Documente Academic
Documente Profesional
Documente Cultură
of
Dharam-Qazigund Section
of
Forwarded to
HCC Limited
Forwarded to:
Page
Chapter
Description No
No
1.0 Introduction 01
Geotechnical Investigation Report of Piers P1, P2,P3 ,P5,P6 ,P7 and Abutment A2 of
Bridge No.3 Of Dharam-Qazigund Section Of USBRL Project
Jammu And Kashmir
1.0 Introduction.
The Hindustan Constructional Company Limited (hereinafter referred to as the HCC) has been
Entrusted with the construction of the proposed bridge No.3 across Dassa Nallah respectively
by M/S IRCON International Limited (hereinafter referred to as the IRCON) along Dharam-
Qazigund Section of USBRL Project, J&K (under package 2, 3, 4&5). M/S HCC have taken
the services of Space Engineers Consortium Pvt Ltd. for carrying out Geotechnical
Investigation for this proposed bridge site under Work order No HCC ENG 106 B 02 007
Dated 29th January 2018.The Investigation of 07 bore holes located at piers P1, P2, P3, P5,P6,
P7 and A2 of bridge No.3 have been completed during January 2018- May 2018.This report
includes results of geological logs of boreholes, Standard Penetration Test (SPT) besides
geological studies around the tunnel T-49 alignment area.
Brief details
The tunnel T-49 is part of the USBRL railway line project in Northern India, in the state of
Jammu & Kashmir. Its length is approx. 10 km. Its section is typical for an Indian mountain
railway line: single track main tunnel with parallel escape tunnel. Its gradient is approx. 1%.
After the initial part of civil design and 3 years of supervision, the Client assigned the
electromechanical design to Lombardi. With the experience gathered in the neighboring tunnel
T-48, the E&M standard can be respected for an homogeneous design. Its length and its
gradient, with the portals on two different sides of a local ridge, the requirements are for a
dedicated ventilation concept in case of current operation
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |1
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Item
Item Description Unit Qty.
No.
Mobilization
Mobilization of necessary equipment, drilling rigs,
tools and tackles, men and materials to the site and
all services and demobilization on completion of the Lump
1 1
work (Sufficient Hydraulic rigs in working condition sum
shall be mobilized to complete the Drilling within
specified time period)
Per Borehole
2 Shifting and setting of Drilling rig at Bore hole location 21
location
Drilling of Nx size (76mm diameter) boreholes in all
types of Soil and overburden strata / Soft Ground
3 Rm 216
without core recovery inclusive of driving of
casing up to the overburden depth
a NGL up to 20m Rm. 179
b Beyond 20m Rm 37
Drilling of Nx size (76mm diameter) boreholes in all
types of Soil and overburden strata / Soft Ground
4 Rm. 216
with core recovery and inclusive of driving of
casing up to the overburden
b Beyond 20m Rm 36
c Conducting Permeability test Falling head method Nos. 25
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |2
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
8 Report Preparation
Preparation and submission of 03 copies of
Lump
a Geotechnical Investigation Report. Combined report 1
sum
for Bridge No. 2 and Bridge No. 3.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |3
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
3.1 The proposed Bridge No 3 across Dassa Nallah is located at Sumbar village along
Dharam-Qazigund Section of USBRL Project in Ramban District of Jammu province of
J&K State. The proposed Bridge No3 is approximately 326.4mtrs in length supported on
7 piers and 02 abutments each with a span of 40.8m .The Nallahs passes through the
mountainous terrains and the Bridges passes at an elevation of around 1416mtrs. Refer to
Plate-I for sectional view of the proposed Bridge No 3 site.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |4
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
The details of borehole locations marked on ground by the Engineer In-charge of HCC are
given in Plate-I and Table 1.
Location
Bore Depth of Collar
Bridge.
No
Hole Bore hole elevation(m) R.L(m)
No (m) Easting Northing
The investigation was planned to obtain the subsurface stratification in the proposed project
site and collect overburden / bed rock samples for laboratory testing to determine the
engineering properties besides engineering classification of the subsurface stratum.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |6
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
a) The drilling fluid used was clean water to avoid contamination. Circulation of drilling fluid
was used before the core barrel reached to the bottom of the hole to prevent cuttings or sludge
from entering the core barrel at the start of coring. In order to collect the sludge / rock cuttings,
drilling fluid were circulated continuously down the hollow rods.
c) The rotational speed of the bit (spindle speed), the amount of downward pressure applied on
the bit (bit pressure) and water pressure were suitably adjusted and properly monitored so that
the core is collected with least disturbance and to avoid shearing of the core from its base.
d) As per the drilling schedule the minimum drill run should be 0.75m and maximum. 1.5min
length provided the core recovery observed is more than 80% in two successive 0.75m drill
runs. When core recovery is less than 20% then SPT shall be per formed before commencing
the next drill run .This procedure was strictly adhered to on the approval from the site
engineer.
e) If at any time blocking of the bit or grinding of the core was observed, the core barrel was
immediately withdrawn from the drill hole regardless of the length of drill run completed.
a) During drilling operations, the colour of return water was regularly monitored and sediments
carried were keenly observed so as to determine change in the lithology and physical
properties of formations.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |7
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
b) The depth & rate of penetration was monitored to ascertain the depth at which marked change
in rate of penetration or sudden fall of drill rod occurred, the depth at which any blockage of
drill bit causing core loss if any was encountered.
c) Any heavy vibration or torque noticed during drilling was recorded together with the depth of
occurrence.
d) Special conditions like the depth at which grouting was done during drilling, presence of
artesian conditions, loss of drilling fluid, observation of gas discharge with return water etc
were also monitored
e) During drilling operation, observation on return water, rate of penetration etc shall be
recorded.
Standard Penetration Tests (SPT) prescribed as per IS specifications. SPT split spoon sampler
of standard dimensions is to be driven into the overburden from the drill hole bottom using
63.5 kg Hammer falling from 75 cm height. The SPT weight is mechanically lifted to the
specified height and allowed to fall freely on the anvil with the use of cat-head winch with one
to one and half turn of the drum. Blow counts for the penetration of every 15 cm are recorded
and the N is reported as the blow counts for 30 cm penetration of the sampler leaving the first
15 cm penetration as seating drive.
When the number of blows exceeded 50 to penetrate the first or second 15 cms length of the
sampler, the SPT N is regarded as more than 100. The test is terminated in such case and a
record of penetration of the sampler under 50 blows or more is made. SPT refusal is recorded
when there is no penetration of the sampler at any stage and also when a rebound of the
sounding system is recorded.
SPT ‘N’ values are correlated with relative density of non-cohesive stratum and with
consistency of cohesive stratum.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |8
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
[
Hard Above 32
Disturbed overburden samples collected in the SPT sampler are preserved in polythene covers
and transported to the laboratory. One more polythene cover is provided to prevent the loss of
moisture during the transit period.
Immediately after withdrawal from the core barrel, the cores samples were placed in a tray and
transferred into boxes specially prepared for the purpose. The core boxes were made from G I
sheet .The details of drill hole along with details of core run were recorded on core boxes.
After core logging the data was recorded for future use.
Bore hole logs are given in Annexure I and are summarized in table 4
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e |9
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
P1 29.0
P2 24.0
P3 25.0
P6 5.0
P7 3.0
A2 7.0
Rocks of Siwalik and Murree Group of foreland to Pre-Tertiary rocks of Lesser Himalaya are
exposed along the proposed rail alignment. These rocks are traversed by number of thrusts and
faults which are considered to be still active. Due to this tectonic activity the rocks along the
proposed alignment are highly jointed, fractured, folded.
The general trend of the rocks is NW-SE having dip towards NE direction. Murree Thrust
marks the tectonic contact between Tertiary and Pre-Tertiary rocks comprising meta volcano-
sedimentary of Lesser Himalayan terrain. It is thought to be an autochthonous folded belt of
tightly compressed and recumbent anticline varying in width upto about 7 kms. It lies between
the Murree Group of the foreland and the Salkhal ameta sediments of the Kashmir nappe. Its
outer boundary is the Murree Thrust, which has brought the rocks of this para autocthonous
folded belt over the Murree Group.
The northern boundary is marked by the Panjal Thrust/ main central Thrust, a low angle plane
almost parallel to Murree Thrust, which has brought the entire Tethyan Himalayan
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 10
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Phanerozoic succession of Kashmir along with its crystalline basement over the Lesser
Himalayan Belt. The Lesser Himalayan Belt extends up to north of Digdaul from where the
Phanerozoic succession of Kashmir nappe with basement of Salkhalas starts (Agarwal and
Agrawal, 2005). Overriding the rocks of Parautochthonous belt along Panjal thrust, Salkhala
Group of rocks occur, as a narrow belt in Digdaul- Sildhar - Rajgarh section, comprising of
thick sequence of schistose quartzites, phyllite, and schists intruded by granodiorite-diorite,
gabbro, pegmatites and basic rocks. These are uncomfortably overlain with Ramsu Formation
comprising of highly compressed sequence of pyritiferous, carbonaceous Phyllitic Quartizites,
dolomitic crystalline, siliceous limestone, quartzite, phyllite and basic rocks and are in turn
uncomfortably overlain with the limestone, marl quartzite, Phyllitic Quartizite lithology of
Syringothyris Limestone Formation, and in turn are overland with Fenestella Shales Formation
and Agglomeratic Phyllitic Quartizite Formation exposed in the hill slopes south of Banihal
Pass and Panjal Volcanic Formation exposed in the Banihal tunnel.
Fig. 1 Outline geological map of the Himalayan Mountain Belt showing its major tectonic
subdivisions across the range.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 11
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
North of Banihal Tunnel the folded Triassic limestone along with minor Jurassic shale beds
are exposed in the section upto Qazigund. Quaternary sediments represented by Karewas
Formation are exposed beyond Qazigund towards north upto Srinagar in Kashmir. Table
showing Stratigraphic sequence (based on GSI Special Pub. 26, 1989) is given below table 2:
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 12
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
5.2 Slates/Phyllites exposures constitute bed rock in the area, in the right and left banks of Nallah .
At bridge site bed rock outcrops are exposed in the river bed right bank. Phyllites /Slate thinly
foliated with occasional Quartzite bands are commonly met with & ptygmatic folding is
pronounced. The thick sequence of meta sediments exposed are compact to blocky, with
moderate to weak strength. Occasionally micro to macro qtz veins is traversing the formations
& gives it more compactness. The weathering grade is slightly to moderately weathered. On the
regional scale they are placed as Precambrian and in the proximity theses rocks are separated
from the Murries formation by a thrust called Murree Thrust &from Salkhlas by Panjal Thrust.
These thrust, close proximately have impact on the Bridge components. The joints, partially
open to wide with variable spacing, are criss cross in nature. The multiple joints have rendered
the rocks very blocky to disturbed and susceptible to rock fall at some locations in the area. The
rock mass consists of slate/phyllite & Phyllitic quartzite interbedded with carbonaceous
phyllite. Presence of quartzite has also been detected.
These lithounits mostly conceal the older terraces & bed rock. The debris is made of angular to
sub-angular components embedded in clayey matrix mostly compact, whereas the rock fall
being mostly thin and loose in nature. The strata are made of pre-existing lithounits.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 13
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
This material is of Recent to Sub Recent origin and is occupied by the Dassa Nallah. and
nallah material comprises of rounded to sub-rounded boulders, pebbles, cobbles associated
with sand and silt. The river terraces are fresh brought by the fluvial processes & are pervious
in nature.
borehole(
inclinatio
lithology
depth(m)
Bed rock
Borehole
Location
Depth of
Depth
Sr. No
wise
No
m)
n
0.00 -20.00(OB)
1 P1 Vertical 43 20.00
20.00-43.0(BR)
0.00 -17.00(OB)
2 P2 Vertical 40 17.00
17.00-40.0(BR)
0.00-64.00(OB)
3 P3 Vertical 73 64.0
64.00-73.00(BR)
0.00-69.00(OB)
4 P5 Bridge No 3 Vertical 78 69.0
69.00-78.00(BR)
0.00-49.00(OB)
5 P6 Vertical 63 49.0
49.00-63.00(BR)
0.00-30.00(OB)
6 P7 Vertical 61 30.0
30.00-61.00(BR)
0.00-2.00(OB)
7 A2 Vertical 27 2.0
2.00-27.00(BR)
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 14
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Note: OB (Overburden) i.e., gravel, pebble, cobble, boulder in silty sand matrix
BR (Bed Rock)
From the perusal of the core log data, following observations were made to revel the
subsurface Geology.
This material is of Recent to Sub Recent origin and is occupied by the Dasa Nallah. And
nallah material comprises of rounded to sub-rounded boulders, pebbles, cobbles associated
with sand and silt. The river terraces are fresh brought by the fluvial processes & are pervious
in nature. The estimated thickness encountered in Borehole P6 and P7 is 30.00m and 49.00m
respectively.
Colluvium of variable thickness encountered in Boreholes P1, P2, P3, P5 at major bridge
across Dassa Nallah. It comprises angular, sub-angular and sub-rounded boulders and rock
fragments of slate/phyllite, Quartzite& Gneiss within finer rock fraction & silt.
The bed rock comprises Phyllitic Quartzite & Quartzite. This unit covers the entire project area
and is often exposed or concealed under overburden of varying thickness. The megascopic
examination reveals that the rocks mass is moderately weathered to fresh (W2-W0). The depth
of weathering is anticipated is deep which is reflected from the joint planes. GreyishColoured
slightly weathered, Blocky to very blocky/sheared, medium strong to weak Phyllitic Quartzite
& interbedded occasional bands dark coloured slightly weathered to fresh Slate/Phyllites.
Slate/Phyllites is mostly of very blocky/blocky nature as the foliation planes & joint are
closely spaced. The massive milky white hard quartzite bands are also interbedded with
phyllitic quartzite.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 15
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
BH-P1
Overburden from 0.00m to 20.00m drilling depth consisting Angular to sub angular pebbles,
cobbles& boulders of Slate & Quartzite having capping of clay matrix.
Bed rock from 20.00m to 43.00m drilling depth consisting Greyish coloured slightly to
moderately weathered to fresh, fine to coarse grained Quartzite contains random quartz veins
& interbedded shear seam/zones.
S. Depth
Lithology Geological Description
No. Range
BH-P2
Overburden from 0.00m to 17.00m drilling depth consisting angular pebbles of slate/phyllite
embedded in soft reddish clay matrix.Angular to sub angular pebbles, cobbles & boulders of
Quartzite, Phyllitic Quartzite &Slate. Bed rock from 17.00m to 40.00m drilling depth
consisting milky white coloured, very blocky, slightly weathered & strong Quartzite contains
reddish Iron stains on core surface and along joint planes.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 16
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
BH-P3
Overburden from 0.00m to 64.00m drilling depth consisting angular pebbles of slate/phyllite
embedded in soft reddish clay matrix. Angular to sub angular pebbles, cobbles& boulders of
Phyllitic Quartzite/Slate, from 64.00m to 73.00m drilling depth consisting Milky white
coloured, very blocky , slightly weathered & medium strong to strong quartzite..
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 17
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 18
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
BH-P5
Overburden from 0.00m to 69.00m drilling depth consisting of boulders, cobbles and pebbles
of Phyllite, Mica Schist and Gneiss. Bed rock from 69.00m to 78.00m drilling depth consisting
Grey coloured, fine to medium grained, slightly to moderately weathered, foliated Phyllite.
Thin quartz veins are present. Detailed Lithological Summary of Boreholes as per below.
BH-P6
Overburden from 0.00m to 49.00m drilling depth consisting Semi angular to semi rounded
pebbles, cobbles & Boulders of Gneiss, Phyllitic Quartzite. From49.00m to 63.00m drilling
depth consisting Dark coloured, blocky slightly weathered & medium strong to weak Phyllite
contain quartz veins along foliation as well as randomly.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 19
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
BH-P7
Overburden from 0.00m to 30.00m drilling depth consisting Sub rounded to sub angular
pebbles, cobbles & boulders of Gneiss, Slate & Quartzite. Bed rock from 30.00m to 61.00m
drilling depth consisting Greyish coloured, blocky, slightly weathered & medium strong fine
grained phyllitic quartzite contains random Quartz veins.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 20
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Depth
S. no. Lithology Geological Description
Range
BH-A2
Overburden from 0.00m to 2.00m drilling depth consisting angular angular pebbles & cobbles
of Phyllite. Bed rock from 2.00m to 27.00m drilling depth consisting Dark grey coloured, very
blocky slightly weathered & weak Phyllite contains occasional quartz veins.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 21
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 22
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
cased up to 19.00m & from 19.00 -40.00m remains uncased indicates weakness of the slope
debris. The penetration rate varies in slope debris from 17-28mm/min, & in bed rock from 15-
33mm/min & fracture frequency is over 15/m to 8-5/m.The ground water table has met at
24.00 drilling depth. The expected foundation media is very blocky/blocky, strong milky white
quartzite.
This bore-hole has been drilled vertical to a depth of 78.0 mts, from ground level at RL –
1394.753. The bed rock comprising Gray coloured, fine to medium grained, slightly to
moderately weathered, foliated Phyllite contains thin quartz veins. Rock mass is slightly to
moderately weathered. Two plus sets of joints have blocky /very blocky the rock mass. The
core recovery in bed rock is of the order of 44 to 66% and R. Q. D. is NIL to 32%. The nil to
partial water loss is observed from 0.00 to 78. 00m.The bore is cased up to 55.00m & from
55.00 -78.00m remains uncased indicates weakness of the slope debris &consolidation of deep
slope debris &rock mass. The penetration rate varies in slope debris from 1.67-5cm/min & in
bed rock from 1.42-2.5cm/min . The fracture frequency is over 15/m to 15-8/m &ground water
table has met at 37.00 drilling depth. The expected foundation media is very blocky/blocky,
medium strong to weak foliated Phyllite.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 23
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
This bore-hole has been drilled vertical to a depth of 63.0 mts, from ground level at RL –
1407.996 mts. The bed rock comprising Dark colored, blocky slightly weathered &medium
strong to weak phyllite contain quartz veins along foliation as well as randomly.Two plus sets
of joints have blocky /very blocky the rock mass. The core recovery in bed rock is of the order
of 81 to 100% and R. Q. D. is NIL to 67. The complete water loss has been observed from
00.00 - 63. 00m.The bore is cased up to 49.00m & from 49.00 -63.00m remains uncased
indicates weakness of the fluvio-glacial deposit. The penetration rate varies in slope debris
from 15-22mm/min, & in bed rock from 14-19mm/min & fracture frequency is over 15/m to
8-5/m. The ground water table has met at 5.00 drilling depth. The expected foundation media
is medium strong to weak phyllite contain quartz veins.
This bore-hole has been drilled vertical to a depth of 61.0 mts, from ground level at RL -
1402.101.The bed rock comprising Greyish coloured, blocky, slightly weathered & medium
strong fine grained phyllitic quartzite contains random Quartz veins. Two plus sets of joints
have blocky /very blocky the rock mass. The core recovery in bed rock is of the order of 32 to
100% and R. Q. D. is NIL to 48%. The partial is observed from 0.00 to 12.00m& 19-38m&
complete water loss has been observed from 12.00 to 19. 00m& 38-61m. The bore is cased up
to 38.00m & from 38.00 -61.00m remains uncased indicates weakness of the fluvio-glacial .
The penetration rate varies in fluvio-glacial debris from 15-20mm/min & in bed rock from 15-
20mm/min . The fracture frequency is over 15/m to 15-8/m. The ground water table has met at
3.00 drilling depth. The expected foundation media is Greyish coloured, blocky, slightly
weathered & medium strong fine grained phyllitic quartzite contains random Quartz veins.
This bore-hole has been drilled vertical to a depth of 27.0 mts, from ground level at RL –
1416.831mts. The bed rock comprising Dark grey colored, very blocky slightly weathered &
weak PHYLLITE contains occasional quartz veins.three plus sets of joints have blocky /very
blocky the rock mass. The core recovery in bed rock is of the order of 44 to 100% and R. Q. D.
is NIL to 100%. The partial water loss is observed from 0.00 to 27.00m. The bore is cased up
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 24
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
to 2.00m & from 2.00 -27.00m remains uncased indicates hardness of the rock mass . The
penetration rate varies in slope derisdebris from 22mm/min & in bed rock from 15-20mm/min
. The fracture frequency is over 15/m to <1/m. The ground water table has met at 7.00 drilling
depth. The expected foundation media is Dark grey coloured, very blocky slightly weathered
& weak phyllite contains occasional quartz veins
6.5 Seismicity
6.5.1 Seismo tectonic studies on the Himalayas and Parsons et al., 2006; have revealed that
some segments of the Himalayan mountain belt have not experienced major and great
earthquakes in the past 100 years or so though they have the potential to generate large
earthquakes (Gahalaut. 2006). Based on the earthquake occurrence and their locations
along the Himalayas, three main seismic gaps/segments have been Identified in the
Himalaya; Assam gap (1950 Assam and 1934 Bihar- Nepal earthquakes), Central gap
(1905 Kangra and 1934 Bihar—Nepal earthquakes) and Kashmir gap (1905 west of the
Kangra earthquake) (Khattari, 1987; Seeber and Armbruster, 1981). These gaps are
also considered as the future locations of major and great earthquakes. The study area
lies towards Southeast of Kashmir seismic gap.
6.5.2 The seismic activity in the area is attributed to the active nature of Murree Thrust, Panjal
Thrust and other deep faults present in the area. Themicro earthquake data (given in
subsequent section) suggests that the area is seismically active. Seismic hazard map of
the Jammu and Kashmir is given in Plate 2. Accordingly the study area falls within Zone
V of seismic map of India. It is therefore important to consider seismicity while
designing the civil structure as per zone-V.
Actual seismic coefficient for acceleration is evaluated on the basis of seismo tectonic
analysis of the area which is normally being undertaken by earthquake department of IIT
Roorkee and is beyond our scope. However based on IS 1893 zone factor of this area can
be considered as vertical acceleration value for design, for horizontal coefficient half of
the zone factor can be considered for design.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 25
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Plate 2
6.5.3 Massive landslides and catastrophic mass movements are a regular affair in the
Himalayas and related high ranges. The Himalaya, with the greatest relief and steep
slopes on the earth, has high magnitude landslides. Landslide hazard map given in Plate -
3 reveals that the study area is prone to landslides.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 26
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Plate 3
SI.
Test Designation Standard Codes
No
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 27
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 28
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
(Part 5 & 6). The liquid limit has been determined using the Casagrande apparatus method. The
soil sample preparation, in accordance with the code of practice, included removal of soil
particles retained on the 425μm sieve. Accordingly, where a significant quantity of coarser
particles was present, it should be noted that the Atterberg Limits results are representative of the
relatively fine soil fraction, and not of the complete soil sample.
7.2.5 Saturated Moisture Content, Unit Weight, Specific Gravity and Porosity of Rock specimen
were determined for rock samples by using saturation and buoyancy technique, in accordance
with the methods of IS:13030.
7.2.6 Test Point load Index tests were performed on selected rock lump and rock specimen, not
amenable to UCS test, in accordance with the method suggested by IS: 8764 (1978) and
International Society for Rock Mechanics.
7.2.7 Uniaxial compressive strength for cylindrical rock specimens was determined in accordance
with the methods of ISRM. The uniaxial compressive strength of the specimen was corrected
for a height to diameter ratio of two for specimens whose height to diameter ratio was other
than two using the following relationship:
Where,
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 29
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
m3= Mass in g of the container with its lid and the sample after drying
7.2.9 Porosity And Density Determination Using Saturation And Buoyancy Techniques
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 30
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
g) The sample is removed from the immersion bath and surface dry the sample with a moist
cloth, care being taken to remove only surface water and to ensure that no rock fragment are
lost. The sample is transferred to the sample container and replace the lid. The mass, M4, of
the saturated surface dry sample plus container is determined.
h) The lid is removed and place the container with contents and lid in the oven and dry at 105 &
3°C. The sample is deemed to be dry when the difference between successive determination of
mass of the cooled sample at interval of 4 hours does not exceed 0.1 percent of the original
mass of the sample.
i) Replacing the lid, remove the container from the oven and place the whole in the desiccator to
cool for 30 minutes.
k) The dried mass, M5, of the container with the oven dry sample is determined.
Calculations
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 31
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Pd = (Ms) (kg/m3)
V
The ability of spherical seat to rotate freely shall be checked before each test. The surfaces of
the two bearing discs and the test specimen shall be wiped clean. The specimen shall be kept
on the lower disc. The axis of the specimen shall be carefully aligned with the centre of the
thrust of the spherical seat. As the load is gradually brought to bear on the specimen, the
movable portion of the spherically seated disc shall be adjusted to ensure uniform seating.
Load on the specimen shall be applied continuously at a constant stress rate such that failure
will take place in about 5 to 15 minutes of loading. Alternatively, the stress rate shall be within
the limits of 0.5 MPa/s to 1 MPa/s. The maximum load on the specimen shall be recorded in N
within 1 Percent accuracy. The number of specimens to be tested should be determined from
practical considerations.
CALCULATION
The unconfined compressive strength of the specimen shall be calculated by dividing the
maximum load carried by the specimen during the test, by the average original cross-sectional
area.
8.1 The sub-surface in general is based on Boreholes drilled at P1, P2,P3, P5,P6 and P7 locations
respectively is comprises of Metamorphic rock-Phyllitic Quartizites of different alterations
underlying colluvium (Pebbles , Cobbles , Boulders of Phyllitic Quartizite, Schists with sandy
matrix). The thickness of colluviums( gravel, boulder, pebble, cobble,) ranges from 20 to 69 mtrs
in pier locations The drilling through bed rock of Phyllitic Quartizite has shown RQD nil to 100.
The rock mass rating (RMR) is found to of poor to fair class.
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 32
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 33
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Table -3
Parameters P1 P2 P3 P5 P6 P7 A2
Over burden in 64 49 30 2
20 17 69
(m)
Overburden
Overburden(Semi
Overburden (angular Overburden consists of
angular to semi Overburden
Overburden (angular pebbles of Slate phyllite (angular to boulders, cobbles
rounded pebbles (subrounded to sub Overburden
to subangular pebbles embedded in soft subangular and pebbles of
,cobbles & boulders angular boulders of (angular pebbles
,cobbles & boulders reddish clay pebbles ,cobbles Phyllite, Mica
of Gneiss ,Phyllitic Slate Quartizite, &cobbles of
of Slate & Quartizite matrix.Angular to & boulders of Schist and geneiss
Quartizite) Gneiss & Migmatite phyllite)
having capping of subangular pebbles , Slate ,Phyllitic and rock Gray
Bedrock(Dark and rock of grayish Bedrock(dark grey
Rock type clay matrix and rock cobbles & boulders of Quartizite) coloured, fine to
coloured ,blocky coloured blocky, coloured,very
of Greyish coloured Quartizite Phyllitic Bedrock (milky medium grained,
slightly weathered & slightly weathered & blocky slightly
slightly to moderately Quartizite & Slate and white slightly to
medium strong weak medium strong fine weathered &weak
weathered to fresh , rock of Milky white coloured,very moderately
phyllite contain grained Phyllitic phyllite contains
fine to coarse grained coloured, very blocky, blocky, slightly weathered, foliated
Quartz veins along Quartizite contains quartz veins)
Quartizite slightly weathered & weathered & Phyllite. Thin
foliation as well as random Quartz veins
strong Quartizite strong Quartizite quartz veins are
randomly)
present.
Core recovery % 20-83 19-98 10-91 22-100 29-100 30-100 30-100
RQD Nil -46 Nil -70 Nil-26 Nil -32 Nil-67 Nil-48 Nil -100
RMR Poor Poor-fair Poor Poor Poor-fair Poor Poor-fair
Depth of water
29 24 25 37 5 3.0 7
table (m)
Any geological
structure met No No No No No No No
with
UCS(Normal/su Under progress 36.82/32.83 Under progress
bmerged) (MPa)
Point Load 1.88
(MPa)
Porosity % 0.89
Water absorp % 0.33
Bulk Density 2.745/2.736
/Dry density (%)
Specific gravity 2.760
(gm/cc)
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 34
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No : P1(Br-3)
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Drilling Depth
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
UCS Rating
3 3 8 3 8 3 8 8 8 3 3 3 3 8 3 3 3 3 3 3 3 3 3
RQD Rating
8 8 10 8 8 8 10 10 10 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Spacing of discontinuities
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Persistance
Condition of discontinuities
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Aperture
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Roughness
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Infilling
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Ground water conditions
38 38 45 38 43 38 45 45 45 38 38 38 38 43 38 38 38 38 38 38 38 38 38
Adjustment strike and dip
-7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7
orientation
RMR Value 31 31 38 31 36 31 38 38 38 31 31 31 31 36 31 31 31 31 31 31 31 31 31
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 35
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No : P2(Br-3)
Drilling Depth 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
UCS Rating 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
RQD Rating 3 3 3 3 3 3 3 3 3 3 3 8 8 13 13 13 3 13 8 8 3 3 3
Spacing of discontinuities 8 8 8 8 8 8 8 8 8 8 8 10 10 10 10 10 8 10 10 10 8 8 8
Persistance 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Condition of discontinuities
Aperture 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Roughness 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Infilling 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
38 38 38 38 38 38 38 38 38 38 38 45 45 50 50 50 38 50 45 45 38 38 38
RMR Value 31 31 31 31 31 31 31 31 31 31 31 38 38 43 43 43 31 43 38 38 31 31 31
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 36
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No : P3(Br-3)
Drilling Depth 64.00 65.00 66.00 67.00 68.00 69.00 70.00 71.00 72.00 73.00
UCS Rating 4 4 4 4 4 4 4 4 4
RQD Rating 3 8 3 3 3 3 3 3 3
Spacing of discontinuities 8 10 8 8 8 8 8 8 8
Condition of discontinuities
Persistance 2 2 2 2 2 2 2 2 2
Aperture 4 4 4 4 4 4 4 4 4
Roughness 5 5 5 5 5 5 5 5 5
Infilling 6 6 6 6 6 6 6 6 6
Weathering 6 6 6 6 6 6 6 6 6
Ground water conditions 0 0 0 0 0 0 0 0 0
Adjustment strike and dip orientation -7 -7 -7 -7 -7 -7 -7 -7 -7
RMR Value 31 38 31 31 31 31 31 31 31
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 37
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No : P5(Br-3)
Drilling Depth 69 70 71 72 73 74 75 76 77 78
UCS Rating 4 4 4 4 4 4 4 4 4
RQD Rating 8 3 3 3 3 3 3 3 3
Spacing of discontinuities 8 8 8 8 8 8 8 8 8
Aperture 4 4 4 4 4 4 4 4 4
Roughness 5 5 5 5 5 5 5 5 5
Infilling 6 6 6 6 6 6 6 6 6
Weathering 6 6 6 6 6 6 6 6 6
RMR Value 36 31 31 31 31 31 31 31 31
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 38
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No : P6(Br-3)
Drilling Depth 49.00 50.00 51.00 52.00 53.00 54.00 55.00 56.00 57.00 58.00 59.00 60.00 61.00 62.00 63.00
UCS Rating 4 4 4 4 4 4 4 4 4 4 4 4 4 4
RQD Rating 3 3 8 8 13 8 3 3 13 3 13 8 3 8
Spacing of discontinuities 10 10 10 10 15 8 8 8 15 8 15 10 10 10
Persistance 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Roughness 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Infilling 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering 6 6 6 6 6 6 6 6 6 6 6 6 6 6
RMR Value 33 33 38 38 48 36 31 31 48 31 48 38 33 38
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 39
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No :
P7(Br-3)
Drilling Depth 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61
UCS Rating 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
RQD Rating 8 8 8 3 8 8 3 3 3 3 3 3 3 8 8 3 3 3 3 3 3 3 3 3 3 8 8 8 8 8 8
Spacing of discontinuities 10 10 10 8 10 10 8 8 8 8 8 8 8 10 10 8 8 8 8 8 8 8 8 8 8 10 10 10 10 10 10
Persistance 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Condition of discontinuities
Aperture 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Roughness 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Infilling 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 40
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Borehole No : A2(Br-3)
2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0
Drilling Depth
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
UCS Rating
3 3 3 3 3 3 8 3 3 3 3 8 8 3 8 20 3 3 3 3 8 8 3 13 20
RQD Rating
Spacing of 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 15 10 10 10 10 10 10 10 10 15
discontinuities
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Persistence
Condition of discontinuities
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Aperture
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Roughness
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Infilling
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Weathering
Ground water 15 15 15 15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
conditions
Adjustment strike and -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7 -7
dip orientation
48 48 48 48 33 33 38 33 33 33 33 38 38 33 38 55 33 33 33 33 38 38 33 43 55
RMR Value
SUBMITTED
TO Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment A2 of bridge No 3
P a g e | 41
Of Dharam-Qazigund Section Of USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
The subsurface in general at all the borehole locations can be considered as sedimentary
formations comprising of Boulders, gravel, cobble with sandy matrix The overlying
Phyllitic Quartizites of different alterations over burden material neither falls in rocks
nor under soil and the investigation for establishing design parameters in such materials
have be carried out in accordance with IS: 10042whichnecessities conducting in situplate
load tests, blocks hear tests and in-situ density measurements. Such types of deposits be
have peculiarly, initially these materials upon loadings how rapid increase in settlement
and beyond about 1% settlement with increasing loads the rate of settlement decreases.
This is primarily due to the fact that unlike ordinary soils these materials show initial
rapid compression and once particle to particle contact gets established the compression
decrease considerably with load carrying function mainly be in taken over by the larger
sized particles. Figure-2of IS:10042bringoutthis behavior clearly.
The material that is met with at the proposed bridge site is somewhat similar to that is
reported in Figure-2 of IS: 10042 which is reproduced below for reference and better
understanding.
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 42
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
It is observed from the afore said figure that settlement ratio (ratio of settlement observed
in the case of large size to settlement of small size) increases with the increase in size of
test plate. In accordance with IS:1888 for permissible settlement of 25mm for shallow
foundation of 8mx8msize,the allowable bearing capacity of gravel boulder is evaluated
from Figure-2 corresponding to settlement of plate as per equation Sp=Sf
[B(Bp+0.3)/Bp(B+0.3)]² =17.22mm. For settlement of 17.22mm,the allowable bearing
capacity works out to be 4.2kg/cm2 or 42t/m2. On the other hand, Teng’s modified
allowable bearing capacity for gravelly soils for 25mm settlement given by
q25=3.35xCb(N-3)[(B+0.3)/2B]2dwdf (in which Cb=constant=2 for gravelly soil sand dw
&df are water table reduction factor and depth factor respectively) .With depth factor
dflimited to 1.33 for deep foundation and water table correction factor as 0.5,the net
allowable bearing capacity for 25mm permissible settlement works out to be 56.35t/m²for
8m dia well with depth of foundation at 20m.However the gross allowable bearing
capacity shall be limited to (42+20)=62t/m2.
Under shear consideration for Ø = 34o, the safe bearing capacity in accordance with IS
6403 the safe bearing capacity works out to be greater than 100t/m2 for width of 8m.
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 43
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
8 42 62 67 87
20
10 41 61 65 85
P3
8 69 99 107 137
30
10 68 98 104 134
8 42 62 67 87
20
10 41 61 65 85
P5
8 69 99 107 137
30
10 68 98 104 134
8 42 62 67 87
20
10 41 61 65 85
P6
8 69 99 107 137
30
10 68 98 104 134
8 42 62 67 87
20 P7
10 41 61 65 85
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 44
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 45
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
1. As per IS code 10042 it is not reliable to believe on the laboratory tests of disturbed
samples, as the natural arrangements of the grains and matrix material are never achieved
by re compaction the best results are obtained by properly chosen field test.
2. We opine to use the aforesaid values limiting the net bearing capacity values for well
foundation to 110t/m2 or the values given in section 8.6 whichever is lower ensuring at
least 1.0m embedment in rock subject to the condition that rock type available at site
same as given in the reference boreholes. However, deep well foundation will not be
feasible from practical consideration.
3 Adequate protective measures for the abutment slopes may be suitably provided during
construction stage at the proposed bridge sites.
4. The detailed geological mapping may be carried out to delineate the different geological
formation and related problems likely to be encountered during the construction stage.
The Bridge sites lie in seismic zone V (IS 1893 Part-1) 2002 for adopting suitable seismic
coefficient for civil engineering structures in the area
5. Indian railway standard code of practice for the design of structure and design of bridges
(Revised 1985) may be adopted for the design of bridge.
Consultant
Space Engineers Consortium Pvt. Ltd
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL P a g e | 46
Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and
TO
Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 47
USBRL Project Jammu And Kashmir
HCC Limited
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
BR-03 P1
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+196
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 5111079.245E, 3684672.283N FEATURE Major Bridge Abutment
COLLAR ELEVATION (m) 1391.717 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 43.00
GROUND ELEVATION(m) 1391.617 TYPE(S) OF CORE BARREL Triple Tube
STARTED : 15.03.2018 COMPLETED 25.03.2018 DRILLING AGENCY : SECP Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
15
25
35
60
25
_
_
_
_
_
_
1.000 1.00
20
29
36
65
30
_
_
_
_
_
2.000 2.00
20 40
_
2
_
_
3.000 3.00
PX
PX
25 40
_
_
_
2
_
4.000 4.00
30 45
_
_
2
1
5.000 5.00
20 40
_
_
_
_
_
6.000 6.00
28 35
_
_
2
_
_
7.000 7.00
25 40
_
_
_
_
_
8.000 8.00
Slope Debris(Colluvium)
Slope Debris(Colluvium)
25 50
_
_
2
_
_
9.000
Angular to sub
9.00
Not Applicable
angular
pebbles,cobbles Overburden
30 50
_
_
1
1
_
Partial
10.000 10.00
& boulders of
Slate & Quartzite 30 30
_
_
2
_
_
11.000 11.00
having capping
of clay matrix. 30 40
_
_
2
_
_
12.000 12.00
HX
HX
23 40
_
_
2
_
_
13.000 13.00
30 50
_
_
3
1
_
14.000 14.00
Dry
34 40
_
_
5
_
_
15.000 15.00
30 45
_
_
1
_
_
16.000 16.00
35 50
_
_
1
1
17.000 17.00
IMP (NX Size ) Diamond Bit
46 50
_
_
1
2
_
18.000 18.00
41 40
_
_
1
2
_
19.000 19.00
Core samples
30 50
_
_
1
_
_
20.000 20.00
Very Very
40 17 60
_
_
_
_
1
Over 15
blocky/shea blocky/s
21.000 21.00 red heared
Very Very
42 NIL 55
_
_
2
1
_
blocky/shea blocky/s
22.000 22.00 red heared
15-8
Blocky Blocky 63 42 60
_
_
1
_
2
23.000 23.00
Over
Greyish colored
15
Blocky Blocky 41 10 60
_
_
2
2
Blocky Blocky 52 27 60
_
_
2
1
1
Blocky Blocky 51 12 65
_
_
2
2
_
NX
NX
Blocky Blocky 83 46 70
_
_
3
1
2
Blocky Blocky 60 44 65
_
_
1
_
2
Very Very
68 13 70
_
_
1
1
1
blocky/sheablocky/s
30.000 30.00 red heared
Very Very
72 NIL 70
_
_
2
2
1
blocky/sheablocky/s
31.000 31.00 red heared
Very Very
64 14 60
_
_
1
2
1
blocky/sheablocky/s
32.000 32.00 red heared
Very Very
53 NIL 65
_
_
6
_
_
blocky/sheablocky/s
33.000 33.00 red heared
Over 15
34.000
slightly blocky/sheablocky/s
34.00 red heared
weathered, fine
Very
to coarse Very block 36 NIL 75
_
_
2
1
_
Page 48
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
BR-03 P1
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+196
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 5111079.245E, 3684672.283N FEATURE Major Bridge Abutment
COLLAR ELEVATION (m) 1391.717 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 43.00
GROUND ELEVATION(m) 1391.617 TYPE(S) OF CORE BARRELTriple Tube
STARTED : 15.03.2018 COMPLETED 25.03.2018 DRILLING AGENCY : SECP Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
Very
Very block 60 60
_
_
5
1
_
_
Greyish colored block
Core samples
40.000 40.00 block NIL
NX
Complete
fresh, fine to
Over 15
Very
NX
coarse grained Very block 53 12 60
_
_
2
1
1
NIL
Very
Quartzite veins. Very block 82 10 60
_
_
1
6
Quartzite/Quarzitic
Schist
Page 49
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO. P2
SHEET NO.: 1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+236.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511096.700E,3684709.815N FEATURE P2(Br-3)
COLLAR ELEVATION (m) 1393.538 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 40.00
GROUND ELEVATION(m) 1393.438 TYPE(S) OF CORE BARREL DT/TT
STARTED : 01.04.2018 COMPLETED 24.04.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Size of core Structural Drill Water SPT-Number of
Lithology Ratio Percent Core Recovery (%) Loss Permeability
pieces (In No's) Condition Blows
Fracture Frequency / m
Interpreted %age of
Special
Interpreted %age of
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
rock fragments
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
10 to 25 mm interpretations /
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
mm/s OR
Depth (m)
Description
Description
Type of Bit
matrix (fine)
Weathering Grade
LUGEON
(mm/min)
Complete
>150 mm
In figures
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
Angular pebbles of
slate/phyllite embedded in 25
1.000 1.00 soft reddish clay matrix.
22 22
2.000 2.00
28 22
3.000 3.00
20 20
4.000 4.00
26 17
5.000 5.00
25 18
6.000 6.00
Slope Mass Debris (Colliuvum)
25 17
7.000 7.00
Angular pebbles of 30 17
Not Applicable
Overburden
8.000 8.00 slate/phyllite
embedded in soft
reddish clay matrix. 25 18
9.000 9.00
Angular to sub angular
NX
pebbles, cobbles & 23 17
10.000 10.00 boulders of Quartzite,
Phyllitic Quartzite &
Slate. 30 17
11.000 11.00
30 17
Partial
12.000 12.00
Dry
30 20
13.000 13.00
32 28
14.000 14.00
35 20
15.000 15.00
30 18
16.000 16.00
32 17
17.000 17.00
IMP (Nx size) Diamond Core Bit
Very
Very blocky
/disrturbed
blocky 30 NIL 18
18.000 18.00 /disrturbed
Core Samples
Very
Very blocky
/disrturbed
blocky 40 NIL 17
19.000 19.00 /disrturbed
NX
Very
Very blocky
/disrturbed
blocky 19 NIL 33
20.000 20.00 Milky white colored, /disrturbed
very Very
Very blocky
blocky/disturbed , /disrturbed
blocky 35 NIL 18
21.000 21.00 /disrturbed
slightly weathered &
Very
strong QUARTZITE. Very blocky
/disrturbed
blocky 28 NIL 17
22.000 22.00 /disrturbed
Over 15
Very
Very blocky
/disrturbed
blocky 52 11 18
23.000 23.00 /disrturbed
Very
Very blocky
/disrturbed
blocky 42 15 17
24.000 24.00 /disrturbed
24
Very
Very blocky
/disrturbed
blocky 46 25 15
25.000 25.00 /disrturbed
Very
Very blocky
/disrturbed
blocky 86 24 17
26.000 26.00 /disrturbed
Joint planes
0 0
50 (3) , 30 (1), 70 NIL 15
Sm/Pl & Iron
27.000 27.00 stains
Joint planes
0 0
75 (1) , 45 (1), 94 21 15
Sm/Pl & Iron
28.000 28.00 stains
Joint planes
NIL
0
Milky white colored, 45 (4) Sm/Pl & 98 40 15
15-8
0
Iron stains on core 45 (5) Sm/Pl & 94 70 17
31.000 31.00 Iron stains
surface and along Joint planes
8-5
joint planes. 0 0
45 (4) , 75 (1), 98 61 15
Sm/Pl & Iron
32.000 32.00 stains
Blocky Blocky 98 58 17
33.000 33.00
Joint planes
Over
15
0
50 (1) Sm/Pl & 98 NIL 15
34.000 34.00 Iron stains
Joint planes 40-
8-5
0
50 (2) Sm/Pl & 96 69 17
35.000 35.00 Iron stains
Joint planes
0
45 (3) Sm/Pl & 98 43 15
15-8
0
QUARTZITE. 50 (2) Sm/Pl & 97 20 15
38.000 38.00 fresh
Page 50
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P2
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:- 111+236.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511096.700E,3684709.815N FEATURE P2(Br-3)
COLLAR ELEVATION (m) 1393.538 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 40.00
GROUND ELEVATION(m) 1393.438 TYPE(S) OF CORE BARRELDT/TT
STARTED : 26.03.2018 COMPLETED 24.04.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
Bit Bit
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type ofCore
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
IMP (Nx size) Diamond
Partial
15-30
30-45
0-15
Log
Log
Core Samples
Joint planes
Complete
0 0
68 11 17
Over 15
Not Met
50 (2), 25 (1)
Milky white colored, very
39.000 39.00 Sm/Pl & fresh
NIL
NX
blocky , slightly weathered
& strong QUARTZITE.
Blocky Blocky 70 15 17
40.000 40.00
Quartzite
Page 51
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P3
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE P3(BR-3)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 73.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARREL Triple Tube
STARTED : 26.03.2018 COMPLETED 08.05.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
0.500 Reddish - - - - -
1.000 1.00 coloured soft 20
1.500 clay contains
- - - - -
2.000 2.00 angular pebbles. 17
2.500 Washout material
2 - - - - 30
3.000 3.00 coarse sand and 18
silt.
3.500
5 - - - - 30
4.000 4.00 22
Angular to sub
4.500
angular pebbles 3 - - - - 33
5.000 5.00 17
& cobbles of
5.500
Slate & Phyllitic 7 - - - - 32
6.000 6.00 18
Quartzite .
6.500
3 - - - - 33
7.000 7.00 17
7.500
7 - - - - 51
8.000 8.00 17
HX
HX
8.500
3 2 1 - - 90
9.000 9.00 Angular to sub 20
9.500 angular boulders
5 - - - - 60
10.000 10.00 of Phyllitic 15
10.500 Quartzite
4 1 - - - 55
11.000 11.00 17
11.500
6 1 - - - 65
12.000 12.00 18
12.500
5 - - - - 60
13.000 13.00 17
13.500
6 - - - - 55
14.000 14.00 20
14.500
5 - - - - 55
15.000 15.00 18
15.500
5 - - - - 50
16.000 16.00 Angular to sub 15
16.500 angular 7 - - - - 50
17.000 17.00 pebbles,cobbles 17
17.500 & boulders of
Slope Debris (Colliuvum)
2 - - - - 40
18.000 18.00 Phyllitic 18
Not Applicable
Core Samples
Quartzite/Slate
Overburden
18.500
5 - - - - 55
Partial
19.000 19.00 17
19.500
5 - - - - 40
20.000 20.00 20
20.500
5 - - - - 55
21.000 21.00 18
21.500
3 - 1 - - 80
22.000 22.00 17
22.500
1 1 1 - - 58
23.000 23.00 18
23.500
3 - - - - 48
24.000 24.00 17
24.500 Angular to sub 8 - - - - 44
25.000 25.00 angular boulders 18
25.500 of
3 2 - - - 63
25
27.500
- 1 - - - 24
28.000 28.00 17
28.500
4 - - - - 43
29.000 29.00 15
29.500
- - - - - 13
30.000 30.00 20
Washout material
30.500
coarse sand and - - - - - 10
31.000 31.00 silt. 25
31.500
- - - - -
32.000 32.00 25
32.500
2 - - - - 18
33.000 33.00 18
33.500
4 1 - - - 43
34.000 34.00 15
34.500 Angular to sub - - - 1 - 79
35.000 35.00 angular boulders 15
35.500 of Gneiss &
4 - - - - 55
36.000 36.00 Slate. 20
36.500
1 1 - - - 30
37.000 37.00 22
37.500
3 - - - - 31
38.000 38.00 22
Page 52
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P3
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE P3(BR-3)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 73.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARRELTriple Tube
STARTED : 26.03.2018 COMPLETED 04.09.2016 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
38.500
2 1 - - - 30
_
39.000 39.00 _ 22
39.500
- 2 - - - 41
_
40.000 40.00 22
40.500
2 - - - - 38
_
43.000 43.00 20
43.500
4 - - - - 35
_
44.000 44.00 20
44.500
3 - - - - 35
_
45.000 45.00 22
45.500
4 - - - - 34
_
46.000 46.00 25
46.500 Angular to sub 2 2 - - - 40
_
49.000 49.00 18
49.500
Slope Debris (Colliuvum)
3 1 - - - 45
_
50.000 50.00 20
Not Applicable
Overburden
50.500
3 - - - - 50
_
Partial
51.000 51.00 20
51.500
2 1 - - - 38
_
2 1 - - - 40
_
54.000 54.00 22
54.500
4 - - - - 45
_
Core samples
55.00 25
NX
55.000
NX
55.500
- 1 - - - 36
_
56.000 56.00 25
56.500
5 - - - - 34
_
57.000 57.00 22
57.500
2 1 - - - 37
_
58.000 58.00 25
58.500 Angular to sub 1 2 - - - 46
_
62.000 62.00 . 25
62.500
2 1 - - - 45
_
63.000 63.00 22
63.500
4 1 1 - - 92
_
64.000 64.00 15
Very
64.500 Very blocky/
11 2 - - - blocky/ 66 NIL
_
Disturbed
65.000 65.00 Disturbed 15
Over 15
Very
65.500 Very blocky/
6 3 - - - blocky/ 90 NIL
_
Disturbed
66.000 66.00 Disturbed 15
Very
66.500 Very blocky/
10 2 - - - blocky/ 90 26 15-8
_
Disturbed
67.000 67.00 Disturbed 17
Milky white Very
67.500 Very blocky/
colored, very 9 1 - - - blocky/ 90 18
_
Disturbed
Complete
Disturbed
69.000 69.00 Disturbed 15
medium strong Very
69.500 Very blocky/
to strong 3 - - - - blocky/ 35 NIL
_
Over 15
Disturbed
70.000 70.00 Disturbed 17
QUARTZITE. Very
70.500 Very blocky/
4 - - - - blocky/ 35 NIL
_
Disturbed
71.000 71.00 Disturbed 15
Very
71.500 Very blocky/
3 1 - - - blocky/ 35 NIL
_
Disturbed
72.000 72.00 Disturbed 17
Very
NIL
Disturbed
73.000 73.00 Disturbed 17
Quartzite
Page 53
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No: 01
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI
STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018
PENETRATION RATE
SIZE OF CORE PIECES WATER
DEPTH OF WATER
in Nos LOSS
TYPE OF CASING
% OF RECOVERY
BILITY
TEST SECTION
cm/min
SPECIAL
ELEVATION
FREQUENCY
TYPE OF BIT
COMPLETE
75-150mm
DEPTH OF
PARTIAL
LUGEON
10-25mm
25-75mm
FRACTURE
>150mm
OBSERVATION
<10mm
% OF RQD
HOLE
NIL
DESCRIPTION LOG 20 40 60 80 100
LEVEL
NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL
1393.8 1.00 ── ── 2 ── ── 30 ── NA 100 HX ── ─ ─ ── ── 3.33
1392.8 2.00 ── ── 2 ── ── 30 ── NA 100 HX ── ─ ─ ── ── 2.50
1391.8 3.00 ── ── 6 ── ── 39 ── NA 100 HX ── ─ ─ ── ── 2.00
1390.8 4.00 Overburden consists of ── ── 2 ── ── 22 ── NA 100 HX ── ─ ─ ── ── 2.50
boulders, cobbles and pebbles
DIAMOND BIT
1389.8 5.00 ── 1 2 ── ── 35 ── NA 100 HX ── ─ ─ ── ── 2.22
of Phyllite, Mica Schist and
1388.8 6.00 Gneiss. ── ── 4 ── ── 40 ── NA 100 HX ── ─ ─ ── ── 2.50
1387.8 7.00 ── ── 5 4 ── 66 12 NA 100 HX ── ─ ─ ── ── 2.00
1386.8 8.00 ── ── 4 ── ── 37 ── NA 100 HX ── ─ ─ ── ── 2.22
1385.8 9.00 ── ── 4 1 ── 34 ── NA 100 HX ── ─ ─ ── ── 2.50
1384.8 10.00 ── ── 5 1 ── 41 ── NA 100 HX ── ─ ─ ── ── 2.00
1383.8 11.00 ── ── 3 ── ── 28 ── NA 100 HX ── ─ ─ ── ── 2.50
1382.8 12.00 ── ── 2 ── ── 32 ── NA 100 HX ── ─ ─ ── ── 2.00
Overburden consists of
1381.8 13.00 boulders, cobbles and ── ── 4 ── ── 40 ── NA 100 HX ── ─ ─ ── ── 2.50
1380.8 14.00 pebbles of Phyllite, Mica ── ── 4 ── ── 64 ── NA 76 NX ── ─ ─ ── ── 2.50
1379.8 15.00 Schist and Gneiss. ── ── 2 ── ── 51 ── NA 76 NX ── ─ ─ ── ── 2.00
1378.8 16.00 ── ── 2 ── ── 30 ── NA 76 NX ── ─ ─ ── ── 2.50
DIAMOND BIT
1377.8 17.00 ── ── 6 2 ── 66 12 NA 76 NX ── ─ ─ ── ── 2.22
1376.8 18.00 ── ── 2 ── ── 27 ── NA 76 NX ── ─ ─ ── ── 2.50
1375.8 19.00 ── ── 3 2 ── 45 ── NA 76 NX ── ─ ─ ── ── 2.22
1374.8 20.00 Overburden consists of ── ── 2 ── ── 46 ── NA 76 NX ── ─ ─ ── ── 2.00
1373.8 21.00
boulders, cobbles and ── ── 1 ── ── 41 ── NA 76 NX ── ─ ── ── ── 1.67
pebbles of Phyllite, Mica
1372.8 22.00 ── ── ── 1 1 35 15 NA 76 NX ── ─ ── ── ── 1.82
Schist and Gneiss.
1371.8 23.00 ── ── ── 3 ── 34 ── NA 76 NX ── ─ ── ── ── 1.67
1370.8 24.00 ── ── 1 1 ── 41 14 NA 76 NX ── ─ ── ── ── 2.00
Page 54
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No:
02
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI
STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018
DEPTH OF WATER
% OF CORE RECOVERY
TYPE OF CASING
% OF RECOVERY
PENETRATION
in Nos LOSS
RATE cm/min
BILITY
TEST SECTION
ELEVATION
FREQUENCY
TYPE OF BIT
COMPLETE
SPECIAL
75-150mm
DEPTH OF
PARTIAL
LUGEON
10-25mm
25-75mm
FRACTURE
>150mm
<10mm
% OF RQD
HOLE
OBSERVATION
NIL
DESCRIPTION LOG 20 40 60 80 100
LEVEL
NIL NIL
1369.8 25.00 ── ── 1 ── ── 32 ── NA 76 NX ── ─ ─ ── ── 2.00
1368.8 26.00 ── ── 1 ── 1 33 19 NA 76 NX ── ─ ─ ── ── 2.00
1367.8 27.00 Overburden consists of ── ── 7 ── ── 55 ── NA 76 NX ── ─ P ─ ── ── 2.00
1366.8 28.00 boulders, cobbles and ── 1 ── 1 ── 40 ── NA 76 NX ── ─ P ─ ── ── 2.50
1365.8 29.00 pebbles of Phyllite, Mica ── ── 2 ── ── 56 ── NA 76 NX ── ─ P ─ ── ── 2.00
DIAMOND BIT
Schist and Gneiss.
1364.8 30.00 ── ── 2 3 ── 56 ── NA 76 NX ── ─ P ─ ── ── 1.67
1363.8 31.00 ── ── 4 ── ── 60 ── NA 76 NX ── ─ P ─ ── ── 2.00
1362.8 32.00 ── ── 3 2 ── 55 23 NA 76 NX ── ─ P ─ ── ── 1.67
1361.8 33.00 ── ── 2 2 2 95 68 NA 76 NX ── ─ P ─ ── ── 1.67
1360.8 34.00 ── ── 2 3 1 85 40 NA 76 NX ── ─ P ─ ── ── 1.67
1359.8 35.00 Overburden consists of ── ── ── ── 2 93 93 NA 76 NX ── ─ P ─ ── ── 1.53
boulders, cobbles and
1358.8 36.00 ── ── 1 2 2 100 72 NA 76 NX ── ─ P ─ ── ── 1.82
pebbles of Phyllite, Mica
1357.8 37.00 Schist and Gneiss. ── ── ── ── 2 84 84 NA 76 NX ─ P ─ ── ── 1.53
1356.8 38.00 ── ── 5 2 1 88 ── NA 76 NX ─ P ─ ── ── 1.67
1355.8 39.00 ── ── 1 2 2 60 41 NA 76 NX ─ P ─ ── ── 1.82
1354.8 40.00 ── ── 6 3 ── 63 ── NA 76 NX ─ P ─ ── ── 2.00
1353.8 41.00 ── ── 4 ── ── 27 ── NA 76 NX ─ P ─ ── ── 2.50
DIAMOND BIT
1352.8 42.00 ── ── 2 1 ── 30 ── NA 76 NX ─ P ─ ── ── 2.50
1351.8 43.00 Overburden consists of ── ── 4 ── ── 30 ── NA 76 NX ─ P ─ ── ── 2.00
boulders, cobbles and
1350.8 44.00 ── ── 1 3 ── 52 10 NA 76 NX ─ P ─ ── ── 2.00
pebbles of Phyllite, Mica
1349.8 45.00 Schist and Gneiss. ── ── 3 1 ── 37 ── NA 76 NX ── P ─ ── ── 1.82
1348.8 46.00 ── ── 3 ── ── 22 ── NA 76 NX ── P ─ ── ── 2.50
1347.8 47.00 ── ── ── 1 2 62 50 NA 76 NX ── P ─ ── ── 1.67
1346.8 48.00 ── ── 1 1 1 38 19 NA 76 NX ── P ─ ── ── 2.00
Page 55
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No: 03
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
PENETRATION RATE
% OF CORE RECOVERY
in Nos LOSS BILITY
DEPTH OF WATER
DEPTH OF HOLE
TYPE OF CASING
% OF RECOVERY
TEST SECTION
cm/min
ELEVATION
COMPLETE
75-150mm
SPECIAL
PARTIAL
LUGEON
10-25mm
25-75mm
>150mm
FREQUENCY
TYPE OF BIT
<10mm
OBSERVATION
FRACTURE
NIL
% OF RQD
DESCRIPTION LOG 20 40 60 80 100
LEVEL
1345.8 49.00 ── ── 1 ── ── 20 ── NA 76 NX ─ P ─ ── ── 2.00
1344.8 50.00 ── ── ── 1 1 63 63 NA 76 NX ─ P ─ ── ── 2.00
Overburden consists of
1343.8 51.00 boulders, cobbles and ── ── 1 ── 1 30 20 NA 76 NX ─ P ─ ── ── 1.67
DIAMOND BIT
1342.8 52.00 pebbles of Phyllite, Mica ── ── 2 ── ── 27 ── NA 76 NX ─ P ─ ── ── 1.40
1341.8 53.00 Schist and Gneiss. ── ── 2 ── ── 24 ── NA 76 NX ─ P ─ ── ── 1.67
1340.8 54.00 ── ── ── 1 1 40 35 NA 76 NX ─ P ─ ── ── 1.67
1339.8 55.00 ── ── ── ── 2 45 35 NA 76 NX ─ P ─ ── ── 1.42
1338.8 56.00 ── ── 1 ── 1 50 19 NA 76 ─ ─ P ─ ── ── 1.53
1337.8 57.00 Overburden consists of ── ── ── ── ── Wash Sample NIL ── NA 76 ─ ─ P ─ ── ── 1.67
boulders, cobbles and
1336.8 58.00 ── ── ── ── ── Wash Sample NIL ── NA 76 ─ ─ P ─ ── ── 1.67
pebbles of Phyllite, Mica
1335.8 59.00 Schist and Gneiss. ── ── 1 1 ── 40 ── NA 76 ─ ─ P ─ ── ── 1.82
1334.8 60.00 ── ── 1 1 ── 45 ── NA 76 ─ ─ P ─ ── ── 1.67
1333.8 61.00 ── ── 3 ── ── 40 ── NA 76 ─ ─ P ─ ── ── 1.42
1332.8 62.00 ── ── 3 1 ── 40 ── NA 76 ─ ─ P ─ ── ── 1.53
DIAMOND BIT
1331.8 63.00 ── ── 3 ── ── 30 ── NA 76 ─ ─ P ─ ── ── 1.67
1330.8 64.00 ── ── 3 ── ── 30 ── NA 76 ─ ─ P ─ ── ── 1.53
Overburden consists of
1329.8 65.00 boulders, cobbles and ── ── 3 ── ── 35 ── NA 76 ─ ─ P ─ ── ── 2.00
1328.8 66.00 pebbles of Phyllite, Mica ── ── 3 ── ── 30 ── NA 76 ─ ─ P ─ ── ── 1.82
1327.8 67.00 Schist and Gneiss. ── ── 3 1 ── 46 ── NA 76 ─ ─ P ─ ── ── 1.67
1326.8 68.00 ── ── 3 ── ── 40 ── NA 76 ─ ─ P ─ ── ── 2.00
1325.8 69.00 ── ── 2 ── ── 30 ── NA 76 ─ ── P ─ ── ── 1.67
1324.8 70.00 Bedrock Phyllite ── ── ── ── 1 44 32 >15 76 ─ ── P ─ ── ── 2.00
Page 56
NAME OF AGENCY: SPACE ENGINEERS CONSORTIUM (P) LTD.
NAME OF PROJECT: USBRL, J&K
GEOLOGICAL LOG OF DRILL HOLE HOLE No: PIER 05
SHEET No: 04
LOCATION: SUMBER CO-ORDINATE: 3684821.760N ,511142.848 E DEPTH OF HOLE: 78 m
FEATURE: BRIDGE 02 ANGLE WITH HORIZONTAL: 90 Degree TYPE OF BARREL: TRIPLE TUBE
CHAINAGE: 111+359.20 GROUND ELEVATION: 1394.753m LOGGED BY: JAVED GANAI
STARTED: 30.01.2018 COLLAR ELEVATION: 10cm END: 20.03.2018
DEPTH OF WATER
% OF CORE RECOVERY
TYPE OF CASING
% OF RECOVERY
PENETRATION
RATE cm/min
in Nos LOSS BILITY
TEST SECTION
FREQUENCY
ELEVATION
TYPE OF BIT
COMPLETE
SPECIAL
75-150mm
DEPTH OF
PARTIAL
FRACTURE
LUGEON
10-25mm
25-75mm
>150mm
<10mm
% OF RQD
HOLE
OBSERVATION
NIL
DESCRIPTION LOG 20 40 60 80 100
LEVEL
1323.8 71.00 ── ── 3 1 ── 40 ── >15 76 ── ── P ── ── ── 1.67
1322.8 72.00 ── ── 3 1 1 55 17 >15 76 ── ── P ── ── ── 2.00
DIAMOND BIT
1321.8 73.00 Gray coloured, fine to ── ── 4 1 ── 51 ── >15 76 ── ── P ── ── ── 1.67
1320.8 74.00
medium grained, slightly ── ── 5 1 ── 45 ── >15 76 ── ── P ── ── ── 1.42
to moderately weathered,
1319.8 75.00 ── ── 3 1 ── 60 ── >15 76 ── ── P ── ── ── 1.67
foliated Phyllite. Thin
1318.8 76.00 quartz veins are present. ── ── 5 1 ── 66 ── >15 76 ── ── P ── ── ── 1.53
1317.8 77.00 ── ── 4 1 ── 60 10 >15 76 ── ── P ── ── ── 1.42
1316.8 78.00 ── ── 3 3 ── 55 ── >15 76 ── ── P ── ── ── 1.53
Index:
NA= Not Applicable, Overburden=
P= Partial,
C= Complete, Phyllite=
Page 57
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P6
SHEET NO.:
1 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE BR-3 (P6)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 63.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARREL Triple Tube
STARTED : 04.04.2018 COMPLETED 04.05.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
Dry sample contains
angular pebbles of 25
1.000 1.00 Phyllite/Phyllitic Quartzite. - - - - -
35 22
2.000 2.00 5 - - - -
PX
PX
30 20
3.000 3.00 5 - - - -
30 18
4.000 4.00 3 - - - -
30 17
5.000 5.00 Semi angular to 3 - - - -
5
semi rounded 35 15
6.000 6.00 pebbles, cobbles & 6 - - - -
Boulders of
38 17
7.000 7.00
Gneiss, Phyllitic 6 - - - -
Quartzite.
38 20
8.000 8.00 2 - - - -
40 18
9.000 9.00 4 - - - -
50 20
10.000 10.00 4 - - - -
33 17
11.000 11.00 4 - - - -
HX
HX
50 18
12.000 12.00 5 - - - -
38 20
13.000 13.00 1 1 - - -
40 17
14.000 14.00 3 1 - - -
50 22
15.000 15.00 3 1 - - -
41 20
16.000 16.00 - 2 - - -
Semi angular to
semi rounded 42 20
17.000 17.00 2 - - -
IMP (NX Size ) Diamond Core Bit
Fluvio-glacial deposit(Alluvium)
Boulders of
55 17
18.000 18.00 Slate/Phyllite 6 - - -
Not Applicable
Gneiss, Phyllitic
Core Samples
Overburden
Complete
Quartzite & 29 22
19.000 19.00 1 - - -
Quartzite.
32 22
20.000 20.00 - - - -
32 20
21.000 21.00 - 1 - - -
78 20
22.000 22.00 1 2 - - -
100 17
23.000 23.00 - 4 1 - -
82 18
24.000 24.00 3 2 - -
71 15
25.000 25.00 1 1 - -
Semi angular to 60 18
26.000 26.00 2 - - - -
semi rounded
pebbles, cobbles & 46 22
27.000 27.00 Boulders of Gneiss 2 1 - - -
& Phyllitic
NX
NX
50 17
28.000 28.00 interbedded stiff 1 3 - - -
brownish to reddish
clay contains 60 17
29.000 29.00 1 2 - - -
angular pebbles of
Phyllite. 35 15
30.000 30.00 1 - - - -
43 22
31.000 31.00 4 - - - -
Pebbles of Phyllite in silty
sandy matrix.
47 20
32.000 32.00 2 - - - -
46 20
33.000 33.00 3 2 - -
Semi angular to
semi rounded 43 22
34.000 34.00 pebbles, cobbles & 2 - - - -
Boulders of
72 20
35.000 35.00 Slate/Phyllite 5 1 - -
Gneiss, Phyllitic
Quartzite & 98 18
36.000 36.00 2 5 - -
Quartzite.
78 20
37.000 37.00 2 3 - -
Semi angular to semi
rounded Boulders of 85 22
38.000 38.00 Phyllitic Quartzite . 10 1
LOGGED BY : CHECKED BY :
Page 58
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
P6
SHEET NO.:
2 of 2
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE BR-3 (P6)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 63.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARRELTriple Tube
STARTED : 04.04.2018 COMPLETED 04.05.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Fracture Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
Semi angular to semi
rounded Boulders of 56
39.000 39.00 Phyllitic Quartzite. 11 20
Fluvio-glacial deposit(Alluvium)
sandy matrix. 70
42.000 42.00 3 2 17
70
Not Applicable
Overburden
43.000 43.00 2 3 20
68
44.000 44.00 5 1 18
Semi angular to
semi rounded 67
45.000 45.00 3 1 17
pebbles, cobbles
NX
& Boulders of 57
46.000 46.00 1 1 15
Gneiss/Schist,
Phyllitic Quartzite 75
47.000 47.00 7 17
& Quartzite.
60
48.000 48.00 2 1 15
IMP (NX Size ) Diamond Core Bit
81
49.000 49.00 2 3 20
Blocky Blocky 96 11
Over 15
Core Samples.
50.000 50.00 1 4 17
Complete
Joint Plane
NX
0
45 (1) Sm/Pl 81 NIL
51.000 51.00 2 4 & stains 19
Blocky Blocky 93 30
15-8
52.000 52.00 5 14
Blocky Blocky 86 29
53.000 53.00 2 3 1 14
8-5
Blocky Blocky 92 59
54.000 54.00 Dark colored, 3 1 15
blocky slightly
15-8
Blocky Blocky 90 44
55.000 55.00 weathered & 3 1 15
medium strong
Over
15
0
25 (1) Rg/Unl 98 40
57.000 57.00 contain quartz 4 1 & stains 15
veins along
8-5
58.000 58.00 2 3 1 17
as randomly.
Over
15
0
45 (1) Sm/Pl 100 60
60.000 60.00 2 4 1 & stains 15
15-8
Blocky/sheare Blocky/sh
15
d eared
100 16
62.000 62.00 2 5 15
15-8
Phyllite
LOGGED BY : CHECKED BY :
Page 59
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO. P7
SHEET NO.: 1of 2
PROJECT : USBRL Project CHAINAGE:- 111+440.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511174.039E, 3684896.849N FEATURE P7(Br-3)
COLLAR ELEVATION (m) 1402.201 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 61.00
GROUND ELEVATION(m) 1402.101 TYPE(S) OF CORE BARREL Triple Tube
STARTED : 06.04.2018 COMPLETED 26.04.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Size of core Structural Drill Water SPT-Number of
Lithology Ratio Percent Core Recovery (%) Loss Permeability
pieces In No's) Condition Blows
Fracture Frequency / m
Interpreted %age of
Special
Interpreted %age of
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
rock fragments
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
10 to 25 mm interpretations /
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
mm/s OR
Depth (m)
Description
Description
Type of Bit
matrix (fine)
Weathering Grade
LUGEON
(mm/min)
Complete
>150 mm
In figures
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
30 20
1.000 1.00
PX
Sub rounded to
sub angular 35 17
2.000 2.00
pebbles, cobbles
& boulders of 35 17
3.000 3.00 Slate.
3.00
35 15
4.000 4.00
65 18
5.000 5.00
Sub rounded to
sub angular 75 17
Partial
6.000 6.00
pebbles, cobbles
& boulders of 55 17
7.000 7.00 Slate, Quartzite,
Gneiss & 52 15
8.000 8.00 Migmatite.
HX
30 17
9.000 9.00
32 20
10.000 10.00
67 18
11.000 11.00
42 17
12.000 12.00
Sub rounded to 57 17
Fluvio-glacial deposit(Alluvium)
Fluvio-glacial deposit(Alluvium)
Gneiss &
Overburden
Migmatite. 65 Complete 15
15.000 15.00
57 18
16.000 16.00
70 17
17.000 17.00
IMP (Nx size) Diamond Core Bit
40 17
18.000 18.00
Core Samples
69 15
19.000 19.00
77 15
20.000 20.00
Sub rounded to
sub angular 51 20
21.000 21.00
pebbles, cobbles
& boulders of 67 17
22.000 22.00 Gneiss ,Slate
/Phyllite& 67 18
23.000 23.00 Quartzite
53 20
24.000 24.00
54 17
25.000 25.00
60 20
26.000 26.00
NX
Sub rounded to 73 17
27.000 27.00 sub angular
pebbles, cobbles
74 15
28.000 28.00 & boulders of
Partial
76 17
30.000 30.00
Blocky Blocky 97 26 15
31.000 31.00
15-8
Blocky Blocky 79 28 17
32.000 32.00
Greyish colored,
Blocky Blocky 84 33 15
33.000 33.00
blocky, slightly
weathered &
Over
15
37.000 37.00
Page 60
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO. P7
SHEET NO.: 2 of 2
PROJECT : USBRL Project CHAINAGE:- 111+440.8
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- 511174.039E, 3684896.849N FEATURE P7(Br-3)
COLLAR ELEVATION (m) 1402.201 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 61.00
GROUND ELEVATION(m) 1402.101 TYPE(S) OF CORE BARREL Triple Tube
STARTED : 06.04.2018 COMPLETED 26.04.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Size of core Structural Drill Water SPT-Number of
Lithology Ratio Percent Core Recovery (%) Loss Permeability
pieces In No's) Condition Blows
Fracture Frequency / m
Interpreted %age of
Special
Interpreted %age of
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
rock fragments
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
interpretations /
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
mm/s OR
Depth (m)
Description
Description
Type of Bit
matrix (fine)
Weathering Grade
LUGEON
(mm/min)
Complete
>150 mm
In figures
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
Greyish colored, Blocky Blocky 100 17 15
39.000 39.00
PHYLLITIC
QUARTZITE. Blocky Blocky 100 NIL 17
40.000 40.00
Over 15
Very Very
blocky/ blocky/ 95 NIL 18
41.000 41.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 76 NIL 17
42.000 42.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 73 NIL 18
43.000 43.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 86 28 17
15-8
44.000 44.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 70 27 20
45.000 45.00 Greyish colored, Disturbed Disturbe
very blocky, Very Very
blocky/ blocky/ 73 NIL 17
46.000 46.00
slightly Disturbed Disturbe
weathered to Very Very
moderately & blocky/ blocky/ 64 NIL 20
47.000 47.00 Disturbed Disturbe
medium strong Very Very
fine grained
IMP (Nx size) Diamond Core Bit
blocky/ blocky/ 32 NIL 18
48.000 48.00 PHYLLITIC Disturbed Disturbe
Very Very
QUARTZITE blocky/ blocky/ 43 NIL 20
Core Samples
49.000 49.00 contains random Disturbed Disturbe
Complete
Very Very
Quartz veins.
NIL
NX
Over 15
blocky/ blocky/ 77 25 17
50.000 50.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 83 NIL 17
51.000 51.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 80 NIL 15
52.000 52.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 96 NIL 15
53.000 53.00 Disturbed Disturbe
Very Very
blocky/ blocky/ 92 NIL 15
54.000 54.00 Disturbed Disturbe
Blocky - Blocky - 81 10 15
55.000 55.00 massive massive
Phyllitic Quartzite
Page 61
GEOLOGICAL LOG OF DRILL HOLE
HOLE NO.
A2
SHEET NO.:
1 of 1
PROJECT : USBRL Project CHAINAGE:-
BEARING OF HOLE (Degree) Verticle CO-ORDINATES:- FEATURE Br-3(A2)
COLLAR ELEVATION (m) 0.10 cm 90
ANGLE WITH HORIZONTAL(degree) TOTAL DEPTH (m) 27.00
GROUND ELEVATION(m) TYPE(S) OF CORE BARREL Triple Tube
STARTED : 27.04.2018 COMPLETED 01.05.2018 DRILLING AGENCY : SECL Srinagar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Frequency / m
Interpreted %age of
Interpreted %age of
Special
Penetration Rate
Observations and
80.00 - 100.00
75 to 150 mm
20.00 - 39.99
40.00 - 59.99
60.00 - 79.99
rock fragments
10 to 25 mm
25 to 75 mm
Test section
0.00 - 19.99
Size of hole
interpretations /
mm/s OR
Description
Depth (m)
Description
Type of Bit
matrix (fine)
LUGEON
Complete
(mm/min)
>150 mm
In figures
Weathering Grade
< 10 mm
RQD(%)
N-Value
Casing
Partial
15-30
30-45
0-15
Log
Log
Slope Debris
Slope Debris
Overburden
33
1.000 1.00 Angular pebbles & 1 - - - - 22
cobbles of Phyllite..
HX
HX
30
2.000 2.00 3 - - - - 22
Very blocky Very blocky
/disturbed /disturbed
46 NIL
3.000 3.00 6 - - - - 20
Very blocky Very blocky
/disturbed /disturbed
44 NIL
4.000 4.00 5 - - - - 20
Very blocky Very blocky
48 14
Over 15
/disturbed /disturbed
5.000 5.00 4 1 - - - 18
Very blocky Very blocky
/disturbed /disturbed
47 10
6.000 6.00 4 1 - - - 20
Very blocky Very blocky
Dark grey colored, /disturbed /disturbed
52 NIL
7.000 7.00 very blocky slightly 5 1 - - - 18
7
weathered & weak Very blocky Very blocky
/disturbed /disturbed
50 NIL
8.000 8.00 PHYLLITE contains 5 - - - - 17
occasional quartz Joint Plane 45-
15-8
0
veins.. 50 (2) Sm/Pl & 56 27
9.000 9.00 3 2 - - - yellow stains 17
Very blocky Very blocky
/disturbed /disturbed
52 11
10.000 10.00 3 1 - - - 17
Very blocky Very blocky
61 NIL
Over 15
/disturbed /disturbed
11.000 11.00 5 - - - - 15
IMP (NX Size) Diamond Core Bit.
Core Samples
/disturbed /disturbed
13.000 13.00 9 - - - - 17
Partial
Joint Plane
0 0
45 (1) & 35 (1) 94 50
Sm/Pl,Rg/Un &
15-8
14.000 14.00 2 3 1 - - 15
yellow stains
Joint Plane
Uncased
0 0
70 (1) & 40 (1) 95 42
15.000 15.00 6 2 1 - - Sm/Pl,Sm/Un & 15
NX
15-8 Over 15
stains
Joint Plane
0
50 (1) Sm/Un & 95 11
16.000 16.00 11 2 - - - stains 17
Blocky Blocky 95 29
17.000 17.00 9 3 - - - 15
Joint Plane
<1
0
35 (1) Rg/Un & 92 92
18.000 18.00 - 4 - - - stains 15
Blocky Blocky 92 22
19.000 19.00 Dark grey colored, 9 2 - - - 17
blocky to very Joint Plane
0
95 14
Over 15
Blocky Blocky 92 27
15-8
23.000 23.00 3 7 - - - 15
Blocky Blocky 95 26
24.000 24.00 4 5 - - - 15
Over 15
0
45 (1) Rg/Un & 100 60
26.000 26.00 3 3 43 - - stains 15
<1
Phyllite
LOGGED BY : CHECKED BY :
Page 62
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Photographs of Core boxes
BH No P1
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 01 (One)
Depth : 0.00 m o 17.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 03 (Two)
Depth : 17.0m to 27.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 63
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 03 (Three)
Depth : 27.0m to 35.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P1
Bridge No : 03
Box No : 04 (Four)
Depth : 35.0 m to 43.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 64
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P2
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 01 (One)
Depth : 0.00 m to 18.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 02 (Two)
Depth : 18.0m to 27.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 65
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 03 (Three)
Depth : 28.0 m to 32.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 04 (Four)
Depth : 33.0m to 37.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 66
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Project : USBRL Annexure-II
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P2
Bridge No : 03
Box No : 05 (Five)
Depth : 38.0m to 40.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 67
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P3
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 01 (One)
Depth : 0.0m to 11.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 02 (Two)
Depth : 11.0m to 21.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 68
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 03 (Three)
Depth : 21.0 m to 32.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 04 (Four)
Depth : 32.0m to 44.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 69
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 05 (Five)
Depth : 44.0m to 57.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 06 (Six)
Depth : 57.0m to 65.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 70
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P3
Bridge No : 03
Box No : 07 (Seven)
Depth : 65.0m to 73.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 71
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P5
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 01 (One)
Depth : 0.00m to 16.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 02 (Two)
Depth : 16.0m to 26.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 72
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 03 (Three)
Depth : 26.0 m to 34.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 04 (Four)
Depth : 34.0m to 42.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 73
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 05 (Five)
Depth : 42.0m to 54.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 06 (Six)
Depth : 54.0m to 70.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 74
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P5
Bridge No : 03
Box No : 07 (Seven)
Depth : 70.0m to 78.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 75
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P6
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 01 (One)
Depth : 0.0m to 12.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 02 (two)
Depth : 12.0m to 22.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 76
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 03 (Three)
Depth : 22.0m to 30.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 04 (Four)
Depth : 31.0m to 38.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 77
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 05 (Five)
Depth : 38.0m to 46.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 06 (Six)
Depth : 47.0m to 52.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 78
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 06 (Six)
Depth : 53.0m to 57.0 m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P6
Bridge No : 03
Box No : 07 (Seven)
Depth : 58.0m to 63.0 m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 79
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No P7
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 01 (One)
Depth : 0.00m to 10.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 02 (Two)
Depth : 10.0m to 18.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 80
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 03 (Three)
Depth : 18.0m to 25.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 04 (Four)
Depth : 26.0m to 32.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 81
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 05 (Five)
Depth : 33.0m to 37.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 06 (Six)
Depth : 38.0m to 43.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 82
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 07 (Seven)
Depth : 44.0m to 52.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : P7
Bridge No : 03
Box No : 08 (Eight)
Depth : 53.0m to 61.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 83
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
BH No A2
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 01 (One)
Depth : 00.0m to 11.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 02 (Two)
Depth : 11.0m to 17.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 84
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-II
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 04 (Four)
Depth : 24.0m to 27.0m
Project : USBRL
Client : HCC
Agency : Space Engineers Consortium Private Limited
BH No : A2
Bridge No : 03
Box No : 03 (Three)
Depth : 17.0m to 23.0m
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2,P3, P5,P6 ,P7 and Abutment
TO
A2 of bridge No 3 Of Dharam-Qazigund Section Of USBRL Project Jammu And P a g e | 85
Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-III
Sample Calculation
For well dia 8m
For permissible settlement of 25mm and Bf=8m and Bp=1.2m
Sp/Sf=(Bp(Bf+0.3)/Bf(Bp+0.3))2
Sp=(1.2(8+0.3)/8(1.2+0.3))2 x 25
Sp=17.22mm
qa=3.35xCb(N-3)((B+0.3)/2B)2dwdf
dw=0.5+0.5wB/D
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2, P3,P5
TO
P6, ,P7and Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 86
USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-III
Sample Calculation
For well dia 10m
For permissible settlement of 25mm and Bf=10m and Bp=1.2m
Sp/Sf=(Bp(Bf+0.3)/Bf(Bp+0.3))2
Sp=(1.2(10+0.3)/10(1.2+0.3))2 x 25
Sp=16.97mm
Corresponding to settlement of 16.97mm ,a stress of 4.1kg/cm2 is obtained from IS 10042-
1981 Fig 2 . So the qa for 25mm permissible settlement is 41t/m2 .
qa=3.35xCb(N-3)((B+0.3)/2B)2dwdf
dw=0.5+0.5wB/D
w= depth of water table below footing
df=1+Df/B<2
For 20m deep foundation df=1.33
Cb for gravely soil=2
qa=3.35x2x(50-3)(10+0.3/2x10)2x0.5x1.33
qa=55.54t/m2
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2, P3,P5
TO
P6, ,P7and Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 87
USBRL Project Jammu And Kashmir
HCC Limited
Space Engineers Consortium Private Limited
Ist Floor, Alfarooq Building Jawahar Nagar, Srinagar
Annexure-III
For Rocky strata (BH 5)
i) UCS Criteria
Safe bearing pressure
qs= qcNj
Where
qs= safe bearing pressure (gross)
qc = average uniaxial compressive strength of rock cores,
Nj= empirical coefficient depending on the spacing of discontinuities
3 + S/B1
10 √(1+300 δ/S
Classification No I II III IV V
IS – 12070-1987
In instant case
RMR have been taken as 33
Safe bearing pressure = qns= 112.94 t/m2 (say 112t/m2)
SUBMITTED
Geotechnical Investigation Report Of Piers P1, P2, P3,P5
TO
P6, ,P7and Abutment A2 of bridge No 3 Of Dharam-Qazigund Section Of P a g e | 88
USBRL Project Jammu And Kashmir
HCC Limited