Sunteți pe pagina 1din 7

BILL OF ENGINEERING MEASUREMENT AND ESTIMATION (BEME) FOR EXISTING FENCE DEMOLITION

AND CITADEL FENCE INSTALLTION (138.03 LINEAR METERS) WORKS TO COMPLETELY FENCE OFF THE
PAN OCEAN FACILITY AT AMUKPE
S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT
A PRELIMINARIES
1 MOBILIZATION

Allow for contractor to mobilize completely


to site all requisite personnel, equipment
and every other necessity for complete
execution of the job. LOTS L/S 2,000,000
2 CASHES

Allow a provisinal sum for community


Affairs, Safety, Health, Environment and
Security. LOTS L/S 500,000
SUB-TOTAL OF PRELIMINARIES
CARRIED TO SUMMARY PAGE
2,500,000
DEMOLITION OF EXISTING WIRE MESH
3 FENCE

Allow for the provision of tools, equipment,


and personnel for demolition of existing
wire mesh fence including all existing posts
and gates. 138.03 m 2500 345,075

Allow for carting away demolished wire


mesh fence including all existing posts and
gates to Pan Ocean specified location. 138.03 m 3000 414,090
SUMMARY FOR DEMOLITION
WORKS
759,165
PROCUREMENT OF CITADEL
FENCE MATERIALS AND
ACCESSORIES
B

PROVISION OF CITADEL FENCE MATERIALS


4 AND ALL ASSOCIATED ACCESSORIES
Allow a provisional sum for purchase and
delivery to site of all citadel fence materials
and accessories required for the complete
execution of the job.
N/B:
1) Make provision for 1 nos
(one) double leaf swing vehicular gate and
2 nos (two) single leaf swing gates
installation with all accessories along fence
route as will be directed by client
supervising engineer.
2) Concertina wires to be installed at
all sections on top of citadel fence . 138.03 m 180000 24,845,400
SUMMARY FOR PROCUREMENT
OF CITADEL FENCE MATERIALS
AND ACCESSORIES CARRIED TO
SUMMARY PAGE 24,845,400
C CIVIL JOBS

BUSH CLEARING AT SOME POINTS ALONG


5 FENCE ROUTE
Clear bushes along citaden fence route
prior to excavation works 138.03 m 500 69,015
EXCAVATION WORKS FOR CITADEL FENCE
6 GROUND BEAM

Excavate trench 900mm wide, 400mm


deep.
N/B:
1) Increase depth of
excavation at post positions for firmness
and rigidity not exceeding 1m, but bearing
in mind that the final height of fence shall
be 3m above existing ground level.
49.69 m3 1,600 79,504

7 COMPACTION OF EXCAVATED TRENCHES

Carryout adequate compaction of all


excavated trenches 55.21 m2 500 27,605
8 BLINDING

Place in-situ C15 concrete as blinding on


compacted treneches as blinding in
accordance with BS 8110. 6.20 m3 25,000 155,000

CARPENTRY FORMWORK CONSTRUCTION


9 AND REMOVAL

Construct (and remove after casting)


carpentry formworks with adequate
bracing to receive citade fence ground
beams. 111 m2 3,720 412,920
REINFORCEMENT WORKS FOR GROUND
10 BEAM
Provide High Tensile bar reinforcement (Y12) in
straight and bent bars including anneated tying
wires to BS 4449
1,067 kg 295 314,765

CONCRETE CASTING OF GROUND BEAMS


11 FOR CITADEL FENCE

On completeion of joint pre-inspection


with the Supervising engineer and signing
off of pre-concrete work checklist, place
vibrated in-situ C30 concrete with
adequate compaction for the citadel
ground beam in conformity with BS 8110-
1;1997. N/B:
1) Ensure
creation of 25mm wide by 75mm
deepgroove at the centre of concrete to
embed fence material in ground beam.
24.85 m3 35,000 869,750
12 QUALITY ASSURANCE AND CONTROL

Allow a provisional sum for quality


assurance tests in conformity with BS 1337.
for in-situ concrete cube samples to be
collected for Compressive strength
laboratory test and results submitted for
proper documentation. 1 L/S 500,000
INSTALLATION OF CITADEL FENCE TO RUN
13 ALONG EXISTING ROAD DRAIN

Install citadel fence materials on reinforced


concrete beams with all accessoroes sofit
and one (1 nos) double swing vehicular
gate as shown on the drawing and to the
satisfaction of Pan Ocean supervising
engineer. 138.03 m 10,000 1,380,300
14 BACKFILLING

Backfill all excavated trenches after


installation of citadel fence material 24.84 m3 700 17,388
SUB-TOTAL OF CIVIL JOBS
CARRIED TO SUMMARY PAGE
3,826,247
15 SITE CLEANUP AND DEMOBILIZATION
Clear site completely of all generated
debris to the satisfaction of client site
Supervisors and demobilize completely all
personnel and equipment(s) from site. LOTS L/S 500,000
SUB-TOTAL OF SITE CLEANUP
AND DEMOBILIZATION CARRIED
TO SUMMARY PAGE
500,000

TOTAL 32,430,812

SUMMARY PAGE
S/N ITEM DESCRIPTION AMOUNT
1 PRELIMINARIES 2,500,000
2 DEMOLITION WORKS 759,165
PROCUREMENT OF CITADEL FENCE
3 MATERIALS AND ACCESSORIES 24,845,400
4 CIVIL JOBS 3,826,247

5 SITE CLEANUP AND DEMOBILIZATION 500,000


TOTAL 32,430,812

AMOUNT IN WORDS (#) ____________________________________________

______________________________________________________________________________
___________

S-ar putea să vă placă și