Documente Academic
Documente Profesional
Documente Cultură
Works Department
Oflice Memorandum
To facilitate uninterrupted construction of bridge work / fly over during continuous rain fall in
Rainy season, it was felt necessary to adopt new item of Analysis of Rates of 'PSC M-40 Grade
in Girder & RCC M-40 Grade in Deck Slab / Cross girder/diaphragm of PSC Girder & RCC Deck
Slab composite structure" in the Schedule of Rates-2006 for 2014. After careful consideration
Government have been pleased to approve supporting Analysis of Rates of PSC M-40 Grade in
Girder at Rs.22,682.93 / Cum & RCC M-40 Grade in Deck Slab at Rs.1 0,345.00 / Cum for Bridge
Works item at Sl. No.14 to15 respectively placed in Chapter-XXll of Analysis of Rates- 2006 for
20'14 and addendum to Chapter-XXlllof Bridge Works as ilem at Sl. No.14 & 15 respectively.
1. The new Analysis of Rates of PSC M-40 Grade in Girder & RCC M-40 Grade in Deck Slab
and Schedule of Rates-2006 tor 2014 is effective from the date of issue of this Office
Memorandum and it will be available in web-site of State Government.
2. To arive at the rate for Analysis of Rates of "M-40 PSC Girder & RCC M-40 Grade in Deck
Slab, the guidelines as laid down in Analysis of Rates- 2006 and supporting new Analysis of
Rates for Bridge Works at item under Sl. No.14 to15 placed in Chapter-Xxll of Analysis of
Rates- 2006 will be followed.
3. This has been concurred in by the Finance Deoartment vide their U.O.R. No.92-WF-l
Dt.18.4.2015.
Encl: As above
6+Ay'.g-7
EIC - cum- Secretary to Government
MemoNo. to\LtF ^/|/,dated,
\L 4'\S
Copy with enclosure forwarded to P. S. to Hon'ble Chief Minister, Odisha for information
and necessary action- \'\
%L--ek1Vi;t >-at,
FA - cum- Addl. Secretant t'o Government
Memo No. \ olL\ 1 AN,dated, \\ , 1,ig
Copy with enclosure forwarded to OSD to Chief Secretary, Odisha i P.S. to Developmenl
Commissioner-cum-Additional Chief Secretary, Odisha for information and necessary action.
*Wtls/*rr
FA - cum- Addl. Secretarv to Government
(P.r.o.)
-z-
Memo No. t o-+So rw,dated, \\' q,l(
Copy with enclosure forwarded to All Departments / Managing Director, OB & CC Ltd.,
Bhubaneswar / Managing Director, OCC Ltd., Bhubaneswar for information and necessary
action.
FA-cum- ooo,.ffi#"i{^.n
Memo No. \ D-'-S I Alv,dated, \\' Q. r_f
Copy with enclosure foruarded to EIC (Civil), Odisha / All Chief Engineers, Odisha / All
Superintending Engineers / All Executive Engineers (under Works Department) for information
and wide circulation among subordinate offices.
FA - cum- G6#et'8"fr""t
Memo No. 1 o-yS\ /W, dated, \\ '' a 't5 ^ddt.
Copy with enclosure forwarded to the Accountant General (A&E), Odisha, Bhubaneswar /
Accountant General, Odisha, Puri Branch, Puri for information and necessary action.
No. \ olr5S
ra -
"r - aaars""*?Yr^,(l(oelk!k"n
Memo nltl,dated, \\. a.)-f
Copy with enclosure forwarded to the Luminous Infoways Pvt. Ltd., N-6 / 373, Jaydev
Vihar, Bhubaneswar email: support @ lipl.in for information and necessary action.
They are requested to display it in the web-site of State Government.
*^2^'L*
FA - cum- Addi s""ra.{r4(8,i!rn .nt
MemoNo. \olryf M,dated, \\. a.tg
Copy with enclosure forwarded to A,/C-l Section / A,/C-ll Section / Road Section / Plan
Section / Building Section / Budget Section i N.Hs. Section / FC & AA Section / PPP Cell / EAP
Cell, Works Department for information and necessary action.
Addendum to Chapter XXIV of Bridqe Work of Schedule of Rates-2006 for 2014 as ltem-14 & 15.
PSC Girder M-40 & RCC M-40 in Deck Slab / Cross cirder/Diaphraqm
(PSC Girder & RCC Deck Slab Composite Superstructure Span-30.630 Mtr c/c piers)
14- P.S.C. M-40 Grade in girders including cost of all 1 Cum Rate to be derived
materaals, labour charges for machineries, T&P, as per Analysis of
centering and shuttering, charges towards casting yard, Rate.
casting bed, roads for lifting and launching of the
girders including charges towards providing cranes,
vehicle with trailer for lifting and to support the erection of
girder for launching and placement at the required height
and position including all chargers for arrangement for
movement of cranes, trailers of required nos. and
capacity complete but excluding cost and labour for
M.S. reinforcement, H.T. steel, wire/ strand, sheathing,
Bearing plale, Tube 'units', wedges etc. accessories,
charges towards stressing and grouting, hire chargers of
Jack and other equipment required for stressing and
grouting.
(Analysis is based on the (i) analysis for PSC M-40
grade concrete as per Data book P-483 and (ii) for other
items such as centering, shuttering, charges, towards
casting yard, casting bed, lifting and launching of girder
by crane etc. as per actual practice followed for similar
works).
15- RCC M-40 grade in Deck slab/Cross girder/ diaphragm 1 Cum Rate to be derived
including cost of all materials, labour, charges for as per Analysis of
machinery, T&P charges for suspended type staging/ Rate.
centering and shuttering, supported on girders with M.S.
bracket arrangement for cantilever portion including
charges for all materials and labour for centering
shuttering etc. complete.
(Analysis is based on the (i) Analysis for RCC M40
grade concrete as per Data book P483 and (ii) for other
items such as centering, shuttering charges etc. as per
actual practice followed for similar works).
Addendum to Chapter-XXII of Bridge Work of Schedule of Rate 2006for2014 as item 14& 15
Analysis of rate for M-40 in PSC Girder and RCC-M-40 in Deck SlabiCross girder/diaphragm
PSC Girder & RCC Deck Slab composite Superstructure ( Span - 30.630Mtr c/c of piers)
SI Description UNIT QNTY RATE AMOUNT Remarks
Unit=CUM
Taking Output:l20CUM
a) Maferial As per Data book page-483
Cement MT 51.q 6s40 377464.00
Coarse Sand Cum 54 55 29'10.00
20 mm aggregate Cum 64.8, 1!30 73224.00
l0 mm aggregate Cum 43.2, 1150 49680.00
Admixture @,0.4% of Cement Kg 206.4 r00 20640.00
b) Labour As per Data book page-483
Mate day 0.94 170 159.80
Mason day 3.s 205 717.50
Mazdoor day 20 150 3000.00
c) Machinery As per Data book page-483
Batching plant (assuming output 20 cum / hr) hour 6 1200 ':200'00
Generator 125 KVA hogr 6 905 s430.00
Loader hour 6 520 3120.00
Transit Mixer (Capacity 4.0 cum)
Lead upto 1 Km hour 15 600 9000.00
Lead beyond lKm , L- 2+ p&m 0.5km:2.5km in Km t. tm 300 5 1500.00
Concrete Pump hour 6 165 990.00
P-1
JI Description UNIT QNTY RATE AMOUNT Remarks
Cement
Coarse Sand
20 mm aggregate
10 mm aggregate
fl Add Royalty (to be provided as per prevailing rate)
Coarse Sand Cum
20 mm aggregate Cum
l0 mm aggregate Cum
592359.60
Total cost per cum without Centering & Shuttering Cum 4936.33 (A)
=592359.60/120 cum
B) Add towards charges for centering & shuttering as
per details in enclosed sheets (Annexure -I)
Cost Dercum Cum 3539.81 (B)
@ 6.691 Sqm /Cum
:Rs.3539.81
@ Rs.529.0-l/sqm
C) Cost per Cum chargeble to PSC girder towards
casting yard,casting bed , approach road, service
road for movement of crane,vehicle with trailor etc. for
lifting, shifting and launching of girders.
as per details in enclosed sheets (AnnexureJl)
3940.88+1604.1l:5544.99 Cum ss44.ee (c )
D) Charges towards cranes, vehicle with trailers etc. for
lifting of girders from casting yard, bed, shifting to site
, launching/ elevating the same and placing in position
with all care etc. complete . i.e transportation of Girder
by HYD axle cranes vehicle with trailers of required
nos and capacify for lifting and to support for
erection of each Girder for placement at the elevated
required height and position @ Rs.2750 per MT
( Prevailing market rate including all eharges i.e.
charges of transportation of cranes,vehicle with
trailers to site , charges to complete the work as above
at site etc. complete)@ 2.50MT/Cum
DA
Annexure- I
PSC Girder & RCC Deck Slab composite SupeBtructure ( Span - 30.630Mtr c/c ofpiers)
Detaifed Analysis for Centering and Shuttering of PSC Giruler (1 No,) to be casted at casting yard.
Length of the C irder 29.1 60Mtr ( For span of 30.630Mtr C/C)
l48.2l2sqm 7836.48 kg
Deduct Channel portion -
2X29.16X0.10=5.83
2 X 0.55 X 0.10 - 0.1|
4 X 29.16 X 0.10 = il.66
I oral = 17.604
Net = 148.212-17.60a- 130.608 @ 60.00
kg/sqm
iv) ISMC 100 x 50 mm (middle & top channeL)
Charges to\ ards steel material cost for once use 1s8.80 (a)
per sqm. 23535.40 /148.212
b) Consumables
Charged towards consumables etc for once use 20.24 (b)
per sqm approx. Rs.3000.00 per girder
Charges per Sqm = 3000.00/148.212
6.691 Sqm
Centering and shuttering area ofgirder per cum
142.914
P-6
Annexure-II
Analysis for casting yard bed, approach road for shifting and launching ofgirders
( for 45nos of girder of 29.16Mtr) each.
P-7
sl. Itme of work UNIT QNTY RATE AMOUNT
No
i----.i- --------..----
i iii) iProviding 250mm Moorum sub base - 433t25
i " '-:iApproach road -500 Xl5X 0.25m
-'-'-' '-' -.' -
i -
i iConsideringtheuseoftheroad,TDYoofthecostofthe : :
_'- _'_
"'_ i -_ - - _ _ - "'_'_ -'i ----------- -l- ----------:-
i iCo.t chargeble to Deck stab percum= i i
724.32
:2202562.50x0.30/15x60.817/cum i
P-8
AnnExure-lll
PSC Girder & RCC Deck Slab composite Superstructure ( Span - 30.630Mtr c/c of piers)
Detailed Analysis for Centering and Shuttering of RCC Deck Slab/Cross girder/Diaphragm (
Suspended type i.e. Centerinq & Shutterinq supoorted on Girder and bracketes for Cantilever
c) Hire & Running charges of Diesel welding 8 nour 8l .00 648.00 (c)
set @ 2 hour per day for 4 days : 8 hour @ 8l
Notes:-
Shuttering / Centering area
265.93
Cross
2X5X1.90X0.275 5.20 Sqm
195.97 Sqm
Quantity ofConcrete per Span = 50.494 Sqm
Rate Centering Shuttering area per Cum =
195.94 / 50.494=3.90 Sqm/ Cum
Cross Girder Area
Note lf
the concrele quantity and shuttering area of cross girders/diaphragm are considered along with
deck slab,then the centering/shuttering area is found to be 4.'16 sqm/cum. So on lesser side i.e
3.90 sqm/cum has been considered as the shuttering area of deck slab per cum)
P-12
PSC Girder & RCC Deck Slab composite Superstructure ( Span - 30.630Mtr c/c of piers)
High tensile steel wires/strands including all accessories for stressing, stressing operations
and erouting complete as per drawine and Technical Specifications
AJd 0.50 per celt co\t ol rnalerial tbr Spacers. t32.893 t32.89
lnsulation tape and miscellaneous items
b) Labour
i) For making and fixing cables. anchorages
Mate day 0.t6 170.00 27.20
Blacksmith day 1.00 190.00 190.00
Mazdoor day j.00 150.00 450.00
ii) For prestressing
Mate/Supcrvisor oay 0.05 1t0.00 8.50
c) Machin€ry
(a+b+c) 2890.t7
Yts
Sr No Ref. to Description Rate Rs Cost Rs
lttr",n
of Data MoRTH
Istno Book Spec.
I
l r 6566.09
sa! 116566.10
P-14
Item Sr No Ref. to Description Unit Quanti Rate Rs Cost Rs
SI of MoRT ty
No Data H Spec.
Loosening, leveling and compacting original
ground supporting embankment to facilitate
plac€ment of First layer of embankment ,
scarified to adepth of 150 mm, mixed with
water at OIUC and then compacted by rolling
so as to {chieve minimum dry dcnsit} .,..
a) Labour
Masson 2nd class citcfl 0.180 t90.00 34.20
Mulia unslillid eacn 3.90 150.00 585.00
619.20.
b) Material
ctushcl brokcn granitc stonc icnr sizc Cunl 0.96 829.00 '795.84
P-15
Cement concrete (l:2:4) with l2mm size hard
granite metal per I cum
{) Labour
Masson 2nd class cach 0.500 r90.00 95.00
l\'lolia unskilled each t.40 t50.00 210.00
305.00
b) lUaterial
(lrushcr brokcn grrnile stonc l2rl1m sizc Curn I 150.00 1035.00
0.900
Sald (\cr!('ncd & \ra.hcd) Clun) 55.00 24.75
0 45
Ccl)rcnl Qntl 323 65.1.00 2l12.42
3t't2.t7
c) Overhead charges @ 7.570 on (a+b) 260.79
#t"l'-
P- I6
Providing & laying good quality of
moorum in sub-base in layers not
exceding 22.5 cm watering and compaction
including hire and running charges of PRR
etc. complete.
'7
Cost lor 100 cum 41't .50
sa! 7491.70
I cum 74.92 (A)
P-t7
Compacting & watering upto OMC & rolling
with PRR incl[ding hire and running charges
I trrt r ultl
'lultilrg oulpul 100 dtt !
hire and running charges ofPRR (425 cum lhr l-88 2lo An $*a
per day )
costofwater with an avg lead 5 km (5 tips of cum 1.28 1380 1166.4
uatcr requrre for 390 cum earth)
labour required for sprinkling water for 390 cum 12.8 t50 t920
= 50 Nos.
432i.i2 (a)
b) Overhead charges @ 7.5o/o on (a) 324.28
P- I8
"4
,i
ql
' {1r
'lli
't,
I
€