TABLE OF CONTENTS
1.1 Overview
With growing network building demands, Addition of wireless access NEs in various scenarios is
required. Common scenarios include:
IPGB
RPU
RPU
IT Network
(one or more
iBSC switch/router) SGSN
Purpose
Operations
Purpose
To verify that the target SGSN is reachable from BSC. All IP LINK is normal
ADD LAI
Add RAI
Add NSE
Format:
ADD NSE :NSEI=2101,BEARMODE="IP",NSVCMODE="Static",VPNID=20,T10TIMER=6,NAME="BSC";
Format:
ADD REMOTE ENDPOINT:NSEI=2101,IPADDR=10.69.XXX.XXX,PORT=32768,SIGWEIGHT=10,
DATAWEIGHT=10,ENDPOINTID=9;
Add IP NSVC
After the Completion of all Configuration Part the Data have to be saved for that use below
Command:
SYN;
3 After-Creation Observation
In Performance Statistics, observe resource usage, compare it with the usage before
the operation, and evaluate whether the operation has any impact during busy hours.
Analyze the alarms and notifications after the operation; compare them with the
alarms and notifications produced before the cutover. Pay attention to abnormal
alarms and notifications, analyze the reasons, and handle them immediately.
Observe the operational status of each board, and check whether it is abnormal. If a
board is abnormal, replace it to eliminate the potential risks.
If the cutover operation involves charging changes or affects CDR generation, ask the
charging side for assistance before performing the operation. After the operation,
check immediately whether CDR generation and sorting is still normal.
If the cutover operation involves the superior network management system’s data
gathering or reporting, ask the superior network management side for assistance
before performing the operation. After the operation, ask the superior network
management side to verify that it is still normal.
After the operation, analyze the signaling traced in the service tests and failure
observation information, and handle abnormal cases immediately.
Verify that the operational status of each NE is consistent with the status shown in the rack
chart.