Thierry Buhagiar
Smart Substation Project Manager
GRID+STORAGE 25/11/15
The Flow of Energy: a European Concern
The Flow of Energy – also a Local Concern
Producers
Consumers
Challenge
• Refurbishment of existing protection & control system for two large
substations (10 Bays 225 kV, 12 Bays 90 kV)
• Innovative solutions bringing new functionality, complete
substation digitizing (electrical, mechanical, environmental data)
• Manage redundancy, move away from hardwiring
• Manage inter-substation automation
Solution
• Full DCS and protection system (DS Agile), process bus 1Gb/s
• Condition monitoring, real time situational awareness
• Wide Area Control Scheme, security system
• COSI-CT + COSI-VT
Key benefits
• Minimized outage time, improved equipment availability
• Increased safety, prevent cyber-security attacks
• Improved inter-changeability, enhanced flexibility and grid operability
• Increased reliability with inherent system redundancy
• Optimized maintenance, remote substation monitoring
• Reduced relay footprint 80 TE -> 40 TE, for smaller panels
What’s New at Blocaux? Detailed View
70 km
• + 12 substations
Poste raccordé au réseau
• 1000 MW RES (80 horizontal
windfarms)
• 600 MW max Extended
consumption
90 km
• 21 OHL (500 km)
• Distant mixed
104/61850 gateways
with local automation
and emergency
Smartsubstatio
restoration capacities
French perspectives for RES integration in 2020
Building permits for wind farms
A HIGH DENSITY WIND FARMS AREA
OVERLOAD RISK
Démonstrateurs PI
Wind and power correlation
14
12
10
valeur
8
moyenne 1h
en m/s
12
14
10
12
valeur
8
moyenne 1h
10 en m/s
6
valeur
8
moyenne 1h
en m/s
4
6
2
4
2 0
0
Wind influence on ampacity
Amp.
2800
2600
2400
2200
2000
1800
1600
1400
1200
1000
800
10 9
8
7 800 900 1000
6 700
5 600
4 500
3 400
m/s 300
2 200
1 W/m2
100
0
DLR simulations on BLOCAUX AREA
180
150%
160
140
100%
120
100 50%
80
0%
60 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
40
-50%
20
0 -100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
AraiL41Argoe AraiL41Croi5 BlocaL41Croi5 ArgoeL61Bloca AlleuL41Bloca AlleuL42ZFoui
AraiL41Argoe AraiL41Croi5 BlocaL41Croi5 ArgoeL61Bloca AlleuL41Bloca AlleuL42ZFoui BlocaL41Fouil BlocaL42ZFOUI ArgoeL61BXCH5 BlocaL41BZBEL BXCH5L41BZBEL BXCH5L41SAUCO
BlocaL41Fouil BlocaL42ZFOUI ArgoeL61BXCH5 BlocaL41BZBEL BXCH5L41BZBEL BXCH5L41SAUCO BXCH5L42TREPO BXCH5L41ZNEUF NEUF5L41ZNEUF Neuf5L42ZAUMA SAUCOL41TREPO AUMALL41BLOCA
RTE develops its own DLR system including the congestion management
tools and risk mitigation without any sensor on the cables
Congestion management
• Today :
−maintaining all the interconnections inside the perimeter is
highly risky by windy days (N-1 probability high and load
transfer on 90 kV needs a fast response in a time not
compatible with scada abilities)
−Clustering the area is the only solution to avoid the risk and
guarantee the security for electrical risk -> weakened grid
resilience (N-1 not guaranteed, shutdown for the cluster,
consumers and producers are impacted)
• Tomorrow :
−Local tools for fast response : acceptable duration
estimation, load flow for topology optimisation, «surgical »
load shedding plan activation and emergency shutdown
tools, potentially storage management (not market oriented)
−Interconnections maintained all the time, no need to
anticipate de N-1, the system does it in real time
Poste Intelligent Conclusion