Sunteți pe pagina 1din 1

CONTRACTING FOR CAPITAL PROJECTS AACE INTERNATIONAL

• Delays—Delay is a term of art in that there are numerous as a result.


ways to define the term. In the broadest sense, a delay
may be defined as any event that causes the project to • Damages—The work costs more and/or takes longer
complete later than planned and beyond the current con- than planned.
tract completion date. Most contracts identify and deal
with four generic causes of delay—owner, contractor, The burden of proof of all three elements of a claim rests
third-party and concurrent delay. Many contracts also squarely on the shoulders of the party making the claim. That
deal, in general terms, with seven types of delay—float is, the claimant bears the burden of affirmatively proving all
consumption, inexcusable, excusable, compensable, con- three elements of the claim based upon a preponderance of the
current, pacing, and early completion delays [2]. evidence. To successfully recover in a claim situation, the
claimant must document and prove all three parts before
• Acceleration – Acceleration is a directive from the owner becoming eligible to recover any damages at all. Thus, notice
to the contractor to complete work earlier than required of claim, clear documentation of facts (including both liability
under the contract or earlier than scheduled. and causation), and concise tracking of damages (both cost
and time) are a necessary prerequisite to a successful claim.
• Constructive Acceleration—This is an inadvertent
owner action or failure to act, which results in a contrac- Dispute Resolution
tor being required to complete work earlier than A contract traditionally includes a disputes clause. This is the
required under the contract and causes a cost impact. clause that details, to a greater or lesser degree, the process by
For example, issuing change orders while refusing to which all contract disputes will be prosecuted. While there are
examine delay related issues may bring about construc- numerous variations on the theme, there are four basic meth-
tive acceleration. ods of resolving disputes on project, as follows.

• Termination for Convenience—This is an action on the • Negotiation—Face-to-face negotiation may be accom-


part of the owner to end, in whole or in part, the work of plished in the field between project teams or elevated in
the contract prior to completion through no fault of the both the owner’s and the contractor’s organizations. In
contractor. either case, the concept is for the project participants to
discuss the disputed issue and mutually arrive at an
• Termination for Default—This is an action to end the acceptable business solution to the problem. Outsiders
work of the contract prior to completion due to a materi- are rarely involved in negotiation. The process and the
al breach of the contract. Failing to mobilized to the site outcome are entirely under the control of the parties to
to commence work after the notice to proceed was issued the dispute and the outcome is confidential.
constitutes such a material breach, for example.
• Mediation—Mediation is a form of a structured negotia-
For each of the above eleven types of claims there are a myr- tion between the parties utilizing the services of an out-
iad of rules and case law. Each particular situation is quite side, neutral facilitator—the mediator. It is a voluntary
fact-intensive and is highly dependent upon the exact word- submission of the dispute to a process, which is largely
ing of the contract clause being relied upon. Additionally, controlled by the parties. The mediator’s only power is
there is normally written notice requirement, which must be the power of persuasion, and the mediator’s role is gen-
fulfilled or the contractor may risk losing their legal right to erally to help bring the parties closer together until
an equitable adjustment. It is, therefore, important for a cost agreement on a solution can be reached. The parties, not
engineer to study the field of claims to learn the basics of the mediator, control both the process and the outcome
each type of claim and then examine carefully the terms and of the mediation.
conditions of each contract.
• Arbitration—Arbitration is a more formalized and legal-
The basic equation of a successful claim is summarized below: istic proceeding, whereby the dispute is heard by an out-
side organization typically operating under a national or
• Liability—An event or circumstance has occurred dur- international set of rules, such as the American
ing project performance, which gives rise to a legal right Arbitration Association (AAA), the Judicial Arbitration
to an adjustment to the contract. For example, a change, and Mediation Service (JAMS), or the International
delay or differing condition. Chamber of Commerce (ICC). There may be a single
arbitrator or a panel appointed by one of these organiza-
• Causation – The event or circumstance causes something tions. Formal hearings are generally held with testimony,
which otherwise would not occur. For example some examination, cross examination, submittal of evidence,
portion of the work is revised and performed differently etc. At the end of the hearing(s) the arbitrator “rules” on
than originally planned and work has to be resequenced the outcome of the dispute. In most arbitration proceed-

25.16

S-ar putea să vă placă și