and with
consistency of cohesive stratum.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |8
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
[

CORRELATION FOR CLAY/PLASTIC CORRELATION FOR SAND/NON-


SILT PLASTIC SILT

Penetration Penetration Value


Value (Blows/300 Relative (Blows/300 mm)
Consistency
mm) Density
Very Soft 0 to 2 Blows Very loose 0 to 4 Blows

Soft 3 to 4 Blows Loose 5 to 10 Blows

Medium Stiff 5 to 8 Blows Medium 11 to 30 Blows

Stiff 9 to 16 Blows Dense 31 to 50 Blows

Very Stiff 17 to 32 Blows Very Dense Above 50

Hard Above 32

4.7 Disturbed Sampling in Drill holes

Disturbed overburden samples collected in the SPT sampler are preserved in polythene covers
and transported to the laboratory. One more polythene cover is provided to prevent the loss of
moisture during the transit period.

4.8 Undisturbed Sampling in Drill holes


Undisturbed samples to be collected using 100mm diameter and 450mm long MS tubes
provided with sampler head with ball check arrangement. The collection of undisturbed
samples in refusal strata is practically not possible.

4.9 Core Samples in Drill holes

Immediately after withdrawal from the core barrel, the cores samples were placed in a tray and
transferred into boxes specially prepared for the purpose. The core boxes were made from G I
sheet .The details of drill hole along with details of core run were recorded on core boxes.
After core logging the data was recorded for future use.

Bore hole logs are given in Annexure I and are summarized in table 4

Photographs of core boxes are given in Annexure-II.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |9
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Water table levels below ground level


Depth of Water
Bridge Location
table below ground Remarks
No. No.
level (m)

P1 29.0

P2 24.0

P3 25.0

Water table levels


3 P5 37.0
taken after 24 hrs

P6 5.0

P7 3.0

A2 7.0

4.4 Regional Geology of the Study area

Rocks of Siwalik and Murree Group of foreland to Pre-Tertiary rocks of Lesser Himalaya are
exposed along the proposed rail alignment. These rocks are traversed by number of thrusts and
faults which are considered to be still active. Due to this tectonic activity the rocks along the
proposed alignment are highly jointed, fractured, folded.

The general trend of the rocks is NW-SE having dip towards NE direction. Murree Thrust
marks the tectonic contact between Tertiary and Pre-Tertiary rocks comprising meta volcano-
sedimentary of Lesser Himalayan terrain. It is thought to be an autochthonous folded belt of
tightly compressed and recumbent anticline varying in width upto about 7 kms. It lies between
the Murree Group of the foreland and the Salkhal ameta sediments of the Kashmir nappe. Its
outer boundary is the Murree Thrust, which has brought the rocks of this para autocthonous
folded belt over the Murree Group.

The northern boundary is marked by the Panjal Thrust/ main central Thrust, a low angle plane
almost parallel to Murree Thrust, which has brought the entire Tethyan Himalayan

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 10
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Phanerozoic succession of Kashmir along with its crystalline basement over the Lesser
Himalayan Belt. The Lesser Himalayan Belt extends up to north of Digdaul from where the
Phanerozoic succession of Kashmir nappe with basement of Salkhalas starts (Agarwal and
Agrawal, 2005). Overriding the rocks of Parautochthonous belt along Panjal thrust, Salkhala
Group of rocks occur, as a narrow belt in Digdaul- Sildhar - Rajgarh section, comprising of
thick sequence of schistose quartzites, phyllite, and schists intruded by granodiorite-diorite,
gabbro, pegmatites and basic rocks. These are uncomfortably overlain with Ramsu Formation
comprising of highly compressed sequence of pyritiferous, carbonaceous Phyllitic Quartizites,
dolomitic crystalline, siliceous limestone, quartzite, phyllite and basic rocks and are in turn
uncomfortably overlain with the limestone, marl quartzite, Phyllitic Quartizite lithology of
Syringothyris Limestone Formation, and in turn are overland with Fenestella Shales Formation
and Agglomeratic Phyllitic Quartizite Formation exposed in the hill slopes south of Banihal
Pass and Panjal Volcanic Formation exposed in the Banihal tunnel.

Fig. 1 Outline geological map of the Himalayan Mountain Belt showing its major tectonic
subdivisions across the range.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 11
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

North of Banihal Tunnel the folded Triassic limestone along with minor Jurassic shale beds
are exposed in the section upto Qazigund. Quaternary sediments represented by Karewas
Formation are exposed beyond Qazigund towards north upto Srinagar in Kashmir. Table
showing Stratigraphic sequence (based on GSI Special Pub. 26, 1989) is given below table 2:

TABLE 2– Stratigraphic Sequences (Based on GSI Sp. Pub. 26, 1989)

Formation Lithology Age

Quaternary Soil, clay,sand, boulders, pebbles, etc. Recent


sediments
Karewas Clay, silt, sand Pliocene to Pleistocene

Siwalik Sandstone,claystone,siltstone Miocene to Pleistocene


and conglomerate

__________ Main Boundary Fault ____________

Murree Sandstone, claystone, siltstone Miocene to Oligocene

__________ _____ Murree Thrust ______ __________

Vihi Limestone, shale Triassic to Jurassic


Zewan Limestone, slate, Flagstone Upper Permian
Panjal Volcanic Basic lava flows Permian

Agglomeratic slate Slate with pyroclastics Upper Carboniferous

Fenestella shale Quartzite, slate, basic sill, shale Middle Carbonaceous


Syringotheris Silicified limestone, limestone Lower Carbonaceous
Limestone
Ramsu Phyllite, quartzite, Phyllitic quartzite Cambro-Silurian

Ramban Phyllite, slate, quartzite, gypsum. Proterozoic

____________ Panjal Thrust _____________

Salkhala Slate, phyllite, carbonaceous phyllite, Proterozoic


quartzite, marble with gypsum bands.

5.0 Geology of Bridge Area

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 12
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

5.1 The geological sequence of the project area is as under:

5.2 Slates/Phyllites exposures constitute bed rock in the area, in the right and left banks of Nallah .
At bridge site bed rock outcrops are exposed in the river bed right bank. Phyllites /Slate thinly
foliated with occasional Quartzite bands are commonly met with & ptygmatic folding is
pronounced. The thick sequence of meta sediments exposed are compact to blocky, with
moderate to weak strength. Occasionally micro to macro qtz veins is traversing the formations
& gives it more compactness. The weathering grade is slightly to moderately weathered. On the
regional scale they are placed as Precambrian and in the proximity theses rocks are separated
from the Murries formation by a thrust called Murree Thrust &from Salkhlas by Panjal Thrust.
These thrust, close proximately have impact on the Bridge components. The joints, partially
open to wide with variable spacing, are criss cross in nature. The multiple joints have rendered
the rocks very blocky to disturbed and susceptible to rock fall at some locations in the area. The
rock mass consists of slate/phyllite & Phyllitic quartzite interbedded with carbonaceous
phyllite. Presence of quartzite has also been detected.

5.3 Older terraces


The older terraces, made of fluvio-glacial material, have been observed on either side of the
river Dassa Nallah. The material forming this lithounit have abundant clayey content rest in
contact with the slope debris and rock fall material on the hill side and river borne material on
the downhill side along nallah course. These lithounits mostly conceal the older terraces. The
debris is made of angular to sub-angular components embedded in clayey matrix mostly
compact, whereas the rock fall being mostly thin and loose in nature. The strata are made of
pre-existing lithounits.

5.4 Slope Debris and Rock fall Material

These lithounits mostly conceal the older terraces & bed rock. The debris is made of angular to
sub-angular components embedded in clayey matrix mostly compact, whereas the rock fall
being mostly thin and loose in nature. The strata are made of pre-existing lithounits.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 13
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

5.5 River Terrace and Nallah Borne Material

This material is of Recent to Sub Recent origin and is occupied by the Dassa Nallah. and
nallah material comprises of rounded to sub-rounded boulders, pebbles, cobbles associated
with sand and silt. The river terraces are fresh brought by the fluvial processes & are pervious
in nature.

6.0 Sub Surface Geology

Subsurface Geological exploration is perquisite to establish the physical characterizes of bed


rock for the proposed project. However, the present investigation was of detailed nature as
such deep drilling was carried out, to ascertain the subsurface Geology at proposed Major
Bridge across Dassa Nallah.
The detail of drill holes are as under:-
Bore hole

borehole(
inclinatio

lithology
depth(m)
Bed rock
Borehole
Location

Depth of

Depth
Sr. No

wise
No

m)
n

0.00 -20.00(OB)
1 P1 Vertical 43 20.00
20.00-43.0(BR)

0.00 -17.00(OB)
2 P2 Vertical 40 17.00
17.00-40.0(BR)

0.00-64.00(OB)
3 P3 Vertical 73 64.0
64.00-73.00(BR)

0.00-69.00(OB)
4 P5 Bridge No 3 Vertical 78 69.0
69.00-78.00(BR)

0.00-49.00(OB)
5 P6 Vertical 63 49.0
49.00-63.00(BR)

0.00-30.00(OB)
6 P7 Vertical 61 30.0
30.00-61.00(BR)

0.00-2.00(OB)
7 A2 Vertical 27 2.0
2.00-27.00(BR)

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 14
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Note: OB (Overburden) i.e., gravel, pebble, cobble, boulder in silty sand matrix
BR (Bed Rock)

From the perusal of the core log data, following observations were made to revel the
subsurface Geology.

6.1 River Terrace and Nallah Borne Material

This material is of Recent to Sub Recent origin and is occupied by the Dasa Nallah. And
nallah material comprises of rounded to sub-rounded boulders, pebbles, cobbles associated
with sand and silt. The river terraces are fresh brought by the fluvial processes & are pervious
in nature. The estimated thickness encountered in Borehole P6 and P7 is 30.00m and 49.00m
respectively.

6.2 Colluvium (Slope Mass Debris)

Colluvium of variable thickness encountered in Boreholes P1, P2, P3, P5 at major bridge

across Dassa Nallah. It comprises angular, sub-angular and sub-rounded boulders and rock
fragments of slate/phyllite, Quartzite& Gneiss within finer rock fraction & silt.

6.3 Bed Rock – Phyllitic Quartizite

The bed rock comprises Phyllitic Quartzite & Quartzite. This unit covers the entire project area
and is often exposed or concealed under overburden of varying thickness. The megascopic
examination reveals that the rocks mass is moderately weathered to fresh (W2-W0). The depth
of weathering is anticipated is deep which is reflected from the joint planes. GreyishColoured
slightly weathered, Blocky to very blocky/sheared, medium strong to weak Phyllitic Quartzite
& interbedded occasional bands dark coloured slightly weathered to fresh Slate/Phyllites.
Slate/Phyllites is mostly of very blocky/blocky nature as the foliation planes & joint are
closely spaced. The massive milky white hard quartzite bands are also interbedded with
phyllitic quartzite.

The lithology is described with depth wise and is given below.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 15
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

BH-P1
Overburden from 0.00m to 20.00m drilling depth consisting Angular to sub angular pebbles,
cobbles& boulders of Slate & Quartzite having capping of clay matrix.

Bed rock from 20.00m to 43.00m drilling depth consisting Greyish coloured slightly to
moderately weathered to fresh, fine to coarse grained Quartzite contains random quartz veins
& interbedded shear seam/zones.

Detailed Lithological Summary of Boreholes as per below.

S. Depth
Lithology Geological Description
No. Range

Angular to sub angular pebbles, cobbles&


1 0.0-20m Slope debris boulders of Slate & Quartzite having capping of
clay matrix.

Greyish coloured slightly to moderately


weathered to fresh, fine to coarse grained
2 20-32m
Quartzite Quartzite contains random quartz veins
&interbedded shear seam/zones.

Greyish coloured slightly weathered, fine to


Quarzitic
3 32-43m coarse grained Quarzitic Schist Occasional
Schist
Quartzite veins.

BH-P2
Overburden from 0.00m to 17.00m drilling depth consisting angular pebbles of slate/phyllite
embedded in soft reddish clay matrix.Angular to sub angular pebbles, cobbles & boulders of
Quartzite, Phyllitic Quartzite &Slate. Bed rock from 17.00m to 40.00m drilling depth
consisting milky white coloured, very blocky, slightly weathered & strong Quartzite contains
reddish Iron stains on core surface and along joint planes.

Detailed Lithological Summary of Boreholes as per below.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 16
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

S. No. Depth Range Lithology Geological Description

Angular pebbles of slate/phyllite


1 0.0-1m
embedded in soft reddish clay matrix.

Angular pebbles of slate/phyllite


Slope Debris embedded in soft reddish clay matrix.
2 1.0-17m Angular to sub angular pebbles, cobbles
& boulders of Quartzite, Phyllitic
Quartzite & Slate.

Milky white coloured, very


3 17-24m blocky/disturbed, slightly weathered &
strong Quartzite.

Milky white coloured, very blocky,


slightly weathered & strong Quartzite
4 24-36m
contains reddish Iron stains on core
Quartzite surface and along joint planes.

Milky white coloured, very blocky,


5 36-40m
slightly weathered & strong Quartzite.

BH-P3
Overburden from 0.00m to 64.00m drilling depth consisting angular pebbles of slate/phyllite
embedded in soft reddish clay matrix. Angular to sub angular pebbles, cobbles& boulders of
Phyllitic Quartzite/Slate, from 64.00m to 73.00m drilling depth consisting Milky white
coloured, very blocky , slightly weathered & medium strong to strong quartzite..

Detailed Lithological Summary of Boreholes as per below.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 17
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

S. no. Depth Range Lithology Geological Description

Reddish coloured soft clay contains


1 0.0-2m
angular pebbles.

2 2 -3m Washout material coarse sand and silt.

Angular to sub angular boulders of


3 3-7m
Slope Debris Phyllitic Quartzite

Angular to sub angular boulders of


4 7-12m
Phyllitic Quartzite

Angular to sub angular


5 12-22m pebbles,cobbles& boulders of Phyllitic
Quartzite/Slate

Angular to sub angular boulders of


6 22-29m
Gneiss,Phyllitic Quartzite & Quartzite.

7 29-32m Washout material coarse sand and silt.

Angular to sub angular boulders &


8 32-45m
pebbles of Gneiss& Slate.

Angular to sub angular cobbles &


9 45-49m
boulders of Phyllitic Quartzite

Angular to sub angular boulders of


10 49-56m
Slate/phyllite & Gneiss.

Angular to sub angular pebbles, cobbles


11 56-64 boulders of Gneiss , Slate/phylite&
Phyllitic Quartzite
Milky white coloured, very blocky ,
12 64-73 QUARTZITE. slightly weathered & medium strong to
strong QUARTZITE.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 18
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

BH-P5
Overburden from 0.00m to 69.00m drilling depth consisting of boulders, cobbles and pebbles
of Phyllite, Mica Schist and Gneiss. Bed rock from 69.00m to 78.00m drilling depth consisting
Grey coloured, fine to medium grained, slightly to moderately weathered, foliated Phyllite.
Thin quartz veins are present. Detailed Lithological Summary of Boreholes as per below.

S. no. Depth Range Lithology Geological Description

Boulders, cobbles and pebbles of Phyllite,


1 0.0-69m Slope Debris
Mica Schist and Gneiss..

Gray coloured, fine to medium grained,


2 69-78m Phyllite slightly to moderately weathered, foliated
Phyllite. Thin quartz veins are present.

BH-P6
Overburden from 0.00m to 49.00m drilling depth consisting Semi angular to semi rounded
pebbles, cobbles & Boulders of Gneiss, Phyllitic Quartzite. From49.00m to 63.00m drilling
depth consisting Dark coloured, blocky slightly weathered & medium strong to weak Phyllite
contain quartz veins along foliation as well as randomly.

Detailed Lithological Summary of Boreholes as per below.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 19
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

S. no. Depth Range Lithology Geological Description


Dry sample contains angular pebbles of
1 0.0-1m Phyllite/Phyllitic Quartzite.

Semi angular to semi rounded pebbles, cobbles &


2 1-11m
Boulders of Gneiss, Phyllitic Quartzite.
Semi angular to semi rounded pebbles, cobbles &
3 11-24m Boulders of Slate/Phyllite Gneiss, Phyllitic Quartzite &
Quartzite.
Fluvio-glacial deposi Semi angular to semi rounded pebbles, cobbles &
Boulders of Gneiss & Phyllitic interbedded stiff
4 24-31m
brownish to reddish clay contains angular pebbles of
Phyllite.
5 31-32m Pebbles of Phyllite in silty sandy matrix.
Semi angular to semi rounded pebbles, cobbles &
6 32-37m Boulders of Slate/Phyllite Gneiss, Phyllitic Quartzite &
Quartzite.
Semi angular to semi rounded Bouldersof Phyllitic
7 37-39m
Quartzite .
Semi angular to semi rounded pebbles, cobbles &
8 39-42m Boulders of Gneiss, Phyllitic Quartzite & fine sandy
matrix.
Semi angular to semi rounded pebbles, cobbles &
9 42-49m Boulders of Gneiss/Schist, Phyllitic Quartzite &
Quartzite
Dark coloured, blocky slightly weathered & medium
10 49-63m strong to weak Phyllite contain quartz veins along
Phyllite foliation as well as randomly.

BH-P7

Overburden from 0.00m to 30.00m drilling depth consisting Sub rounded to sub angular
pebbles, cobbles & boulders of Gneiss, Slate & Quartzite. Bed rock from 30.00m to 61.00m
drilling depth consisting Greyish coloured, blocky, slightly weathered & medium strong fine
grained phyllitic quartzite contains random Quartz veins.

Detailed Lithological Summary of Boreholes as per below.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 20
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Depth
S. no. Lithology Geological Description
Range

Sub rounded to sub angular pebbles, cobbles &


1 0.00-4m
boulders of Slate.

Sub rounded to sub angular pebbles, cobbles &


2 4.0-9.0m
boulders of Slate, Quartzite, Gneiss & Migmatite.

Sub rounded to sub angular boulders of Slate,


3 9.0-18m
Quartzite, Gneiss & Migmatite
Fluvio-glacial
deposit
Sub rounded to sub angular pebbles, cobbles &
4 18-25m
boulders of Gneiss ,Slate /Phyllite& Quartzite

Sub rounded to sub angular pebbles, cobbles &


5 25-30 m
boulders of Gneiss ,Slate& Quartzite

Greyish colored, blocky, slightly weathered &


6 30-40 m medium strong fine grained phyllitic quartzite
contains random Quartz veins.

Greyish colored, very blocky, slightly weathered to


7 40-54m moderately & medium strong fine grained phyllitic
quartzite contains random Quartz veins.
Phyllite Greyish colored, blocky to massive, slightly
8 54-61m Quarzitic weathered & medium strong fine grained phyllitic
quartzite contains random Quartz veins.

BH-A2
Overburden from 0.00m to 2.00m drilling depth consisting angular angular pebbles & cobbles
of Phyllite. Bed rock from 2.00m to 27.00m drilling depth consisting Dark grey coloured, very
blocky slightly weathered & weak Phyllite contains occasional quartz veins.

Detailed Lithological Summary of Boreholes as per below.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 21
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

S. no. Depth Range Lithology Geological Description

1 0.0-2m Slope debris Angular pebbles & cobbles of Phyllite.

Dark grey coloured, very blocky slightly


2 2-13m weathered & weak Phyllite contains
occasional quartz veins.
Phyllite
Dark grey coloured, blocky to very
3 13-27m blocky slightly weathered & weak
Phyllite contains random quartz veins.

6.4 Exploratory Boreholes

6.4.1 Geological Appraisal of Borehole P1


This bore-hole has been drilled vertical to a depth of 43.0 mts, from ground level at RL-
1391.617mts.The bed rock comprising Greyish coloured slightly to moderately weathered to
fresh, fine to coarse grained quartzite contains random quartz veins &interbedded shear
seam/zones.. The core recovery in bed rock is of the order of 36 to 83% and R. Q. D. is NIL to
44%. The partial water loss is observed from 0.00 to 20.00m& complete water loss has been
observed from 20.00 to 43.00m.The bore is cased up to 42.00m & from 42.00 -43.00m
remains uncased indicates weakness of the slope debris & rock mass .The penetration rate
varies in slope debris from 20-40mm/min& in bed rock from 13-21mm/min .The fracture
frequency is over 15/m to 8-5/m,& ground water table has met at 19.00 drilling depth. The
SPT N-value ranges from 60-65. The expected foundation media is very blocky/blocky,
medium strong to weak Quartzite.

6.4.2 Geological Appraisal of Borehole P2


This bore-hole has been drilled vertical to a depth of 40.0 mts, from ground level at RL –
1393.438mts. The bed rock comprising Milky white coloured, very blocky , slightly weathered
& strong quartzite contains reddish Iron stains on core surface and along joint planes. Two
plus sets of joints have blocky /very blocky the rock mass. The core recovery in bed rock is of
the order of 19 to 99% and R. Q. D. is NIL to 70%. The partial water loss is observed from
0.00 to24.00m & complete water loss has been observed from 24.00 - 40. 00m.The bore is

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 22
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

cased up to 19.00m & from 19.00 -40.00m remains uncased indicates weakness of the slope
debris. The penetration rate varies in slope debris from 17-28mm/min, & in bed rock from 15-
33mm/min & fracture frequency is over 15/m to 8-5/m.The ground water table has met at
24.00 drilling depth. The expected foundation media is very blocky/blocky, strong milky white
quartzite.

6.4.3 Geological Appraisal of Borehole P3


This bore-hole has been drilled vertical to a depth of 73.0 mts, from ground level at RL –
1397.155 mts. The bed rock comprising Milky white coloured, very blocky , slightly
weathered & strong quartzite contains reddish Iron stains on core surface and along joint
planes.Two plus sets of joints have blocky /very blocky the rock mass. The core recovery in
bed rock is of the order of 30 to 90% and R. Q. D. is NIL. The partial water loss is observed
from 0.00 to 64.00m &complete water loss has been observed from 64.00 - 70. 00m.The bore
is cased up to 72.00m & from 72.00 -73.00m remains uncased indicates weakness of the slope
debris& rock mass. The penetration rate varies in slope debris from 15-25 mm/min, & in bed
rock from 15-17mm/min & fracture frequency is over 15/m to 15-8/m. The ground water
table has met at 25.00 drilling depth. The expected foundation media is very blocky/blocky,
strong milky white quartzite.

6.4.4 Geological Appraisal of Borehole P5

This bore-hole has been drilled vertical to a depth of 78.0 mts, from ground level at RL –
1394.753. The bed rock comprising Gray coloured, fine to medium grained, slightly to
moderately weathered, foliated Phyllite contains thin quartz veins. Rock mass is slightly to
moderately weathered. Two plus sets of joints have blocky /very blocky the rock mass. The
core recovery in bed rock is of the order of 44 to 66% and R. Q. D. is NIL to 32%. The nil to
partial water loss is observed from 0.00 to 78. 00m.The bore is cased up to 55.00m & from
55.00 -78.00m remains uncased indicates weakness of the slope debris &consolidation of deep
slope debris &rock mass. The penetration rate varies in slope debris from 1.67-5cm/min & in
bed rock from 1.42-2.5cm/min . The fracture frequency is over 15/m to 15-8/m &ground water
table has met at 37.00 drilling depth. The expected foundation media is very blocky/blocky,
medium strong to weak foliated Phyllite.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 23
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

6.4.5 Geological Appraisal of Borehole P6

This bore-hole has been drilled vertical to a depth of 63.0 mts, from ground level at RL –
1407.996 mts. The bed rock comprising Dark colored, blocky slightly weathered &medium
strong to weak phyllite contain quartz veins along foliation as well as randomly.Two plus sets
of joints have blocky /very blocky the rock mass. The core recovery in bed rock is of the order
of 81 to 100% and R. Q. D. is NIL to 67. The complete water loss has been observed from
00.00 - 63. 00m.The bore is cased up to 49.00m & from 49.00 -63.00m remains uncased
indicates weakness of the fluvio-glacial deposit. The penetration rate varies in slope debris
from 15-22mm/min, & in bed rock from 14-19mm/min & fracture frequency is over 15/m to
8-5/m. The ground water table has met at 5.00 drilling depth. The expected foundation media
is medium strong to weak phyllite contain quartz veins.

6.4.6 Geological Appraisal of Borehole P7

This bore-hole has been drilled vertical to a depth of 61.0 mts, from ground level at RL -
1402.101.The bed rock comprising Greyish coloured, blocky, slightly weathered & medium
strong fine grained phyllitic quartzite contains random Quartz veins. Two plus sets of joints
have blocky /very blocky the rock mass. The core recovery in bed rock is of the order of 32 to
100% and R. Q. D. is NIL to 48%. The partial is observed from 0.00 to 12.00m& 19-38m&
complete water loss has been observed from 12.00 to 19. 00m& 38-61m. The bore is cased up
to 38.00m & from 38.00 -61.00m remains uncased indicates weakness of the fluvio-glacial .
The penetration rate varies in fluvio-glacial debris from 15-20mm/min & in bed rock from 15-
20mm/min . The fracture frequency is over 15/m to 15-8/m. The ground water table has met at
3.00 drilling depth. The expected foundation media is Greyish coloured, blocky, slightly
weathered & medium strong fine grained phyllitic quartzite contains random Quartz veins.

6.4.7 Geological Appraisal of Borehole A2

This bore-hole has been drilled vertical to a depth of 27.0 mts, from ground level at RL –
1416.831mts. The bed rock comprising Dark grey colored, very blocky slightly weathered &
weak PHYLLITE contains occasional quartz veins.three plus sets of joints have blocky /very
blocky the rock mass. The core recovery in bed rock is of the order of 44 to 100% and R. Q. D.
is NIL to 100%. The partial water loss is observed from 0.00 to 27.00m. The bore is cased up

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 24
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

to 2.00m & from 2.00 -27.00m remains uncased indicates hardness of the rock mass . The
penetration rate varies in slope derisdebris from 22mm/min & in bed rock from 15-20mm/min
. The fracture frequency is over 15/m to <1/m. The ground water table has met at 7.00 drilling
depth. The expected foundation media is Dark grey coloured, very blocky slightly weathered
& weak phyllite contains occasional quartz veins

6.5 Seismicity
6.5.1 Seismo tectonic studies on the Himalayas and Parsons et al., 2006; have revealed that
some segments of the Himalayan mountain belt have not experienced major and great
earthquakes in the past 100 years or so though they have the potential to generate large
earthquakes (Gahalaut. 2006). Based on the earthquake occurrence and their locations
along the Himalayas, three main seismic gaps/segments have been Identified in the
Himalaya; Assam gap (1950 Assam and 1934 Bihar- Nepal earthquakes), Central gap
(1905 Kangra and 1934 Bihar—Nepal earthquakes) and Kashmir gap (1905 west of the
Kangra earthquake) (Khattari, 1987; Seeber and Armbruster, 1981). These gaps are
also considered as the future locations of major and great earthquakes. The study area
lies towards Southeast of Kashmir seismic gap.

6.5.2 The seismic activity in the area is attributed to the active nature of Murree Thrust, Panjal
Thrust and other deep faults present in the area. Themicro earthquake data (given in
subsequent section) suggests that the area is seismically active. Seismic hazard map of
the Jammu and Kashmir is given in Plate 2. Accordingly the study area falls within Zone
V of seismic map of India. It is therefore important to consider seismicity while
designing the civil structure as per zone-V.

Actual seismic coefficient for acceleration is evaluated on the basis of seismo tectonic
analysis of the area which is normally being undertaken by earthquake department of IIT
Roorkee and is beyond our scope. However based on IS 1893 zone factor of this area can
be considered as vertical acceleration value for design, for horizontal coefficient half of
the zone factor can be considered for design.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 25
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Plate 2

6.5.3 Massive landslides and catastrophic mass movements are a regular affair in the
Himalayas and related high ranges. The Himalaya, with the greatest relief and steep
slopes on the earth, has high magnitude landslides. Landslide hazard map given in Plate -
3 reveals that the study area is prone to landslides.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 26
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Plate 3

7.0 Laboratory Tests methodology for soil/ rock samples

7.1 Summary of Laboratory Test codes on Soil/rock Samples

SI.
Test Designation Standard Codes
No

1 Grain Size Distribution IS 2720 (Part 4)

2 Atterberg Limit IS 2720 (Part 5)

3 Moisture content determination IS 2720 (Part 5)

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 27
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

4 Bulk density IS 2720 (Part 1)

5 Specific gravity IS 2720 (Part 3)

6 Unconsolidated UndrainedTriaxial Tests IS: 2720 (Part 11)

7 Unconfined Compression Tests IS: 2720 (Part 10)

Method of Determination of Point Load


8 IS: 8764-1991
Strength Index of Rocks.
Method of Determination of Unconfined
9 IS: 9143-1991
Compressive Strength of Rock Materials.

10 Description of Discontinuities in Rock Mass- IS: 11315-1991


Core Recovery and Rock Quality.

7.2 Brief procedures of laboratory tests on soil samples


7.2.1 Particle Size Distribution
The particle size distribution were determined on soil samples in accordance with the wet
sieving method described in IS: 2720 (Part 4). Compliance with the Standard, with respect to
minimum sample quantity is dependent on the maximum significant grain size and the method
of sampling. In particular, for SPT samples, the quantity of soil available for testing is typically
about 100g. This sample quantity is considered representative where grain sizes range up to
4.75mm (i.e. to coarse sand size). Where significant quantities of coarser particles are present,
the particle size distribution obtained from such samples should be regarded as indicative only.

7.2.2 Sedimentation / Hydrometer Analysis


Sedimentation analyses were performed for soil samples in accordance with the hydrometer
method described in IS: 2720 (Part 4). The analysis provides an estimate of the particle size
distribution for the fine fraction (<75μm) of a soil sample. The analysis is performed by
monitoring the rate of settlement of soil particles initially suspended uniformly in distilled water.
The rate of settlement, which is monitored by observing the change in fluid density with the
hydrometer device, is theoretically related to the size of particles setting out of suspension

7.2.3 Atterberg’s Limits


The Atterberg’s Limits comprising liquid limit, plastic limit, shrinkage limit and plasticity index
were performed on soil samples in accordance with the relevant methods described in IS: 2720

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 28
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

(Part 5 & 6). The liquid limit has been determined using the Casagrande apparatus method. The
soil sample preparation, in accordance with the code of practice, included removal of soil
particles retained on the 425μm sieve. Accordingly, where a significant quantity of coarser
particles was present, it should be noted that the Atterberg Limits results are representative of the
relatively fine soil fraction, and not of the complete soil sample.

7.2.4 Natural Moisture Content, Density and Specific Gravity


Natural moisture content of undisturbed soil samples collected from trial pits, has been
determined as per procedure given in IS 2720 (Part-II). Bulk density and dry density of the
undisturbed samples has been determined using mass and volume of the same and natural
moisture content. The specific gravity tests specified in the Indian Standard (IS 2720 Part-II

7.2.5 Saturated Moisture Content, Unit Weight, Specific Gravity and Porosity of Rock specimen
were determined for rock samples by using saturation and buoyancy technique, in accordance
with the methods of IS:13030.

7.2.6 Test Point load Index tests were performed on selected rock lump and rock specimen, not
amenable to UCS test, in accordance with the method suggested by IS: 8764 (1978) and
International Society for Rock Mechanics.

7.2.7 Uniaxial compressive strength for cylindrical rock specimens was determined in accordance
with the methods of ISRM. The uniaxial compressive strength of the specimen was corrected
for a height to diameter ratio of two for specimens whose height to diameter ratio was other
than two using the following relationship:

qc (corrected) = (qc 0.889)/ (0.778+ (0.222D/H))

Where,

qc = Uncorrected Uniaxial Compressive Strength


D = Diameter of the specimen tested
H = Height of the Specimen Tested

Brief procedures of laboratory tests on rock samples

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 29
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

7.2.8 Water content determination


The container with its lid is cleaned and dried, and its mass m1 is determined. A representative
sample comprised at least 10 lumps each having either a mass of at least 50 g or a minimum
dimensions of ten times the maximum grain size, whichever is greater, is selected. For in situ
water content determination sampling, storage and handling precautions should be such that
water content remains within 1 percent of the in situ value.The sample is placed in the
container, the lid replaced and the mass m2 of the sample plus container determined. The lid is
removed and the sample dried to constant mass at a temperature of 105 ± 3°C.The lid is
replaced and the sample allowed to cool in the desiccator for 30 minutes. The mass m3 of
sample plus container is determined.

The water content shall be calculated from the following formula:

Water content, w= m2 - m3 X 100 ( percent )


m3 – m1
m1 = Mass in g of the container with its lid at room temperature
m2= Mass in g of the container with its lid and the sample at room temperature

m3= Mass in g of the container with its lid and the sample after drying

7.2.9 Porosity And Density Determination Using Saturation And Buoyancy Techniques

a) A representative sample comprising at least 10 lumps of regular or irregular geometry, each


having either a mass of at least 50 g or a minimum dimension of at least 10 times the
maximum grain size, whichever is the greater, is selected. The sample is washed in water to
remove dust.
b) The sample is saturated by water immersion in a vacuum of less than 0.8 kPa for a period of at
least 1 h, with periodic agitation to remove trapped air.
c) The temperature, t of the water in the immersion bath to the nearest degree centigrade is
determined.
d) The mass, M1, of the basket sub- merged in the immersion bath is determined.
e) The sample is transferred under water to the basket in the immersion bath. The saturated-
submerged mass, M2 of the basket plus sample to an accuracy of 0.01 percent of the sample
mass is taken
f) The mass, M3, of a clean, dry sample container and lid is determined.

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 30
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

g) The sample is removed from the immersion bath and surface dry the sample with a moist
cloth, care being taken to remove only surface water and to ensure that no rock fragment are
lost. The sample is transferred to the sample container and replace the lid. The mass, M4, of
the saturated surface dry sample plus container is determined.
h) The lid is removed and place the container with contents and lid in the oven and dry at 105 &
3°C. The sample is deemed to be dry when the difference between successive determination of
mass of the cooled sample at interval of 4 hours does not exceed 0.1 percent of the original
mass of the sample.
i) Replacing the lid, remove the container from the oven and place the whole in the desiccator to
cool for 30 minutes.
k) The dried mass, M5, of the container with the oven dry sample is determined.

Calculations

a) Calculate the saturated-submerged mass,


Msub, of the sample
Msub= M2 – M1 (kg)

b) Calculate the saturated-surface-dry mass,


Msat, of the sample
Msat = M4 – M3 ( kg )
c) Calculate the dry mass (Grain Weight )
MS, of the sample
Ms = M5-M3 (kg)
d) Calculate the bulk-volume, V, of the sample by the following formula:
V = (Msat – Msub) (m3)
бw

бw = density of water at temperature t


e) Calculate the pore volume, Vv, of the sample by following formula:

Vv = (Msat – Ms) x 100 (percent)


Msat – Msub

f) Calculate porosity, n, of the rock sample by the following formula :


n = (Vv/V) x 100 (percent)
or = (Msat – Ms) x 100 (percent)
Msat – Msub
g) Calculate the dry density, Pa, of the rock sample by the following formula:

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 31
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Pd = (Ms) (kg/m3)
V

7.2.10 Uniaxial compressive strength

The ability of spherical seat to rotate freely shall be checked before each test. The surfaces of
the two bearing discs and the test specimen shall be wiped clean. The specimen shall be kept
on the lower disc. The axis of the specimen shall be carefully aligned with the centre of the
thrust of the spherical seat. As the load is gradually brought to bear on the specimen, the
movable portion of the spherically seated disc shall be adjusted to ensure uniform seating.
Load on the specimen shall be applied continuously at a constant stress rate such that failure
will take place in about 5 to 15 minutes of loading. Alternatively, the stress rate shall be within
the limits of 0.5 MPa/s to 1 MPa/s. The maximum load on the specimen shall be recorded in N
within 1 Percent accuracy. The number of specimens to be tested should be determined from
practical considerations.

CALCULATION
The unconfined compressive strength of the specimen shall be calculated by dividing the
maximum load carried by the specimen during the test, by the average original cross-sectional
area.

8.0 Geotechnical Assessment

8.1 The sub-surface in general is based on Boreholes drilled at P1, P2,P3, P5,P6 and P7 locations
respectively is comprises of Metamorphic rock-Phyllitic Quartizites of different alterations
underlying colluvium (Pebbles , Cobbles , Boulders of Phyllitic Quartizite, Schists with sandy
matrix). The thickness of colluviums( gravel, boulder, pebble, cobble,) ranges from 20 to 69 mtrs
in pier locations The drilling through bed rock of Phyllitic Quartizite has shown RQD nil to 100.
The rock mass rating (RMR) is found to of poor to fair class.

The Geological cross sectional profile is given in Plate IV

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 32
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 33
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Table -3
Parameters P1 P2 P3 P5 P6 P7 A2
Over burden in 64 49 30 2
20 17 69
(m)
Overburden
Overburden(Semi
Overburden (angular Overburden consists of
angular to semi Overburden
Overburden (angular pebbles of Slate phyllite (angular to boulders, cobbles
rounded pebbles (subrounded to sub Overburden
to subangular pebbles embedded in soft subangular and pebbles of
,cobbles & boulders angular boulders of (angular pebbles
,cobbles & boulders reddish clay pebbles ,cobbles Phyllite, Mica
of Gneiss ,Phyllitic Slate Quartizite, &cobbles of
of Slate & Quartizite matrix.Angular to & boulders of Schist and geneiss
Quartizite) Gneiss & Migmatite phyllite)
having capping of subangular pebbles , Slate ,Phyllitic and rock Gray
Bedrock(Dark and rock of grayish Bedrock(dark grey
Rock type clay matrix and rock cobbles & boulders of Quartizite) coloured, fine to
coloured ,blocky coloured blocky, coloured,very
of Greyish coloured Quartizite Phyllitic Bedrock (milky medium grained,
slightly weathered & slightly weathered & blocky slightly
slightly to moderately Quartizite & Slate and white slightly to
medium strong weak medium strong fine weathered &weak
weathered to fresh , rock of Milky white coloured,very moderately
phyllite contain grained Phyllitic phyllite contains
fine to coarse grained coloured, very blocky, blocky, slightly weathered, foliated
Quartz veins along Quartizite contains quartz veins)
Quartizite slightly weathered & weathered & Phyllite. Thin
foliation as well as random Quartz veins
strong Quartizite strong Quartizite quartz veins are
randomly)
present.
Core recovery % 20-83 19-98 10-91 22-100 29-100 30-100 30-100
RQD Nil -46 Nil -70 Nil-26 Nil -32 Nil-67 Nil-48 Nil -100
RMR Poor Poor-fair Poor Poor Poor-fair Poor Poor-fair
Depth of water
29 24 25 37 5 3.0 7
table (m)
Any geological
structure met No No No No No No No
with
UCS(Normal/su Under progress 36.82/32.83 Under progress
bmerged) (MPa)
Point Load 1.88
(MPa)
Porosity % 0.89
Water absorp % 0.33
Bulk Density 2.745/2.736
/Dry density (%)
Specific gravity 2.760
(gm/cc)

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 34
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No : P1(Br-3)
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Drilling Depth
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
UCS Rating
3 3 8 3 8 3 8 8 8 3 3 3 3 8 3 3 3 3 3 3 3 3 3
RQD Rating
8 8 10 8 8 8 10 10 10 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Spacing of discontinuities
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Persistance
Condition of discontinuities

4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Aperture
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Roughness
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Infilling
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Ground water conditions
38 38 45 38 43 38 45 45 45 38 38 38 38 43 38 38 38 38 38 38 38 38 38
Adjustment strike and dip
-7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7
orientation
RMR Value 31 31 38 31 36 31 38 38 38 31 31 31 31 36 31 31 31 31 31 31 31 31 31

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 35
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No : P2(Br-3)

Drilling Depth 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

UCS Rating 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

RQD Rating 3 3 3 3 3 3 3 3 3 3 3 8 8 13 13 13 3 13 8 8 3 3 3

Spacing of discontinuities 8 8 8 8 8 8 8 8 8 8 8 10 10 10 10 10 8 10 10 10 8 8 8

Persistance 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Condition of discontinuities
Aperture 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Roughness 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Infilling 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Weathering 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Ground water conditions 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

38 38 38 38 38 38 38 38 38 38 38 45 45 50 50 50 38 50 45 45 38 38 38

Adjustment strike and dip


-7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7
orientation

RMR Value 31 31 31 31 31 31 31 31 31 31 31 38 38 43 43 43 31 43 38 38 31 31 31

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 36
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No : P3(Br-3)
Drilling Depth 64.00 65.00 66.00 67.00 68.00 69.00 70.00 71.00 72.00 73.00

UCS Rating 4 4 4 4 4 4 4 4 4
RQD Rating 3 8 3 3 3 3 3 3 3
Spacing of discontinuities 8 10 8 8 8 8 8 8 8

Condition of discontinuities
Persistance 2 2 2 2 2 2 2 2 2
Aperture 4 4 4 4 4 4 4 4 4
Roughness 5 5 5 5 5 5 5 5 5
Infilling 6 6 6 6 6 6 6 6 6
Weathering 6 6 6 6 6 6 6 6 6
Ground water conditions 0 0 0 0 0 0 0 0 0
Adjustment strike and dip orientation -7 -7 -7 -7 -7 -7 -7 -7 -7
RMR Value 31 38 31 31 31 31 31 31 31

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 37
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No : P5(Br-3)

Drilling Depth 69 70 71 72 73 74 75 76 77 78

UCS Rating 4 4 4 4 4 4 4 4 4

RQD Rating 8 3 3 3 3 3 3 3 3

Spacing of discontinuities 8 8 8 8 8 8 8 8 8

Persistance Condition of discontinuities 2 2 2 2 2 2 2 2 2

Aperture 4 4 4 4 4 4 4 4 4

Roughness 5 5 5 5 5 5 5 5 5

Infilling 6 6 6 6 6 6 6 6 6

Weathering 6 6 6 6 6 6 6 6 6

Ground water conditions 0 0 0 0 0 0 0 0 0

Adjustment strike and dip


-7 -7 -7 -7 -7 -7 -7 -7 -7
orientation

RMR Value 36 31 31 31 31 31 31 31 31

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 38
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No : P6(Br-3)
Drilling Depth 49.00 50.00 51.00 52.00 53.00 54.00 55.00 56.00 57.00 58.00 59.00 60.00 61.00 62.00 63.00

UCS Rating 4 4 4 4 4 4 4 4 4 4 4 4 4 4

RQD Rating 3 3 8 8 13 8 3 3 13 3 13 8 3 8

Spacing of discontinuities 10 10 10 10 15 8 8 8 15 8 15 10 10 10

Persistance 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Aperture Condition of discontinuities 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Roughness 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Infilling 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Weathering 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Ground water conditions 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Adjustment strike and dip orientation -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7

RMR Value 33 33 38 38 48 36 31 31 48 31 48 38 33 38

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 39
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No :
P7(Br-3)

Drilling Depth 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61

UCS Rating 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

RQD Rating 8 8 8 3 8 8 3 3 3 3 3 3 3 8 8 3 3 3 3 3 3 3 3 3 3 8 8 8 8 8 8

Spacing of discontinuities 10 10 10 8 10 10 8 8 8 8 8 8 8 10 10 8 8 8 8 8 8 8 8 8 8 10 10 10 10 10 10

Persistance 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Condition of discontinuities

Aperture 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Roughness 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Infilling 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Weathering 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Ground water conditions 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


Adjustment strike
-7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7
and dip orientation
RMR Value 38 38 38 31 38 38 31 31 31 31 31 31 31 38 38 31 31 31 31 31 31 31 31 31 31 38 38 38 38 38 38

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 40
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Borehole No : A2(Br-3)

2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0
Drilling Depth

4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
UCS Rating

3 3 3 3 3 3 8 3 3 3 3 8 8 3 8 20 3 3 3 3 8 8 3 13 20
RQD Rating
Spacing of 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 15 10 10 10 10 10 10 10 10 15
discontinuities

2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Persistence
Condition of discontinuities

4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Aperture

5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Roughness

6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Infilling

6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering
Ground water 15 15 15 15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
conditions
Adjustment strike and -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7
dip orientation

48 48 48 48 33 33 38 33 33 33 33 38 38 33 38 55 33 33 33 33 38 38 33 43 55
RMR Value

SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 41
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

9.0 FOUNDATION CONSIDERATIONS


For gravel, pebble, coble, boulder in sand matrix
Settlement criteria based Teng’s Modified criteria
Shear criteria – IS 6403

9.1 Bearing Capacity

The subsurface in general at all the borehole locations can be considered as sedimentary
formations comprising of Boulders, gravel, cobble with sandy matrix The overlying
Phyllitic Quartizites of different alterations over burden material neither falls in rocks
nor under soil and the investigation for establishing design parameters in such materials
have be carried out in accordance with IS: 10042whichnecessities conducting in situplate
load tests, blocks hear tests and in-situ density measurements. Such types of deposits be
have peculiarly, initially these materials upon loadings how rapid increase in settlement
and beyond about 1% settlement with increasing loads the rate of settlement decreases.
This is primarily due to the fact that unlike ordinary soils these materials show initial
rapid compression and once particle to particle contact gets established the compression
decrease considerably with load carrying function mainly be in taken over by the larger
sized particles. Figure-2of IS:10042bringoutthis behavior clearly.

The material that is met with at the proposed bridge site is somewhat similar to that is
reported in Figure-2 of IS: 10042 which is reproduced below for reference and better
understanding.

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 42
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

It is observed from the afore said figure that settlement ratio (ratio of settlement observed
in the case of large size to settlement of small size) increases with the increase in size of
test plate. In accordance with IS:1888 for permissible settlement of 25mm for shallow
foundation of 8mx8msize,the allowable bearing capacity of gravel boulder is evaluated
from Figure-2 corresponding to settlement of plate as per equation Sp=Sf
[B(Bp+0.3)/Bp(B+0.3)]² =17.22mm. For settlement of 17.22mm,the allowable bearing
capacity works out to be 4.2kg/cm2 or 42t/m2. On the other hand, Teng’s modified
allowable bearing capacity for gravelly soils for 25mm settlement given by
q25=3.35xCb(N-3)[(B+0.3)/2B]2dwdf (in which Cb=constant=2 for gravelly soil sand dw
&df are water table reduction factor and depth factor respectively) .With depth factor
dflimited to 1.33 for deep foundation and water table correction factor as 0.5,the net
allowable bearing capacity for 25mm permissible settlement works out to be 56.35t/m²for
8m dia well with depth of foundation at 20m.However the gross allowable bearing
capacity shall be limited to (42+20)=62t/m2.

Under shear consideration for Ø = 34o, the safe bearing capacity in accordance with IS
6403 the safe bearing capacity works out to be greater than 100t/m2 for width of 8m.

Sample calculation has been given in Annexure III

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 43
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Bearing capacity values of P5 and P7

Net Allowable Net Allowable


Gross Allowable Gross Allowable
Bearing Capacity Bearing Capacity
Depth Dia of well Bearing Capacity Bearing Capacity
Location No for 25mm for 40mm
(m) (m) for25mm Permissible for40mm permissible
Permissible permissible
Settlement(t/m2) settlement(t/m2)
Settlement(t/m2) settlement(t/m2)

8 42 62 67 87
20
10 41 61 65 85
P3
8 69 99 107 137
30
10 68 98 104 134

8 42 62 67 87
20
10 41 61 65 85
P5
8 69 99 107 137
30
10 68 98 104 134

8 42 62 67 87
20
10 41 61 65 85
P6
8 69 99 107 137
30
10 68 98 104 134

8 42 62 67 87
20 P7
10 41 61 65 85

9.3 FOUNDATION CONSIDERATIONS IN ROCKY STRATA


Considering the provisions of IS 12070 the safe bearing pressure based on RMR and
Uniaxial compressive strength is given as under :

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 44
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

Gross Safe Bearing


Net safe Bearing
Depth Pressure(t/m2) Allowable bearing pressure
Location No Pressure(t/m2)
(m) from UCS (t/m2)
from RMR cosiderations
cosiderations

21.0 P1 103 206 100

18.0 P2 103 206 100

31.0 P7 135 206 120

3.0 A2 112 206 110

Sample calculation has been given in Annexure III

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 45
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

10.0 Conclusion and Recommendations

1. As per IS code 10042 it is not reliable to believe on the laboratory tests of disturbed
samples, as the natural arrangements of the grains and matrix material are never achieved
by re compaction the best results are obtained by properly chosen field test.

2. We opine to use the aforesaid values limiting the net bearing capacity values for well
foundation to 110t/m2 or the values given in section 8.6 whichever is lower ensuring at
least 1.0m embedment in rock subject to the condition that rock type available at site
same as given in the reference boreholes. However, deep well foundation will not be
feasible from practical consideration.

3 Adequate protective measures for the abutment slopes may be suitably provided during
construction stage at the proposed bridge sites.

4. The detailed geological mapping may be carried out to delineate the different geological
formation and related problems likely to be encountered during the construction stage.
The Bridge sites lie in seismic zone V (IS 1893 Part-1) 2002 for adopting suitable seismic
coefficient for civil engineering structures in the area

5. Indian railway standard code of practice for the design of structure and design of bridges
(Revised 1985) may be adopted for the design of bridge.

Consultant
Space Engineers Consortium Pvt. Ltd

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 46
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 47
USBRL Project Jammu And Kashmir
HCC Limited
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
BR-03 P1
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+196
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 5111079.245E, 3684672.283N FEATURE Major Bridge Abutment
COLLAR ELEVATION (m) 1391.717 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 43.00
GROUND ELEVATION(m) 1391.617 TYPE(S) OF CORE BARREL Triple Tube
STARTED : 15.03.2018 COMPLETED 25.03.2018 DRILLING AGENCY : SECP Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log

15

25

35

60
25
_
_
_
_
_

_
1.000 1.00

20

29

36

65
30
_
_
_
_
_

2.000 2.00

20 40
_

2
_
_

3.000 3.00

PX

PX
25 40
_
_
_
2
_

4.000 4.00

30 45
_
_
2
1

5.000 5.00

20 40
_
_
_
_
_

6.000 6.00

28 35
_
_
2
_
_

7.000 7.00

25 40
_
_
_
_
_

8.000 8.00
Slope Debris(Colluvium)

Slope Debris(Colluvium)

25 50
_
_
2
_
_

9.000
Angular to sub
9.00

Not Applicable
angular
pebbles,cobbles Overburden
30 50
_
_
1
1
_

Partial
10.000 10.00
& boulders of
Slate & Quartzite 30 30
_
_
2
_
_

11.000 11.00
having capping
of clay matrix. 30 40
_
_
2
_
_

12.000 12.00
HX

HX
23 40
_
_
2
_
_

13.000 13.00

30 50
_
_
3
1
_

14.000 14.00
Dry

34 40
_
_
5
_
_

15.000 15.00

30 45
_
_
1
_
_

16.000 16.00

35 50
_
_

1
1

17.000 17.00
IMP (NX Size ) Diamond Bit

46 50
_
_
1
2
_

18.000 18.00

41 40
_
_
1
2
_

19.000 19.00
Core samples

30 50
_
_
1
_
_

20.000 20.00
Very Very
40 17 60
_
_
_
_
1

Over 15

blocky/shea blocky/s
21.000 21.00 red heared
Very Very
42 NIL 55
_
_
2
1
_

blocky/shea blocky/s
22.000 22.00 red heared
15-8

Blocky Blocky 63 42 60
_
_
1
_
2

23.000 23.00
Over

Greyish colored
15

Blocky Blocky 41 10 60
_
_
2
2

24.000 24.00 slightly to


moderately
15-8

Blocky Blocky 52 27 60
_
_
2
1
1

25.000 25.00 weathered to


fresh, fine to
Over
15

Blocky Blocky 51 12 65
_
_
2
2
_

26.000 26.00 coarse grained


QUARTZITE
Blocky Blocky 66 30 60
_
_
1
2
1

27.000 27.00 contains random


quartz veins &
15-8

NX

NX

Blocky Blocky 83 46 70
_
_
3
1
2

28.000 28.00 interbedded


shear
Complete

Blocky Blocky 60 44 65
_
_
1
_
2

29.000 29.00 seam/zones.


29

Very Very
68 13 70
_
_
1
1
1

blocky/sheablocky/s
30.000 30.00 red heared
Very Very
72 NIL 70
_
_
2
2
1

blocky/sheablocky/s
31.000 31.00 red heared
Very Very
64 14 60
_
_
1
2
1

blocky/sheablocky/s
32.000 32.00 red heared
Very Very
53 NIL 65
_
_
6
_
_

blocky/sheablocky/s
33.000 33.00 red heared
Over 15

Greyish colored Very Very


58 NIL 70
_
_
3
2

34.000
slightly blocky/sheablocky/s
34.00 red heared
weathered, fine
Very
to coarse Very block 36 NIL 75
_
_
2
1
_

35.000 35.00 block


grained
Very
QUARTZITIC Very block 63 NIL 70
_
_
7
1
_

36.000 36.00 block


SCHIST
Very
occasional Very block 60 NIL 60
_
_
4
1
_

37.000 37.00 block


Quartzite veins.
Very
Very block 48 NIL 48
_
_
4
1
_

38.000 38.00 block

LOGGED BY : Javeed Ahmad Ganaie CHECKED BY :

Page 48
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
BR-03 P1
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+196
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 5111079.245E, 3684672.283N FEATURE Major Bridge Abutment
COLLAR ELEVATION (m) 1391.717 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 43.00
GROUND ELEVATION(m) 1391.617 TYPE(S) OF CORE BARRELTriple Tube
STARTED : 15.03.2018 COMPLETED 25.03.2018 DRILLING AGENCY : SECP Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
Very
Very block 60 60
_
_
5
1
_

_
Greyish colored block

IMP (NX Size ) Diamond Bit


39.000 39.00 NIL
slightly
Very
weathered to Very block 41 70
_
_
5
_
_

Core samples
40.000 40.00 block NIL

NX

Complete
fresh, fine to

Over 15
Very

NX
coarse grained Very block 53 12 60
_
_
2
1
1

41.000 41.00 block


QUARTZITIC
Very
SCHIST Very block 63 14 65
_
_
2
3
1

42.000 42.00 block


occasional

NIL
Very
Quartzite veins. Very block 82 10 60
_
_
1
6

43.000 43.00 block End of Borehole

NB: Pl-Planer ,Sm-Smooth,Un-Undulating,Rg-Rough,St-Stepped,Sl-Silica Filling,Cl-Clay,Py-Pyrite and Fr-Fractured.

INDEX Core Recovery

Overburden Bed Rock Boundary

Quartzite/Quarzitic
Schist

LOGGED BY : Javeed Ahmad Ganaie CHECKED BY :

Page 49
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO. P2
SHEET NO.: 1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+236.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511096.700E,3684709.815N FEATURE P2(Br-3)
COLLAR ELEVATION (m) 1393.538 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 40.00
GROUND ELEVATION(m) 1393.438 TYPE(S) OF CORE BARREL DT/TT
STARTED : 01.04.2018 COMPLETED 24.04.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Size of core Structural Drill Water SPT-Number of
Lithology Ratio Percent Core Recovery (%) Loss Permeability
pieces (In No's) Condition Blows

Fracture Frequency / m

Depth of water level(m)


Ground Elevation (m)

Interpreted %age of
Special

Interpreted %age of

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

rock fragments

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
10 to 25 mm interpretations /
25 to 75 mm

Test section
0.00 - 19.99

Size of hole

mm/s OR
Depth (m)

Description

Description

Type of Bit
matrix (fine)
Weathering Grade

LUGEON
(mm/min)
Complete
>150 mm

In figures
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
Angular pebbles of
slate/phyllite embedded in 25
1.000 1.00 soft reddish clay matrix.

22 22
2.000 2.00

28 22
3.000 3.00

20 20
4.000 4.00

26 17
5.000 5.00

25 18
6.000 6.00
Slope Mass Debris (Colliuvum)

Slope Mass Debris (Colliuvum)

25 17
7.000 7.00

Angular pebbles of 30 17

Not Applicable
Overburden
8.000 8.00 slate/phyllite
embedded in soft
reddish clay matrix. 25 18
9.000 9.00
Angular to sub angular

NX
pebbles, cobbles & 23 17
10.000 10.00 boulders of Quartzite,
Phyllitic Quartzite &
Slate. 30 17
11.000 11.00

30 17

Partial
12.000 12.00

Dry
30 20
13.000 13.00

32 28
14.000 14.00

35 20
15.000 15.00

30 18
16.000 16.00

32 17
17.000 17.00
IMP (Nx size) Diamond Core Bit

Very
Very blocky
/disrturbed
blocky 30 NIL 18
18.000 18.00 /disrturbed
Core Samples

Very
Very blocky
/disrturbed
blocky 40 NIL 17
19.000 19.00 /disrturbed
NX

Very
Very blocky
/disrturbed
blocky 19 NIL 33
20.000 20.00 Milky white colored, /disrturbed
very Very
Very blocky
blocky/disturbed , /disrturbed
blocky 35 NIL 18
21.000 21.00 /disrturbed
slightly weathered &
Very
strong QUARTZITE. Very blocky
/disrturbed
blocky 28 NIL 17
22.000 22.00 /disrturbed
Over 15

Very
Very blocky
/disrturbed
blocky 52 11 18
23.000 23.00 /disrturbed

Very
Very blocky
/disrturbed
blocky 42 15 17
24.000 24.00 /disrturbed
24

Very
Very blocky
/disrturbed
blocky 46 25 15
25.000 25.00 /disrturbed

Very
Very blocky
/disrturbed
blocky 86 24 17
26.000 26.00 /disrturbed
Joint planes
0 0
50 (3) , 30 (1), 70 NIL 15
Sm/Pl & Iron
27.000 27.00 stains
Joint planes
0 0
75 (1) , 45 (1), 94 21 15
Sm/Pl & Iron
28.000 28.00 stains
Joint planes
NIL

0
Milky white colored, 45 (4) Sm/Pl & 98 40 15
15-8

29.000 29.00 Iron stains


very blocky , slightly
Joint planes 45-
weathered & strong 0
50 (3) Sm/Pl & 94 35 15
30.000 30.00 QUARTZITE Iron stains/fresh

contains reddish Joint planes


Complete

0
Iron stains on core 45 (5) Sm/Pl & 94 70 17
31.000 31.00 Iron stains
surface and along Joint planes
8-5

joint planes. 0 0
45 (4) , 75 (1), 98 61 15
Sm/Pl & Iron
32.000 32.00 stains

Blocky Blocky 98 58 17
33.000 33.00
Joint planes
Over
15

0
50 (1) Sm/Pl & 98 NIL 15
34.000 34.00 Iron stains
Joint planes 40-
8-5

0
50 (2) Sm/Pl & 96 69 17
35.000 35.00 Iron stains
Joint planes
0
45 (3) Sm/Pl & 98 43 15
15-8

36.000 36.00 Iron stains


Joint planes 45-
Milky white colored, 0
50 (2) Sm/Pl & 99 48 15
37.000 37.00 very blocky , slightly Iron stains

weathered & strong Joint planes


Over
15

0
QUARTZITE. 50 (2) Sm/Pl & 97 20 15
38.000 38.00 fresh

LOGGED BY : Javeed Ganaie CHECKED BY :

Page 50
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P2
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+236.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511096.700E,3684709.815N FEATURE P2(Br-3)
COLLAR ELEVATION (m) 1393.538 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 40.00
GROUND ELEVATION(m) 1393.438 TYPE(S) OF CORE BARRELDT/TT
STARTED : 26.03.2018 COMPLETED 24.04.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

Bit Bit
20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type ofCore
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing
IMP (Nx size) Diamond

Partial

15-30
30-45
0-15
Log

Log

Core Samples
Joint planes

Complete
0 0
68 11 17

Over 15

Not Met
50 (2), 25 (1)
Milky white colored, very
39.000 39.00 Sm/Pl & fresh

NIL
NX
blocky , slightly weathered
& strong QUARTZITE.
Blocky Blocky 70 15 17
40.000 40.00

NB: Pl-Planer ,Sm-Smooth,Un-Undulating,Rg-Rough,St-Stepped,Sl-Silica Filling,Cl-Clay,Py-Pyrite and Fr-Fractured.

INDEX Core Recovery

Overburden Bed Rock Boundary

Quartzite

LOGGED BY : Javeed Ganaie CHECKED BY :

Page 51
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P3
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE P3(BR-3)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 73.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARREL Triple Tube
STARTED : 26.03.2018 COMPLETED 08.05.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
0.500 Reddish - - - - -
1.000 1.00 coloured soft 20
1.500 clay contains
- - - - -
2.000 2.00 angular pebbles. 17
2.500 Washout material
2 - - - - 30
3.000 3.00 coarse sand and 18
silt.
3.500
5 - - - - 30
4.000 4.00 22
Angular to sub
4.500
angular pebbles 3 - - - - 33
5.000 5.00 17
& cobbles of
5.500
Slate & Phyllitic 7 - - - - 32
6.000 6.00 18
Quartzite .
6.500
3 - - - - 33
7.000 7.00 17
7.500
7 - - - - 51
8.000 8.00 17

HX
HX
8.500
3 2 1 - - 90
9.000 9.00 Angular to sub 20
9.500 angular boulders
5 - - - - 60
10.000 10.00 of Phyllitic 15
10.500 Quartzite
4 1 - - - 55
11.000 11.00 17
11.500
6 1 - - - 65
12.000 12.00 18
12.500
5 - - - - 60
13.000 13.00 17
13.500
6 - - - - 55
14.000 14.00 20
14.500
5 - - - - 55
15.000 15.00 18
15.500
5 - - - - 50
16.000 16.00 Angular to sub 15
16.500 angular 7 - - - - 50
17.000 17.00 pebbles,cobbles 17
17.500 & boulders of
Slope Debris (Colliuvum)

Slope Debris (Colliuvum)

2 - - - - 40
18.000 18.00 Phyllitic 18
Not Applicable

Core Samples

Quartzite/Slate
Overburden

18.500
5 - - - - 55
Partial

19.000 19.00 17
19.500
5 - - - - 40
20.000 20.00 20
20.500
5 - - - - 55
21.000 21.00 18
21.500
3 - 1 - - 80
22.000 22.00 17
22.500
1 1 1 - - 58
23.000 23.00 18
23.500
3 - - - - 48
24.000 24.00 17
24.500 Angular to sub 8 - - - - 44
25.000 25.00 angular boulders 18
25.500 of
3 2 - - - 63
25

26.000 26.00 Gneiss,Phyllitic 17


26.500 Quartzite &
2 - - - - 23
27.000 27.00 Quartzite. 18
NX
NX

27.500
- 1 - - - 24
28.000 28.00 17
28.500
4 - - - - 43
29.000 29.00 15
29.500
- - - - - 13
30.000 30.00 20
Washout material
30.500
coarse sand and - - - - - 10
31.000 31.00 silt. 25
31.500
- - - - -
32.000 32.00 25
32.500
2 - - - - 18
33.000 33.00 18
33.500
4 1 - - - 43
34.000 34.00 15
34.500 Angular to sub - - - 1 - 79
35.000 35.00 angular boulders 15
35.500 of Gneiss &
4 - - - - 55
36.000 36.00 Slate. 20
36.500
1 1 - - - 30
37.000 37.00 22
37.500
3 - - - - 31
38.000 38.00 22

LOGGED BY : Javeed Ganaie CHECKED BY :

Page 52
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P3
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE P3(BR-3)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 73.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARRELTriple Tube
STARTED : 26.03.2018 COMPLETED 04.09.2016 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
38.500
2 1 - - - 30
_

39.000 39.00 _ 22
39.500
- 2 - - - 41
_

40.000 40.00 22
40.500
2 - - - - 38
_

41.000 41.00 Angular to sub 22


41.500 angular boulders
3 - - - - 33
_

42.000 42.00 & pebbles of 25


42.500 Gneiss & Slate.
3 - - - - 29
_

43.000 43.00 20
43.500
4 - - - - 35
_

44.000 44.00 20
44.500
3 - - - - 35
_

45.000 45.00 22
45.500
4 - - - - 34
_

46.000 46.00 25
46.500 Angular to sub 2 2 - - - 40
_

47.000 47.00 angular cobbles 20


47.500 & boulders of
3 1 - - - 40
_

48.000 48.00 Phyllitic Quartzite. 20


48.500
- - 1 - - 46
_

49.000 49.00 18
49.500
Slope Debris (Colliuvum)

Slope Debris (Colliuvum)

3 1 - - - 45
_

50.000 50.00 20
Not Applicable
Overburden

50.500
3 - - - - 50
_

Partial
51.000 51.00 20
51.500
2 1 - - - 38
_

52.000 52.00 Angular to sub 22


52.500 angular boulders
2 - - - - 30
_

53.000 53.00 of Slate/phyllite 25


53.500 & Gneiss.
IMP (Nx size) Diamond Core Bit

2 1 - - - 40
_

54.000 54.00 22
54.500
4 - - - - 45
_

Core samples
55.00 25
NX

55.000
NX

55.500
- 1 - - - 36
_

56.000 56.00 25
56.500
5 - - - - 34
_

57.000 57.00 22
57.500
2 1 - - - 37
_

58.000 58.00 25
58.500 Angular to sub 1 2 - - - 46
_

59.000 59.00 angular pebbles 22


59.500 ,cobbles
4 1 - - - 44
_

60.000 60.00 boulders of 22


60.500 Gneiss ,
2 1 - - - 62
_

61.000 61.00 Slate/phylite & 17


61.500 Phyllitic Quartzite
2 1 - - - 40
_

62.000 62.00 . 25
62.500
2 1 - - - 45
_

63.000 63.00 22
63.500
4 1 1 - - 92
_

64.000 64.00 15
Very
64.500 Very blocky/
11 2 - - - blocky/ 66 NIL
_

Disturbed
65.000 65.00 Disturbed 15
Over 15

Very
65.500 Very blocky/
6 3 - - - blocky/ 90 NIL
_

Disturbed
66.000 66.00 Disturbed 15
Very
66.500 Very blocky/
10 2 - - - blocky/ 90 26 15-8
_

Disturbed
67.000 67.00 Disturbed 17
Milky white Very
67.500 Very blocky/
colored, very 9 1 - - - blocky/ 90 18
_

Disturbed
Complete

68.000 68.00 Disturbed 15


blocky , slightly Very
68.500 Very blocky/
weathered & - 2 - - - blocky/ 41 NIL
_

Disturbed
69.000 69.00 Disturbed 15
medium strong Very
69.500 Very blocky/
to strong 3 - - - - blocky/ 35 NIL
_

Over 15

Disturbed
70.000 70.00 Disturbed 17
QUARTZITE. Very
70.500 Very blocky/
4 - - - - blocky/ 35 NIL
_

Disturbed
71.000 71.00 Disturbed 15
Very
71.500 Very blocky/
3 1 - - - blocky/ 35 NIL
_

Disturbed
72.000 72.00 Disturbed 17
Very
NIL

72.500 Very blocky/


4 - - - - blocky/ 30 NIL
_

Disturbed
73.000 73.00 Disturbed 17

INDEX Core Recovery

Overburden Bed Rock Boundary

Quartzite

LOGGED BY : Javeed Ganaie CHECKED BY :

Page 53
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No: 01
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI
STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018

PENETRATION RATE
SIZE OF CORE PIECES WATER

SIZE OF HOLE (mm)


% OF CORE RECOVERY PERMEA

DEPTH OF WATER
in Nos LOSS

TYPE OF CASING
% OF RECOVERY
BILITY

TEST SECTION

cm/min
SPECIAL
ELEVATION

FREQUENCY
TYPE OF BIT

COMPLETE
75-150mm
DEPTH OF

PARTIAL

LUGEON
10-25mm

25-75mm

FRACTURE
>150mm
OBSERVATION

<10mm

% OF RQD
HOLE

NIL
DESCRIPTION LOG 20 40 60 80 100

LEVEL

NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL
1393.8 1.00 ── ── 2 ── ── 30 ── NA 100 HX ── ─ ─ ── ── 3.33
1392.8 2.00 ── ── 2 ── ── 30 ── NA 100 HX ── ─ ─ ── ── 2.50
1391.8 3.00 ── ── 6 ── ── 39 ── NA 100 HX ── ─ ─ ── ── 2.00
1390.8 4.00 Overburden consists of ── ── 2 ── ── 22 ── NA 100 HX ── ─ ─ ── ── 2.50
boulders, cobbles and pebbles

DIAMOND BIT
1389.8 5.00 ── 1 2 ── ── 35 ── NA 100 HX ── ─ ─ ── ── 2.22
of Phyllite, Mica Schist and
1388.8 6.00 Gneiss. ── ── 4 ── ── 40 ── NA 100 HX ── ─ ─ ── ── 2.50
1387.8 7.00 ── ── 5 4 ── 66 12 NA 100 HX ── ─ ─ ── ── 2.00
1386.8 8.00 ── ── 4 ── ── 37 ── NA 100 HX ── ─ ─ ── ── 2.22
1385.8 9.00 ── ── 4 1 ── 34 ── NA 100 HX ── ─ ─ ── ── 2.50
1384.8 10.00 ── ── 5 1 ── 41 ── NA 100 HX ── ─ ─ ── ── 2.00
1383.8 11.00 ── ── 3 ── ── 28 ── NA 100 HX ── ─ ─ ── ── 2.50
1382.8 12.00 ── ── 2 ── ── 32 ── NA 100 HX ── ─ ─ ── ── 2.00
Overburden consists of
1381.8 13.00 boulders, cobbles and ── ── 4 ── ── 40 ── NA 100 HX ── ─ ─ ── ── 2.50
1380.8 14.00 pebbles of Phyllite, Mica ── ── 4 ── ── 64 ── NA 76 NX ── ─ ─ ── ── 2.50
1379.8 15.00 Schist and Gneiss. ── ── 2 ── ── 51 ── NA 76 NX ── ─ ─ ── ── 2.00
1378.8 16.00 ── ── 2 ── ── 30 ── NA 76 NX ── ─ ─ ── ── 2.50

DIAMOND BIT
1377.8 17.00 ── ── 6 2 ── 66 12 NA 76 NX ── ─ ─ ── ── 2.22
1376.8 18.00 ── ── 2 ── ── 27 ── NA 76 NX ── ─ ─ ── ── 2.50
1375.8 19.00 ── ── 3 2 ── 45 ── NA 76 NX ── ─ ─ ── ── 2.22
1374.8 20.00 Overburden consists of ── ── 2 ── ── 46 ── NA 76 NX ── ─ ─ ── ── 2.00
1373.8 21.00
boulders, cobbles and ── ── 1 ── ── 41 ── NA 76 NX ── ─ ── ── ── 1.67
pebbles of Phyllite, Mica
1372.8 22.00 ── ── ── 1 1 35 15 NA 76 NX ── ─ ── ── ── 1.82
Schist and Gneiss.
1371.8 23.00 ── ── ── 3 ── 34 ── NA 76 NX ── ─ ── ── ── 1.67
1370.8 24.00 ── ── 1 1 ── 41 14 NA 76 NX ── ─ ── ── ── 2.00

Page 54
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05

SHEET No:
02
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI
STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018

SIZE OF HOLE (mm)


SIZE OF CORE PIECES WATER PERMEA

DEPTH OF WATER
% OF CORE RECOVERY

TYPE OF CASING
% OF RECOVERY

PENETRATION
in Nos LOSS

RATE cm/min
BILITY

TEST SECTION
ELEVATION

FREQUENCY
TYPE OF BIT

COMPLETE
SPECIAL

75-150mm
DEPTH OF

PARTIAL

LUGEON
10-25mm

25-75mm

FRACTURE
>150mm
<10mm

% OF RQD
HOLE

OBSERVATION

NIL
DESCRIPTION LOG 20 40 60 80 100

LEVEL

NIL NIL
1369.8 25.00 ── ── 1 ── ── 32 ── NA 76 NX ── ─ ─ ── ── 2.00
1368.8 26.00 ── ── 1 ── 1 33 19 NA 76 NX ── ─ ─ ── ── 2.00
1367.8 27.00 Overburden consists of ── ── 7 ── ── 55 ── NA 76 NX ── ─ P ─ ── ── 2.00
1366.8 28.00 boulders, cobbles and ── 1 ── 1 ── 40 ── NA 76 NX ── ─ P ─ ── ── 2.50
1365.8 29.00 pebbles of Phyllite, Mica ── ── 2 ── ── 56 ── NA 76 NX ── ─ P ─ ── ── 2.00

DIAMOND BIT
Schist and Gneiss.
1364.8 30.00 ── ── 2 3 ── 56 ── NA 76 NX ── ─ P ─ ── ── 1.67
1363.8 31.00 ── ── 4 ── ── 60 ── NA 76 NX ── ─ P ─ ── ── 2.00
1362.8 32.00 ── ── 3 2 ── 55 23 NA 76 NX ── ─ P ─ ── ── 1.67
1361.8 33.00 ── ── 2 2 2 95 68 NA 76 NX ── ─ P ─ ── ── 1.67
1360.8 34.00 ── ── 2 3 1 85 40 NA 76 NX ── ─ P ─ ── ── 1.67
1359.8 35.00 Overburden consists of ── ── ── ── 2 93 93 NA 76 NX ── ─ P ─ ── ── 1.53
boulders, cobbles and
1358.8 36.00 ── ── 1 2 2 100 72 NA 76 NX ── ─ P ─ ── ── 1.82
pebbles of Phyllite, Mica
1357.8 37.00 Schist and Gneiss. ── ── ── ── 2 84 84 NA 76 NX ─ P ─ ── ── 1.53
1356.8 38.00 ── ── 5 2 1 88 ── NA 76 NX ─ P ─ ── ── 1.67
1355.8 39.00 ── ── 1 2 2 60 41 NA 76 NX ─ P ─ ── ── 1.82
1354.8 40.00 ── ── 6 3 ── 63 ── NA 76 NX ─ P ─ ── ── 2.00
1353.8 41.00 ── ── 4 ── ── 27 ── NA 76 NX ─ P ─ ── ── 2.50

DIAMOND BIT
1352.8 42.00 ── ── 2 1 ── 30 ── NA 76 NX ─ P ─ ── ── 2.50
1351.8 43.00 Overburden consists of ── ── 4 ── ── 30 ── NA 76 NX ─ P ─ ── ── 2.00
boulders, cobbles and
1350.8 44.00 ── ── 1 3 ── 52 10 NA 76 NX ─ P ─ ── ── 2.00
pebbles of Phyllite, Mica
1349.8 45.00 Schist and Gneiss. ── ── 3 1 ── 37 ── NA 76 NX ── P ─ ── ── 1.82
1348.8 46.00 ── ── 3 ── ── 22 ── NA 76 NX ── P ─ ── ── 2.50
1347.8 47.00 ── ── ── 1 2 62 50 NA 76 NX ── P ─ ── ── 1.67
1346.8 48.00 ── ── 1 1 1 38 19 NA 76 NX ── P ─ ── ── 2.00

Page 55
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No: 03
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m

FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE

CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI

STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018


SIZE OF CORE PIECES WATER PERMEA

PENETRATION RATE
% OF CORE RECOVERY
in Nos LOSS BILITY

SIZE OF HOLE (mm)

DEPTH OF WATER
DEPTH OF HOLE

TYPE OF CASING
% OF RECOVERY

TEST SECTION

cm/min
ELEVATION

COMPLETE
75-150mm
SPECIAL

PARTIAL

LUGEON
10-25mm

25-75mm

>150mm

FREQUENCY
TYPE OF BIT
<10mm
OBSERVATION

FRACTURE

NIL
% OF RQD
DESCRIPTION LOG 20 40 60 80 100

LEVEL
1345.8 49.00 ── ── 1 ── ── 20 ── NA 76 NX ─ P ─ ── ── 2.00
1344.8 50.00 ── ── ── 1 1 63 63 NA 76 NX ─ P ─ ── ── 2.00
Overburden consists of
1343.8 51.00 boulders, cobbles and ── ── 1 ── 1 30 20 NA 76 NX ─ P ─ ── ── 1.67

DIAMOND BIT
1342.8 52.00 pebbles of Phyllite, Mica ── ── 2 ── ── 27 ── NA 76 NX ─ P ─ ── ── 1.40
1341.8 53.00 Schist and Gneiss. ── ── 2 ── ── 24 ── NA 76 NX ─ P ─ ── ── 1.67
1340.8 54.00 ── ── ── 1 1 40 35 NA 76 NX ─ P ─ ── ── 1.67
1339.8 55.00 ── ── ── ── 2 45 35 NA 76 NX ─ P ─ ── ── 1.42
1338.8 56.00 ── ── 1 ── 1 50 19 NA 76 ─ ─ P ─ ── ── 1.53
1337.8 57.00 Overburden consists of ── ── ── ── ── Wash Sample NIL ── NA 76 ─ ─ P ─ ── ── 1.67
boulders, cobbles and
1336.8 58.00 ── ── ── ── ── Wash Sample NIL ── NA 76 ─ ─ P ─ ── ── 1.67
pebbles of Phyllite, Mica
1335.8 59.00 Schist and Gneiss. ── ── 1 1 ── 40 ── NA 76 ─ ─ P ─ ── ── 1.82
1334.8 60.00 ── ── 1 1 ── 45 ── NA 76 ─ ─ P ─ ── ── 1.67
1333.8 61.00 ── ── 3 ── ── 40 ── NA 76 ─ ─ P ─ ── ── 1.42
1332.8 62.00 ── ── 3 1 ── 40 ── NA 76 ─ ─ P ─ ── ── 1.53

DIAMOND BIT
1331.8 63.00 ── ── 3 ── ── 30 ── NA 76 ─ ─ P ─ ── ── 1.67
1330.8 64.00 ── ── 3 ── ── 30 ── NA 76 ─ ─ P ─ ── ── 1.53
Overburden consists of
1329.8 65.00 boulders, cobbles and ── ── 3 ── ── 35 ── NA 76 ─ ─ P ─ ── ── 2.00
1328.8 66.00 pebbles of Phyllite, Mica ── ── 3 ── ── 30 ── NA 76 ─ ─ P ─ ── ── 1.82
1327.8 67.00 Schist and Gneiss. ── ── 3 1 ── 46 ── NA 76 ─ ─ P ─ ── ── 1.67
1326.8 68.00 ── ── 3 ── ── 40 ── NA 76 ─ ─ P ─ ── ── 2.00
1325.8 69.00 ── ── 2 ── ── 30 ── NA 76 ─ ── P ─ ── ── 1.67
1324.8 70.00 Bedrock Phyllite ── ── ── ── 1 44 32 >15 76 ─ ── P ─ ── ── 2.00

Page 56
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No: 04
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI
STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018

SIZE OF HOLE (mm)


SIZE OF CORE PIECES WATER PERMEA

DEPTH OF WATER
% OF CORE RECOVERY

TYPE OF CASING
% OF RECOVERY

PENETRATION
RATE cm/min
in Nos LOSS BILITY

TEST SECTION
FREQUENCY
ELEVATION

TYPE OF BIT

COMPLETE
SPECIAL

75-150mm
DEPTH OF

PARTIAL
FRACTURE

LUGEON
10-25mm

25-75mm

>150mm
<10mm

% OF RQD
HOLE

OBSERVATION

NIL
DESCRIPTION LOG 20 40 60 80 100

LEVEL
1323.8 71.00 ── ── 3 1 ── 40 ── >15 76 ── ── P ── ── ── 1.67
1322.8 72.00 ── ── 3 1 1 55 17 >15 76 ── ── P ── ── ── 2.00

DIAMOND BIT
1321.8 73.00 Gray coloured, fine to ── ── 4 1 ── 51 ── >15 76 ── ── P ── ── ── 1.67
1320.8 74.00
medium grained, slightly ── ── 5 1 ── 45 ── >15 76 ── ── P ── ── ── 1.42
to moderately weathered,
1319.8 75.00 ── ── 3 1 ── 60 ── >15 76 ── ── P ── ── ── 1.67
foliated Phyllite. Thin
1318.8 76.00 quartz veins are present. ── ── 5 1 ── 66 ── >15 76 ── ── P ── ── ── 1.53
1317.8 77.00 ── ── 4 1 ── 60 10 >15 76 ── ── P ── ── ── 1.42
1316.8 78.00 ── ── 3 3 ── 55 ── >15 76 ── ── P ── ── ── 1.53

Index:
NA= Not Applicable, Overburden=
P= Partial,
C= Complete, Phyllite=

Page 57
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P6
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE BR-3 (P6)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 63.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARREL Triple Tube
STARTED : 04.04.2018 COMPLETED 04.05.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
Dry sample contains
angular pebbles of 25
1.000 1.00 Phyllite/Phyllitic Quartzite. - - - - -

35 22
2.000 2.00 5 - - - -

PX
PX
30 20
3.000 3.00 5 - - - -

30 18
4.000 4.00 3 - - - -

30 17
5.000 5.00 Semi angular to 3 - - - -

5
semi rounded 35 15
6.000 6.00 pebbles, cobbles & 6 - - - -
Boulders of
38 17
7.000 7.00
Gneiss, Phyllitic 6 - - - -
Quartzite.
38 20
8.000 8.00 2 - - - -

40 18
9.000 9.00 4 - - - -

50 20
10.000 10.00 4 - - - -

33 17
11.000 11.00 4 - - - -

HX
HX
50 18
12.000 12.00 5 - - - -

38 20
13.000 13.00 1 1 - - -

40 17
14.000 14.00 3 1 - - -

50 22
15.000 15.00 3 1 - - -

41 20
16.000 16.00 - 2 - - -
Semi angular to
semi rounded 42 20
17.000 17.00 2 - - -
IMP (NX Size ) Diamond Core Bit

pebbles, cobbles &


Fluvio-glacial deposit(Alluvium)

Fluvio-glacial deposit(Alluvium)

Boulders of
55 17
18.000 18.00 Slate/Phyllite 6 - - -
Not Applicable

Gneiss, Phyllitic
Core Samples
Overburden

Complete

Quartzite & 29 22
19.000 19.00 1 - - -
Quartzite.
32 22
20.000 20.00 - - - -

32 20
21.000 21.00 - 1 - - -

78 20
22.000 22.00 1 2 - - -

100 17
23.000 23.00 - 4 1 - -

82 18
24.000 24.00 3 2 - -

71 15
25.000 25.00 1 1 - -

Semi angular to 60 18
26.000 26.00 2 - - - -
semi rounded
pebbles, cobbles & 46 22
27.000 27.00 Boulders of Gneiss 2 1 - - -
& Phyllitic
NX
NX

50 17
28.000 28.00 interbedded stiff 1 3 - - -
brownish to reddish
clay contains 60 17
29.000 29.00 1 2 - - -
angular pebbles of
Phyllite. 35 15
30.000 30.00 1 - - - -

43 22
31.000 31.00 4 - - - -
Pebbles of Phyllite in silty
sandy matrix.
47 20
32.000 32.00 2 - - - -

46 20
33.000 33.00 3 2 - -
Semi angular to
semi rounded 43 22
34.000 34.00 pebbles, cobbles & 2 - - - -
Boulders of
72 20
35.000 35.00 Slate/Phyllite 5 1 - -
Gneiss, Phyllitic
Quartzite & 98 18
36.000 36.00 2 5 - -
Quartzite.
78 20
37.000 37.00 2 3 - -
Semi angular to semi
rounded Boulders of 85 22
38.000 38.00 Phyllitic Quartzite . 10 1

LOGGED BY : CHECKED BY :

Page 58
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P6
SHEET NO.:
2 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE BR-3 (P6)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 63.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARRELTriple Tube
STARTED : 04.04.2018 COMPLETED 04.05.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Fracture Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
Semi angular to semi
rounded Boulders of 56
39.000 39.00 Phyllitic Quartzite. 11 20

Semi angular to semi 55


40.000 40.00 rounded pebbles, 1 1 17
cobbles & Boulders of
70
41.000 41.00 Gneiss, Phyllitic 3 2 20
Quartzite & fine
Fluvio-glacial deposit(Alluvium)

Fluvio-glacial deposit(Alluvium)
sandy matrix. 70
42.000 42.00 3 2 17

70

Not Applicable
Overburden
43.000 43.00 2 3 20

68
44.000 44.00 5 1 18
Semi angular to
semi rounded 67
45.000 45.00 3 1 17
pebbles, cobbles

NX
& Boulders of 57
46.000 46.00 1 1 15
Gneiss/Schist,
Phyllitic Quartzite 75
47.000 47.00 7 17
& Quartzite.
60
48.000 48.00 2 1 15
IMP (NX Size ) Diamond Core Bit

81
49.000 49.00 2 3 20

Blocky Blocky 96 11
Over 15

Core Samples.
50.000 50.00 1 4 17

Complete
Joint Plane
NX
0
45 (1) Sm/Pl 81 NIL
51.000 51.00 2 4 & stains 19

Blocky Blocky 93 30
15-8

52.000 52.00 5 14

Blocky Blocky 86 29
53.000 53.00 2 3 1 14
8-5

Blocky Blocky 92 59
54.000 54.00 Dark colored, 3 1 15
blocky slightly
15-8

Blocky Blocky 90 44
55.000 55.00 weathered & 3 1 15
medium strong
Over
15

Blocky Blocky 100 12


56.000 56.00 to weak 2 7 17
Joint Plane
PHYLLITE
15-8

0
25 (1) Rg/Unl 98 40
57.000 57.00 contain quartz 4 1 & stains 15
veins along
8-5

Blocky Blocky 100 67


foliation as well
NIL

58.000 58.00 2 3 1 17
as randomly.
Over
15

Blocky Blocky 100 15


59.000 59.00 1 5 15
Joint Plane
8-5

0
45 (1) Sm/Pl 100 60
60.000 60.00 2 4 1 & stains 15
15-8

Blocky Blocky 100 45


61.000 61.00 3 3 1 15
Over

Blocky/sheare Blocky/sh
15

d eared
100 16
62.000 62.00 2 5 15
15-8

Blocky Blocky 100 28


63.000 63.00 7 3 15

NB: Pl-Planer ,Sm-Smooth,Un-Undulating,Rg-Rough,St-Stepped,Sl-Silica Filling,Cl-Clay,Py-Pyrite and Fr-Fractured.

INDEX Core Recovery

Overburden Bed Rock Boundary

Phyllite

LOGGED BY : CHECKED BY :

Page 59
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO. P7
SHEET NO.: 1of 2
PROJECT : USBRL Project CHAINAGE:- 111+440.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511174.039E, 3684896.849N FEATURE P7(Br-3)
COLLAR ELEVATION (m) 1402.201 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 61.00
GROUND ELEVATION(m) 1402.101 TYPE(S) OF CORE BARREL Triple Tube
STARTED : 06.04.2018 COMPLETED 26.04.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Size of core Structural Drill Water SPT-Number of
Lithology Ratio Percent Core Recovery (%) Loss Permeability
pieces In No's) Condition Blows

Fracture Frequency / m

Depth of water level(m)


Ground Elevation (m)

Interpreted %age of
Special

Interpreted %age of

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

rock fragments

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
10 to 25 mm interpretations /
25 to 75 mm

Test section
0.00 - 19.99

Size of hole

mm/s OR
Depth (m)

Description

Description

Type of Bit
matrix (fine)
Weathering Grade

LUGEON
(mm/min)
Complete
>150 mm

In figures
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
30 20
1.000 1.00

PX
Sub rounded to
sub angular 35 17
2.000 2.00
pebbles, cobbles
& boulders of 35 17
3.000 3.00 Slate.

3.00
35 15
4.000 4.00

65 18
5.000 5.00
Sub rounded to
sub angular 75 17

Partial
6.000 6.00
pebbles, cobbles
& boulders of 55 17
7.000 7.00 Slate, Quartzite,
Gneiss & 52 15
8.000 8.00 Migmatite.

HX
30 17
9.000 9.00

32 20
10.000 10.00

67 18
11.000 11.00

42 17
12.000 12.00
Sub rounded to 57 17
Fluvio-glacial deposit(Alluvium)

Fluvio-glacial deposit(Alluvium)

13.000 13.00 sub angular


boulders of
72 18
14.000 14.00 Slate, Quartzite,
Not Applicable

Gneiss &
Overburden

Migmatite. 65 Complete 15
15.000 15.00

57 18
16.000 16.00

70 17
17.000 17.00
IMP (Nx size) Diamond Core Bit

40 17
18.000 18.00
Core Samples

69 15
19.000 19.00

77 15
20.000 20.00
Sub rounded to
sub angular 51 20
21.000 21.00
pebbles, cobbles
& boulders of 67 17
22.000 22.00 Gneiss ,Slate
/Phyllite& 67 18
23.000 23.00 Quartzite
53 20
24.000 24.00

54 17
25.000 25.00

60 20
26.000 26.00
NX

Sub rounded to 73 17
27.000 27.00 sub angular
pebbles, cobbles
74 15
28.000 28.00 & boulders of
Partial

Gneiss ,Slate &


Quartzite 52 17
29.000 29.00

76 17
30.000 30.00

Blocky Blocky 97 26 15
31.000 31.00
15-8

Blocky Blocky 79 28 17
32.000 32.00
Greyish colored,
Blocky Blocky 84 33 15
33.000 33.00
blocky, slightly
weathered &
Over
15

medium strong Blocky Blocky 98 13 15


34.000 34.00
fine grained
PHYLLITIC Blocky Blocky 90 30 16
15-8

35.000 35.00 QUARTZITE


contains random Blocky Blocky 100 38 15
36.000 36.00 Quartz veins.
Blocky Blocky 92 14 15
Over 15

37.000 37.00

Blocky Blocky 100 16 15


38.000 38.00

LOGGED BY : Javeed Ganaie CHECKED BY :

Page 60
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO. P7
SHEET NO.: 2 of 2
PROJECT : USBRL Project CHAINAGE:- 111+440.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511174.039E, 3684896.849N FEATURE P7(Br-3)
COLLAR ELEVATION (m) 1402.201 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 61.00
GROUND ELEVATION(m) 1402.101 TYPE(S) OF CORE BARREL Triple Tube
STARTED : 06.04.2018 COMPLETED 26.04.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Size of core Structural Drill Water SPT-Number of
Lithology Ratio Percent Core Recovery (%) Loss Permeability
pieces In No's) Condition Blows

Fracture Frequency / m

Depth of water level(m)


Ground Elevation (m)

Interpreted %age of
Special

Interpreted %age of

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

rock fragments

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
interpretations /
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole

mm/s OR
Depth (m)

Description

Description

Type of Bit
matrix (fine)
Weathering Grade

LUGEON
(mm/min)
Complete
>150 mm

In figures
< 10 mm

RQD(%)

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
Greyish colored, Blocky Blocky 100 17 15
39.000 39.00
PHYLLITIC
QUARTZITE. Blocky Blocky 100 NIL 17
40.000 40.00

Over 15
Very Very
blocky/ blocky/ 95 NIL 18
41.000 41.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 76 NIL 17
42.000 42.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 73 NIL 18
43.000 43.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 86 28 17

15-8
44.000 44.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 70 27 20
45.000 45.00 Greyish colored, Disturbed Disturbe
very blocky, Very Very
blocky/ blocky/ 73 NIL 17
46.000 46.00
slightly Disturbed Disturbe
weathered to Very Very
moderately & blocky/ blocky/ 64 NIL 20
47.000 47.00 Disturbed Disturbe
medium strong Very Very
fine grained
IMP (Nx size) Diamond Core Bit
blocky/ blocky/ 32 NIL 18
48.000 48.00 PHYLLITIC Disturbed Disturbe
Very Very
QUARTZITE blocky/ blocky/ 43 NIL 20

Core Samples
49.000 49.00 contains random Disturbed Disturbe

Complete
Very Very
Quartz veins.

NIL
NX
Over 15
blocky/ blocky/ 77 25 17
50.000 50.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 83 NIL 17
51.000 51.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 80 NIL 15
52.000 52.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 96 NIL 15
53.000 53.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 92 NIL 15
54.000 54.00 Disturbed Disturbe

Blocky - Blocky - 81 10 15
55.000 55.00 massive massive

Greyish colored, Blocky - Blocky - 95 32 15


56.000 56.00 blocky to massive massive
massive, slightly Blocky - Blocky - 96 35 15
57.000 57.00 weathered & massive massive
medium strong Blocky - Blocky - 96 48 15
fine grained
15-8

58.000 58.00 massive massive


PHYLLITIC
Blocky - Blocky - 95 29 15
59.000 59.00
QUARTZITE massive massive
contains random
Quartz veins. Blocky - Blocky - 91 32 17
60.000 60.00 massive massive Page 48
Blocky - Blocky - 96 26 15
61.000 61.00 massive massive

NB: Pl-Planer ,Sm-Smooth,Un-Undulating,Rg-Rough,St-Stepped,Sl-Silica Filling,Cl-Clay,Py-Pyrite and Fr-Fractured.

INDEX Core Recovery

Overburden Bed Rock Boundary

Phyllitic Quartzite

LOGGED BY : Javeed Ganaie CHECKED BY :

Page 61
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
A2
SHEET NO.:
1 of 1
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE Br-3(A2)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 27.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARREL Triple Tube
STARTED : 27.04.2018 COMPLETED 01.05.2018 DRILLING AGENCY : SECL Srinagar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Lithology Size of core Ratio Structural Percent Core Recovery (%)


Drill Water SPT-Number of Permeability

Frequency / m

Depth of water level(m)


Loss
pieces (In No's) Condition Blows
Ground Elevation (m)

Interpreted %age of
Interpreted %age of
Special

Penetration Rate
Observations and

80.00 - 100.00
75 to 150 mm

20.00 - 39.99

40.00 - 59.99

60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm

Test section
0.00 - 19.99

Size of hole
interpretations /

mm/s OR
Description
Depth (m)

Description

Type of Bit
matrix (fine)

LUGEON
Complete

(mm/min)
>150 mm

In figures
Weathering Grade
< 10 mm

RQD(%)

Not Applicable Fracture

N-Value
Casing

Partial

15-30
30-45
0-15
Log

Log
Slope Debris

Slope Debris

Overburden
33
1.000 1.00 Angular pebbles & 1 - - - - 22
cobbles of Phyllite..

HX
HX
30
2.000 2.00 3 - - - - 22
Very blocky Very blocky
/disturbed /disturbed
46 NIL
3.000 3.00 6 - - - - 20
Very blocky Very blocky
/disturbed /disturbed
44 NIL
4.000 4.00 5 - - - - 20
Very blocky Very blocky
48 14

Over 15
/disturbed /disturbed
5.000 5.00 4 1 - - - 18
Very blocky Very blocky
/disturbed /disturbed
47 10
6.000 6.00 4 1 - - - 20
Very blocky Very blocky
Dark grey colored, /disturbed /disturbed
52 NIL
7.000 7.00 very blocky slightly 5 1 - - - 18

7
weathered & weak Very blocky Very blocky
/disturbed /disturbed
50 NIL
8.000 8.00 PHYLLITE contains 5 - - - - 17
occasional quartz Joint Plane 45-

15-8
0
veins.. 50 (2) Sm/Pl & 56 27
9.000 9.00 3 2 - - - yellow stains 17
Very blocky Very blocky
/disturbed /disturbed
52 11
10.000 10.00 3 1 - - - 17
Very blocky Very blocky
61 NIL

Over 15
/disturbed /disturbed
11.000 11.00 5 - - - - 15
IMP (NX Size) Diamond Core Bit.

Very blocky Very blocky


/disturbed /disturbed
64 12
12.000 12.00 8 1 - - - 17
Very blocky Very blocky
60 NIL

Core Samples
/disturbed /disturbed
13.000 13.00 9 - - - - 17

Partial
Joint Plane
0 0
45 (1) & 35 (1) 94 50
Sm/Pl,Rg/Un &
15-8

14.000 14.00 2 3 1 - - 15
yellow stains
Joint Plane
Uncased

0 0
70 (1) & 40 (1) 95 42
15.000 15.00 6 2 1 - - Sm/Pl,Sm/Un & 15
NX
15-8 Over 15

stains
Joint Plane
0
50 (1) Sm/Un & 95 11
16.000 16.00 11 2 - - - stains 17

Blocky Blocky 95 29
17.000 17.00 9 3 - - - 15
Joint Plane
<1

0
35 (1) Rg/Un & 92 92
18.000 18.00 - 4 - - - stains 15

Blocky Blocky 92 22
19.000 19.00 Dark grey colored, 9 2 - - - 17
blocky to very Joint Plane
0
95 14
Over 15

45 (1) Sm/Un &


blocky slightly
20.000 20.00 8 2 - - - stains 18
weathered & weak Joint Plane
PHYLLITE contains 0
30 (1) Sm/Un & 95 14
21.000 21.00 random quartz 7 3 - - - stains 15
Joint Plane
veins. 0
80 (1) Rg/Un & 95 10
22.000 22.00 5 4 - - - stains 15

Blocky Blocky 92 27
15-8

23.000 23.00 3 7 - - - 15

Blocky Blocky 95 26
24.000 24.00 4 5 - - - 15
Over 15

Blocky Blocky 90 NIL


25.000 25.00 12 - - - - 15
Joint Plane
8-5

0
45 (1) Rg/Un & 100 60
26.000 26.00 3 3 43 - - stains 15
<1

Blocky Blocky 100 100


27.000 27.00 - 5 - - - 17

NB: Pl-Planer ,Sm-Smooth,Un-Undulating,Rg-Rough,St-Stepped,Sl-Silica Filling,Cl-Clay,Py-Pyrite and Fr-Fractured.

INDEX Core Recovery

Overburden Bed Rock Boundary

Phyllite

LOGGED BY : CHECKED BY :

Page 62
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Photographs of Core boxes

BH No P1

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 01 (One)
Depth : 0.00 m o 17.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 03 (Two)
Depth : 17.0m to 27.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 63
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 03 (Three)
Depth : 27.0m to 35.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 04 (Four)
Depth : 35.0 m to 43.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 64
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P2

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 01 (One)
Depth : 0.00 m to 18.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 02 (Two)
Depth : 18.0m to 27.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 65
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 03 (Three)
Depth : 28.0 m to 32.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 04 (Four)
Depth : 33.0m to 37.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 66
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Project : USBRL Annexure-II
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 05 (Five)
Depth : 38.0m to 40.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 67
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

BH No P3
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 01 (One)
Depth : 0.0m to 11.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 02 (Two)
Depth : 11.0m to 21.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 68
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 03 (Three)
Depth : 21.0 m to 32.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 04 (Four)
Depth : 32.0m to 44.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 69
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 05 (Five)
Depth : 44.0m to 57.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 06 (Six)
Depth : 57.0m to 65.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 70
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 07 (Seven)
Depth : 65.0m to 73.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 71
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P5

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 01 (One)
Depth : 0.00m to 16.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 02 (Two)
Depth : 16.0m to 26.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 72
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 03 (Three)
Depth : 26.0 m to 34.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 04 (Four)
Depth : 34.0m to 42.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 73
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 05 (Five)
Depth : 42.0m to 54.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 06 (Six)
Depth : 54.0m to 70.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 74
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 07 (Seven)
Depth : 70.0m to 78.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 75
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P6

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 01 (One)
Depth : 0.0m to 12.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 02 (two)
Depth : 12.0m to 22.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 76
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 03 (Three)
Depth : 22.0m to 30.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 04 (Four)
Depth : 31.0m to 38.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 77
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 05 (Five)
Depth : 38.0m to 46.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 06 (Six)
Depth : 47.0m to 52.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 78
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 06 (Six)
Depth : 53.0m to 57.0 m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 07 (Seven)
Depth : 58.0m to 63.0 m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 79
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P7

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 01 (One)
Depth : 0.00m to 10.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 02 (Two)
Depth : 10.0m to 18.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 80
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 03 (Three)
Depth : 18.0m to 25.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 04 (Four)
Depth : 26.0m to 32.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 81
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 05 (Five)
Depth : 33.0m to 37.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 06 (Six)
Depth : 38.0m to 43.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 82
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 07 (Seven)
Depth : 44.0m to 52.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 08 (Eight)
Depth : 53.0m to 61.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 83
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No A2

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 01 (One)
Depth : 00.0m to 11.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 02 (Two)
Depth : 11.0m to 17.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 84
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 04 (Four)
Depth : 24.0m to 27.0m

Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 03 (Three)
Depth : 17.0m to 23.0m

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 85
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-III

Sample Calculation
For well dia 8m
For permissible settlement of 25mm and Bf=8m and Bp=1.2m
Sp/Sf=(Bp(Bf+0.3)/Bf(Bp+0.3))2
Sp=(1.2(8+0.3)/8(1.2+0.3))2 x 25

Sp=17.22mm

Corresponding to settlement of 17.22mm ,a stress of 4.2kg/cm2 is obtained from IS 10042-


1981 Fig 2 . So the qa for 25mm permissible settlement is 42t/m2 .

Teng modified equation for 25mm permissible settlement

qa=3.35xCb(N-3)((B+0.3)/2B)2dwdf

dw=0.5+0.5wB/D

w= depth of water table below footing


df=1+Df/B<2
For 20m deep foundation df=1.33
Cb for gravely soil=2
qa=3.35x2x(50-3)(8+0.3/2x8)2x0.5x1.33
qa=56.35t/m2

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2, P3,P5
TO
P6, ,P7and Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 86
USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-III

Sample Calculation
For well dia 10m
For permissible settlement of 25mm and Bf=10m and Bp=1.2m
Sp/Sf=(Bp(Bf+0.3)/Bf(Bp+0.3))2
Sp=(1.2(10+0.3)/10(1.2+0.3))2 x 25
Sp=16.97mm
Corresponding to settlement of 16.97mm ,a stress of 4.1kg/cm2 is obtained from IS 10042-
1981 Fig 2 . So the qa for 25mm permissible settlement is 41t/m2 .

Teng modified equation for 25mm permissible settlement

qa=3.35xCb(N-3)((B+0.3)/2B)2dwdf

dw=0.5+0.5wB/D
w= depth of water table below footing
df=1+Df/B<2
For 20m deep foundation df=1.33
Cb for gravely soil=2
qa=3.35x2x(50-3)(10+0.3/2x10)2x0.5x1.33
qa=55.54t/m2

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2, P3,P5
TO
P6, ,P7and Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 87
USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-III
For Rocky strata (BH 5)

i) UCS Criteria
Safe bearing pressure
qs= qcNj
Where
qs= safe bearing pressure (gross)
qc = average uniaxial compressive strength of rock cores,
Nj= empirical coefficient depending on the spacing of discontinuities

3 + S/B1
10 √(1+300 δ/S

δ= thickness of discontinuities in cm,


S = spacing of discontinuities in cm, and
B1= footing width in cm.
In present case
Nj=0.10
qc = 275.31kg/cm2
qs(gross)= 275.31x0.10 = 27.53kg/cm2
Correction due to submergence=0.75
qs(gross)= = 27.64x 0.75 kg/cm2 =20.64kg/cm2
= 206.4 t/m2

ii) RMR Criteria

Table 3 Net Safe Bearing pressures and Based on RMR

Classification No I II III IV V

Description of work Very good Good Fair Poor Very poor

RMR 100-81 80-61 60-41 40-21 20-0

qns(t/m2) 600-448 440-288 280-151 145-90-58 55-45-40

IS – 12070-1987
In instant case
RMR have been taken as 33
Safe bearing pressure = qns= 112.94 t/m2 (say 112t/m2)

SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2, P3,P5
TO
P6, ,P7and Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 88
USBRL Project Jammu And Kashmir
HCC Limited

S-ar putea să vă placă și