Sunteți pe pagina 1din 1

No Damage for Delay Many contracts contain a clause of the suspension order is something for which the con

limiting a contractor’s recovery for any and all delays to tractor is responsible (i.e., unsafe work conditions, work
a time extension only, no delay damage costs. While not in compliance with contract requirements, etc.) no
some states have adopted statutes precluding no damage recovery of time or cost is allowed.
for delay clauses in public works contract, others strictly
enforce such clauses provided they are clearly written • Termination—Almost all contracts have a provision
and the delay involved should have been within the con- allowing the owner to end, in whole or in part, perform-
templation of the parties at the time of contract execution ance of the work prior to project completion. There are,
(owner review of contractor submittals, for example). typically, two types of termination: termination for con-
venience and termination for default. Termination for
• Order of Precedence –Contracts often recognize that the convenience usually occurs when a project owner
potential for conflicting provisions in a contract is fairly decides, for their own reasons, not to complete the proj-
high. Accordingly, most contracts contain an order of ect as designed. Such situations might arise if the
precedence clause, intended to provide guidance to both owner’s needs change, if project financing fails, or if the
the owner and the contractor in the event of conflicting underlying project economics change substantially. In
provisions. Typically, specifications have precedence such a circumstance, the owner may elect to terminate
over drawings, details over general, special provisions the contractor’s performance for the convenience of the
over general provisions, and so on and so forth. The owner and pay off the contractor in accordance with the
legal concept is to provide guidance to people on projects terms of the clause. Termination for default arises only
in the event there are two or more conflicting provisions when a contractor is found to be in material breach of the
relating to a topic. contract, has been provided with a cure notice from the
owner outlining the material breach, and has failed to
• Owner Responsibilities—Similar to a contractor remedy the breach in a timely manner. (For example, fail-
responsibility clause, an owner responsibility clause ing to man the project in such a manner as to assure time-
ordinarily sets forth the obligations of the project owner, ly project completion.) Usually the owner will terminate
including adequate project financing, all required and the contractor from the project and call upon the con-
necessary permits, appropriate site access, etc. tractor’s financial guarantees to complete the work (i.e.,
letter of credit or surety bond). Some contracts also pro-
• Payments—This is a key contract clause in terms of proj- vide a contractor the right to terminate their participa-
ect cash flow. This clause sets forth how often the con- tion in a project. Under certain carefully proscribed cir-
tractor is to be paid, in what manner, and what are the cumstances (such as, failure to make payments, bank-
conditions precedent to the issuance of payment. ruptcy of the owner, suspension of work for more than a
defined period of time, etc.) the contractor is allowed to
• Quantity Variations—Many contracts contain estimated terminate their own involvement in the project.
quantities to be installed. In the event as-bid quantity • Time of the Essence/Time of Performance—If project
estimates vary substantially (+/- 10 percent or more) completion by a time or date certain is important to an
many contracts (both unit price and lump sum) contain owner, then they must say so in the contract. As timely
a quantity variation clause which allows either the project completion is normally important, most contracts
owner or the contractor to request a redetermination of contain a clause stating that “Time is of the essence of this
the as-bid unit price on affected portions of the work. contract.” Such a clause must be included to make enforce-
able a time of performance clause and collection of late
• Schedules—A schedule clause typically sets forth the completion damages. Absent such a clause, the time of
requirements for contractor scheduling, including for- project completion is considered unenforceable. The time
mat (bar chart vs. CPM), level of detail, submittal of performance clause, typically expressed either in work
requirements, frequency of schedule updating, damages or calendar days after issuance of the notice to proceed,
for failure to submit, delay or time extension analysis sets forth when the work must be completed and the con-

S-ar putea să vă placă și