Documente Academic
Documente Profesional
Documente Cultură
INFRASTRUCTURES LIMITED
[Formerly Simplex Concrete Piles (India) Limited]
(Quality Construction since 1924)
Welcomes
you
to this presentation
BY
D.N. BASU
TECHNICAL DIRECTOR
SIMPLEX INFRASTRUCTURES LIMITED
2
BUSINESS GROWTH
(In INR Million)
5 0 ,0 0 0
4 5 ,0 0 0
4 0 ,0 0 0
3 5 ,0 0 0
3 0 ,0 0 0
47000
2 5 ,0 0 0
2 0 ,0 0 0
1 5 ,0 0 0
28081
17082
1 0 ,0 0 0
13,427
5,479
6,413
9,990
5 ,0 0 0
0
2002- 2003- 2004- 2005- 2006- 2007- 2008-
2003 2004 2005 2006 2007 2008 2009
3
ORDER BOOKING
Order Book as
on 31.03.09 Amount in Crores
Total
Segment %
Amount
1) UMPP Mundra Civil & Structural works for main Power 5 X 800 MW
House, Boiler and Auxiliaries and other major
off site works.
2) Adani Power Civil & Structural Works, Power Island and 2 X 660 MW
Limited, Ph. III BOP
3) Adani Power Civil & Structural Works for 275 M. high 2 X 660 MW
Limited, Ph. IV Multiflue Chimney
5) TNEB, NCTPS Construction of Piling and Pile Cap for Power 1 X 600 MW
Unit I Stage II Island and Boiler Auxiliary
BHEL PS-SR
6) Maithon Power Civil & Structural Works for Power Island, 2 X 525 MW
5
Limited BOP and Chimney
POWER PLANTS UNDER EXECUTION
15) Hindalco, Renukoot Civil & Structural Works for Power Island 5 X 135 MW
and BOP
16) Sepco III Vedanta, Civil, Structural, Piping and BOP Works for 9 X 135 MW
Orissa Unit 4, 5, 6 & 7
7
Contd……
8
People & Management
People Driven System Driven
Senior
management
1%
Non-technical
29%
Technical
70%
9
Total Manpower Strength ~ 7800 (As on May 2009)
LIST OF CO. OWNED MAJOR MACHINERY
QTY. S. No. MAJOR MACHINE NAME QTY.
S.No. MAJOR MACHINE NAME
1 BATCHING PLANT - LARGE 78 20 PAVER - ASPHALT 3
2 BATCHING PLANT - MINI 18 21 PAVER - CONCRETE 3
3 BITUMIN SPRAYER 5 22 PAVER - WMM 3
4 BOOM PLACER 9 23 PLANT - CRUSHER 11
5 CEMENT SILO 40 24 PLANT - HOT MIX 1
6 CONCRETE PUMP 56 25 PLANT - ICE 3
7 CONVEYOR PLACER 5 26 PLANT - WMM 3
8 CRANE - CRAWLER 32 27 PNEUMATIC ROLLER 2
9 CRANE - GANTRY 9 28 RIG - DRIVEN PILING 68
10 CRANE - GOLLIATH 25 29 RIG - HYDRAULIC 85
11 CRANE - HYDRA 53 30 RIG - MARINE PILLING 13
12 CRANE - TOWER 36 31 RIG - MECHANICAL 3
13 DIESEL GENERATOR - (50 KVA-1000 KVA) 151 32 ROCK BREAKER 5
14 DOZER 7 33 VIBRO COMPACTOR 14
15 EXCAVATOR 14 34 TANDEM ROLLER 12
16 KERB LAYING MACHINE 5 35 TIPPER 61
17 LOADER - BACKHOE 30 36 TRANSIT MIXER 181
18 LOADER - WHEEL 18 37 VIBRO HAMMER 8
19 MOTOR GRADER 7 38 WEIGH BRIDGE 16
10
KUDANKULAM NUCLEAR POWER PLANT 2 X 1000 MW
SIMPLEX SCOPE OF WORK
Simplex Infrastructures Limited was the contractor for Civil
Works comprising of Package -4, Turbine Buildings, Emergency
Power Supply Buildings, 220 KV & 400 KV Switch Yards, Cable &
Piping Tunnels, Fuel Storage Building etc. covering both the Units.
11
2 X 1000 MW KUDANKULAM POWER PROJECT AT
CONSTRUCTION STAGE
12
NTPC SIMHADRI SUPER THERMAL POWER PROJECT
2X500 MW
13
TG DECK AT NTPC SIMHADRI – CONSTRUCTION
STAGE
14
SCOPE OF WORK
JINDAL POWER
Simplex Infrastructures Limited was the contractor for Civil Works
comprising mainly of Power House Building, Mill Building, Circulating
Water System, DMPT Plant, Cooling Tower, Fuel Oil System, Turbine
Buildings, Switch-Yards, and all Auxiliary Buildings Raw Water / Fire Water
Pump House, Air Compressor, Ash Slurry Pump House, Covering Structural
Steel Works for Power House, Turbine & Auxiliary Buildings, Roads &
Drainage Works, Pipe Rack & Cable Rack, Piling Works etc.
15
JSPL POWER PROJECT, RAIGARH, AT
CONSTRUCTION STAGE
16
630 MW CCPP OF NTPC AT GANDHAR, GUJARAT
17
4000 MW UMPP AT MUNDRA FOR CGPL (TATA POWER)
- CONSTRUCTION OF 800 MW TG RAFT
19
PROGRESS PHOTOGRAPHS OF 2 X 525 MW TPP OF MAITHON POWER
20
SUGGESTED APPROACHES FOR ACCELERATED
DEVELOPMENT OF POWER PROJECTS
21
SUGGESTED APPROACHES FOR ACCELERATED
DEVELOPMENT OF POWER PROJECTS
22
SUGGESTED APPROACHES FOR ACCELERATED
DEVELOPMENT OF POWER PROJECTS