Documente Academic
Documente Profesional
Documente Cultură
Short and ground all the cable cores/phases at one side or if armor cable than short all the cable
cores with sheath at one side.
Test Equipment
Multi meter with connection leads.
Preparation
Procedure
Procedure
Procedure
Acceptable criteria
o IR value must be >100MΩ.
o AC Hi pot test no break down or tripping of set.
Procedure
Select the multi meter on continuity and measure the continuity buzzer sound will also come if
sheath continuity OK.
If testing with megger due to long length of cable inject 1kV and measure insulation resistance which
must be zero.
(2) Sheath insulation resistance test.
Purpose
Procedure
Switch ON the megger and inject 1kV for 01 minute sheath to ground.
Note the reading of IR and correct at 20°C.
Acceptable criteria
o IR value must be >10MΩ.
180
Procedure
Select the multi meter on continuity and measure the continuity buzzer sound will also come if
sheath continuity OK.
181
If testing with megger due to long length of cable inject 1kV and measure insulation resistance which
must be zero.
Similarly measure the continuity and phasing of Y and B phases.
Sample test record
R OK OK
185 sq-mm
Y OK OK
Single
B OK OK
Switch ON the megger and inject 5kV for 01 minute main conductor to ground.
Note the reading of IR and correct at 20°C.
After HI POT test again perform IR test of same cable.
Similarly measure the IR value of other phases.
Note
o If cable is three core than insulation test between phases R-Y,Y-B and Y-R should be also performed.
Acceptable criteria
IR value must be >10MΩ
Sample test record
IR value @5kV IR value @5kV
Cable size Phase Remarks
before HV test after HV test
R-ground 162GΩ 118GΩ
185 sq-mm Ambient
Y-ground 140GΩ 131GΩ
Single Temp.25°C
B-ground 168GΩ 121GΩ
182
Procedure
Inject slowly voltage by rotating the set dial and observe the injected voltage, leakage current on the
meters provided on set until 24kV voltage.
Test duration is 01 hour. After every 10 minutes note the reading of leakage current.
After completing the test discharge the cable /testing reactor with the ground rod provided by
manufacturer.
Similarly perform HV test on other phase’s cables.
Acceptable criteria
o No break down should occur.
Sample test record
Leakage current after every 10 minutes
Resonant
Cable size Phase Remarks
frequency 10 20 30 40 50 60
Preparation
Connect the operation unit, high voltage unit and equipment to be tested as in diagram given
below
Procedure
The test equipment, preparation and procedure of phasing and continuity test of HV/EHV cables is
same as MV cables already explain above.
186
First perform insulation resistance test phase to ground at 5kV than connect the same sheath to HV
output of DC HI Pot test set.
Connect the other point of dc hi pot set with ground.
Leave the other end of sheath open and clear from ground/main conductor.
Ground the main conductor/sheaths not under test.
Set the leakage current range to higher setting i.e mA.
Give AC supply to dc Hi pot test.
Inject 10kV DC voltage in cable sheath and see the leakage current dial reading in mA if no deflection
of needle set the current range to µA.
Note the measured leakage current in µA.
Perform again megger insulation test of sheath.
Similarly perform insulation resistance and DC HI Pot test of Y,B phase sheaths.
189
R-ground 1.5µA
2000 sq-mm 10kV @01
Y-ground 1.2µA Ambient temp.24°C
Single minute
B-ground 1.0µA
Disconnect the ground connection cable of link box / sheath ground bus bar.
Clean the outer surface of conductor for good continuity.
Connect the ground conductor under test to set E( Exc) terminal with green cable this cable must be
as short as possible as its resistance will be included in final earth resistance value.
Connect set H(EC) red cable with E3 (current) rod and insert the rod in soil up to maximum available
length of red cable.
Connect set S(ET) blue cable with E2 (voltage) rod and insert the rod in soil up to maximum available
length of blue cable.
Select the FUNCTION selector switch of set to position R.
Select the highest measuring range 20kΩ with RANGE selector switch.
Check the testing set battery in charge position.
190
Procedure
Connect the testing set with any cable or other joint as given below:-
191
Procedure
The contact resistance test method is same as breaker contact resistance test.
Inject 100A and measure contact resistance in µΩ.
Similarly measure all joints resistance in link box.
Acceptable criteria
o Contact resistance should not be less than 20µΩ.
Sample test record
Procedure
Inject 2.5kV for 01 minute and measure the IR value by adopting all other test arrangement /
procedure as discussed previously.
192
R-phase 11.3GΩ
Y-phase 8.74GΩ 17.2°C
B-phase 9.04GΩ
Procedure
Inject single phase AC supply by starting generator and adjust the generator output voltage on step
down transformer to i.e 15V as high voltage will increase cable capacitance.
Take the current, voltage and phase angle readings using clap meter, multi meter and phase angle
meter.
Similarly measure the injected voltage, current and phase angle value by changing the connections
between Y-B and B-R phases.
Calculate the positive sequence Impedance by using formula:-
ZRY = V / I Cos ø + V/I j Sinø Ohms → ZRY= V / I ( Cosø + j Sinø )
ZYB = V / I Cos ø + V/I j Sinø Ohms → ZYB= V / I ( Cosø + j Sinø )
ZRB = V / I Cos ø + V/I j Sinø Ohms → ZRB= V / I ( Cosø + j Sinø )
194
Acceptable criteria
o Compare the measured value with cable manufacturer provided data.
Sample test record
Measured Impedance
Measured Measured R=ZCosφOh X=Zsinφ Positive sequence Impedance
Phase phase angle Cosφ Sinφ Ω/Km=Z/179 x
current(A) voltage (U0) m Ohm I Z+I=V/I ( Cosφ+j Sin φ ) ohm
(degree ) 1000
ZRY 81.6 11.1 87.53 0.043 0.999 0.1358 0.0058 0.1358+ j 0.0058 0.7586+ j 0.0324
ZYB 68.8 13.1 88.54 0.025 0.999 0.1902 0.0047 0.1902+j 0.0047 1.0625+ j 0.0262
ZBR 75.7 8.5 80 0.174 0.984 0.1105 0.0195 0.1105+j 0.0195 0.6173+ j 0.1089
Mean
75.36 10.9 .. 0.0806 0.994 0.1455 0.01 0.1455+j 0.01 0.8128+ j 0.0558
value
Impedance per pgase
ZR = (ZRY +ZBR)- ZYB / 2 0.1567 + j 0.0575 Ω/Km
ZY = (ZYB +ZRY)- ZBR / 2 0.6019+ j 0.0252Ω/Km
ZB = (ZBR +ZYB)- ZRY / 2 0.4606+ j 0.0513Ω/Km
All preparation is same as positive sequence impedance test except all phases of cables will be
shorted at test end and at far end all phases will be shorted /grounded.
Make connection as under:-
Procedure
Take reading of Clamp meter, multi meter and phase angle meter by adopting same procedure as in
positive sequence impedance measurement.
Calculate the zero sequence impedance by the formula:-
195
Connect the Generator to all 3 phases of cables at one side and short all phases of cables at other
side.
Deactivate the Generator AVR and connect an external dc current source i.e SEVERKER 750 to
generator exciter winding.
Test connection as under:-
Procedure
Start the Generator with zero excitation and close its output Breaker verify 60Hz frequency.
Measure the output current and voltage of Generator with clamp and multi meter.
Now inject dc current in exciter with SEVERKER 750 until 100A achieved on clamp meter.
Measure the current of each phase and ground and voltage of each phase in all link boxes.
Value of measured current and induced voltage must be very less.
196
Bring the generator current to zero than open the generator output MCB.
Now reverse the sheath connection in any link box and start the generator and measure again the
current and induced voltage in same link boxes this current will be high as 4 times or more.
Acceptable criteria
o Sheath leakage current must be less than 3%.
Sample test record
Connections correct
Current Voltage
Location R Y B Ground R Y B
Link Box.1 10.15mA 10.15mA 10.15mA 10.15mA 100.95mV 86.96mV 90.35mV
Link Box.2 9.25mA 9.45mA 10.15mA 13.95mA 110.85mV 100.95mV 75.90mV
Link Box.3 8.45mA 10.15mA 10.15mA 10.15mA 95.45mV 80.95mV 95.66mV
Link Box.4 10.15mA 12.65mA 10.15mA 11.65mA 88.98mV 86.95mV 100.95mV
Connections reversed
Current Voltage
Location R Y B Ground R Y B
Link Box.1 30A 35A 30A 30A 110.99V 108.89V 105.68V
Link Box.2 50A 40A 35A 38A 115.45V 110.99V 110.99V
Link Box.3 45A 39A 30A 48A 105.66V 95.22V 85.69V
Link Box.4 45A 50A 30A 36A 108.89V 110.99V 110.99V
Procedure
BATTERY TESTING
Following tests should be performed before putting the station battery in service as per IEC60227-2:-
(a) Battery capacity / discharge test
Purpose
To find the discharge capacity of battery.
To find that battery can Support the required load for the specified time.
To find out the condition and problem of battery at load.
This test usually taken for new battery at one time only.
Test Equipment
Load banks or inductive load, AC supply and connection leads.
Preparation
The discharge test duration is 10 hours so divide the AH capacity of cell with 10 and put the same load
on battery bank. Let battery cell AH capacity is 1500AH than 1500/10=150A load will be put on battery
bank for 10 hours.
Battery must not discharge 7 days before capacity test.
Battery charger and load must be disconnected from battery bank.
Record the voltage per cell and terminal voltage of battery.
Select the number of load banks required for conducting test as per load bank manufacturer provided
data.
Connect the load bank with battery as below:-
199
Set the load on 150A ampere and time duration 10 hours on load bank using keypad.
Digital load banks automatically adjust load current as battery voltage decreases.
Give AC supply to load bank.
Procedure
Set the load current on 150A ampere on auto adjustment and time duration 10 hours on load
bank using keypad.
Switch On the main breaker of load bank and start the testing set.
Apply the temperature correction factor to discharge load.
Monitor the voltage per cell and battery terminal voltage and load current after every 30 minutes.
After 10 hours note the voltage per cell / terminal voltage and compare the testing results
with manufacturer.
Usually discharge voltage of one cell is 1.75v and for 60 cell battery bank discharge voltage will be
60x1.75=105.0 V and if during discharge test terminal voltage reaches to this limit stop the test
and find problem i.e Weak cell, loose connection etc.
If there is overheating stop the test.
Most of digital set having volt, AM meter and time device included in the set.
% age Capacity at 77°F= Ta / Tb x 100 where Ta =Actual test time, Tb=Specified test
time.
After discharge test recharge the battery by putting the charger on AUTO charge/
boost charge.
Sample test record
Time 0 Hr 1st Hr 2nd Hr 3rd Hr 4th Hr 5th Hr 6th Hr 7th Hr 8th Hr 9th Hr 10th Hr
Terminal voltage 126 117.19 116.71 116.1 115.44 114.16 113.94 113.02 112.15 110.82 109.5
Terminal current 0 150 150 150 150 150 150 150 150 150 150
Specific gravity 1.26 1.24 1.23 1.22 1.23 1.2 1.18 1.18 1.16 1.14 1.13
Temperature 28 29 29 30 31 31 33 30 32 33 33
Cell No Voltage
1 2.1732 2.016 2.008 1.993 1.995 1.976 1.96 1.943 1.929 1.905 1.881
2 2.18 2.026 2.017 2.007 1.996 1.98 1.971 1.955 1.94 1.916 1.892
3 2.076 2.023 2.014 2.001 1.993 1.974 1.965 1.949 1.935 1.913 1.892
4 2.168 2.02 2.01 1.999 1.998 1.981 1.963 1.946 1.931 1.908 1.886
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
..
58 2.162 2.026 2.018 2.001 1.996 1.97 1.959 1.942 1.926 1.922 1.873
200
Place the clamp meter around any strap to measure the ripple current.
Pull the receiver trigger to save the ripple current value.
Connect the transmitter current source leads (J2) Red to positive terminal specified portion and
Black to negative terminal.
Give AC supply to transmitter.
Procedure
Press the receiver trigger to measure and store the impedance and volts reading appeared on the
screen.
To test the cell strap position the receiver probe on +ve terminal and potential probe on –ve
terminal of strap as under:-
When reading on receiver is stable press the receiver trigger to save the reading.
Once the 1st cell readings are saved 2nd cell test will appear on receiver screen, procedure of testing
2nd cell is same as cell 1.
Similarly test all cells within the portion where transmitter current cables are connected.
To save the last cell record short the receiver and potential probe together when screen display last
cell & strap test result and then press receiver trigger otherwise last cell data will be lost.
Once the all cells in the portion are tested press receiver down key to complete the test , select Y
and to confirm press up key.
Switch OFF the current button of transmitter to block the current and shift transmitter current leads
to other battery portion to be tested.
202
Test the other cells with the same procedure as described above.
After finishing the impedance test press and hold the enter key of receiver and use up/down keys to
select and confirm power down. OFF the current button of transmitter and then switch OFF
transmitter power button. Remove all the interconnection cables.
Acceptable criteria
o The battery cell impedance must be less than 1.5mΩ and strap 0.1mΩ.
Sample test record
Impedance in Resistance in Cell Ambient
Cell No Voltage
mΩ mΩ Temperature Temperature
1 2.1732 0.95 0.321 26°C 26°C
STRAP.1 0.09 0.001
2 2.18 1 0.372 26°C 26°C
STRAP.2 0.095 0.002
3 2.076 0.88 0.331 27°C 26°C
STRAP.3 0.099 0.001
4 2.168 0.85 0.351 27°C 26°C
STRAP.4 0.095 0.002
..
..
..
..
..
..
..
..
..
..
..
..
58 2.162 0.098 0.0018 28°C 26°C
STRAP.58 0.099 0.0015
Give AC supply to charger and switch ON power button and on display unit select Test and manual
operation of charger and verify the following:-
(a) Measured values
Go to display unit AC Input measures and note the following using up/down keys.
1. Nominal AC voltage and Frequency.
2. Float voltage (set the charger on float charging)
3. Boost voltage (set the charger on Boost charging)
4. Pre commissioning voltage (set the charger on Boost charging)
Acceptable criteria
203
o Compare the measured values with charger name plate data or manufacturer given values.
Sample test record
AC Input DATA DC output DATA Measured Expected
Phase R Y B Float voltage 129.3V 129.3V
Nominal voltage 374.6 V 382.1 V 376.8 V Boost voltage 135.1V 135.2V
Frequency 58.3 Hz 58.9 Hz 58.3 Hz Pre commissioning voltage 150.8V 150.8V
Current 1.2A 1.3A 1.3A
2. Load test
Purpose
To verify that charger can take designed full load for specified time.
To identify any problem at full load.
This test is done on 25%,50%,75% and 100% load.
Test Equipment
Load banks programma or other, AC/DC clamp meter, AC supply and connection leads.
204
Preparation
Connect the charger to generator or permanent AC supply.
Switch ON the charger AC supply MCB and than charger On switch.
Give AC supply to load banks.
Procedure
Adjust the load current @25% i.e 112.5A and start the load banks.
Close the output DC MCB.
Note the AC voltage & current, output dc voltage& current, frequency, Power factor and ripple
voltage using AC/DC clamp meter and multi meter.
Similarly adjust the load banks on 50% (225A), 75% (337.5A) and 100% (450A) and take the same
readings as taken at 25% load.
To take the ripple voltage by adjusting the multi meter on AC voltage measurement and take voltage
on dc output side of charger.
Acceptable criteria
o There should be no abnormal sound, excessive heating and tripping of battery charger.
Sample test record
Input AC Voltage AC Current (A)
Load in Output DC DC Current Frequency Ripple
Power factor
% Voltage (V) (A) (Hz) voltage (mV)
R-Y Y-B B-R R Y B
25% 378.8 379.4 379.4 30.1 30.2 29.8 129.6 112.5 60.01 0.8 90
50% 379.9 379.5 379.3 59.7 59.7 59.8 129.04 225 60.02 0.8 120
75% 380.4 381.4 381.4 91.03 90.03 91.04 128.96 337.5 60.03 0.8 140
100% 384.2 385.3 385.1 126.66 126.65 126.66 128.74 450 60.02 0.8 150
205
Efficiency of charger can be calculated by taking the readings of Input current/voltage and output
current/voltage taken during battery load test.
The efficiency of battery is calculated on 50% and 100% load.
Efficiency of charger can be calculated by the formula
Efficiency= DC Output power/ AC input Power x 100 = VI / √3VICOSφ
Sample test record
METERS TESTING
Following meters are used in substation to measure various electrical quantities:-
1. LV AC &DC Volt & AM meters
2. HV AC Volt & AM meters
3. Multifunction (MFM) meters
Transducers
(1) LV AC Volt & AM meters testing
Calibration test of Voltmeters
(a) Analogue AC Voltmeter
Purpose
To verify measuring accuracy of voltmeter.
This test is done on 0%,25%,50%,75% ,100%,120% of rated voltage and full scale display (FSD) of
meter.
Test Equipment
Variable voltage transformer or digital secondary injection tester SEVERKER760or Freja300, AC supply
and connection leads.
Preparation
Set the Severker on AC output voltage.
Give AC supply to testing set.
207
Procedure
Let the meter rated voltage 380V AC full scale display (FSD) is 500V AC.
Inject 25% of rated voltage (95V) in meter by SEVERKER 760 or Freja300 and note the injected and
measure voltage values.
Similarly inject 50% (190V), 75% (285V), 100% (380V), 120% (456V) and FSD 500V note the injected
and measured voltage.
Calculate the %age error by formula= (Injected voltage-measured voltage / Injected voltage) x100
Acceptable criteria
Acceptable criteria depends on meter class, If the meter is class.1 than % age error must be < ±1%,if 1.5
than< ±1.5%.
Sample test record
Procedure
The testing procedure of dc voltmeter is same as AC voltmeter except select testing set output
voltage to dc.
Make sure set +ve cable should be joined with +ve meter and –ve with –ve of meter.
Test record of 150V FSD and rated voltage 120VDC is as under:-
208
25% 30 30 0
50% 60 60 0
75% 90 90 0 % Error=[ (c-d)/d ]*100
Class 1.0=±1%
100% 120 120 0
120% 144 145 0.69
FSD 150 152 1.33
Procedure
Let the meter CT ratio is 150/5A, full scale display (FSD) is 180A.
Inject 25% of rated secondary current 5x25%= (1.25A) in meter by SEVERKER 760 or Freja300 and
note the injected and measured current values.
The reading on meter should be 150x25%=37.5A
Similarly inject 50% (2.5A), 75% (3.75A), 100% (5A), 120% (6A) and note the injected and measured
current values.
Calculate the %age error by formula= (expected current- Injected current / expected current) x100
Acceptable criteria
Acceptable criteria depends on meter class, If the meter is class.1 than % age error must be < ±1%,if 1.5
than< ±1.5%.
Sample test record
DC Ampere meters works on mV given by the shunt connected in series with the power circuit.
Let the meter scale shows data class 2.5, 100A/60mV, this means if voltage drop in shunt is 60mV
than the reading on Ampere meter will be 160A.
We will inject 25% of 60mV,60*25%=15mV than the reading on meter should be 160x25%=40A
210
Similarly inject 50% (30mV), 75% (45mV), 100% (60mV), and 120% (72mV) and note the injected and
measured current values.
Sample test record
As VT secondary rated voltage written on the meter is 110V ph-ph or three phase, 25 % will be
110x25%=16.13V.
Go to 1st page of Freja 300 and select 16.13V on each phase and then press start button of Freja 300.
211
Note the Ph-Ph and Ph-G voltage appeared on kV meter, it should be 380x25%=95kV Ph-Ph and
95/√3=54.5kV Ph-G or single phase.
Similarly inject 50% (55V), 75% (82.5V), 100% (110V), 120% (132V) of rated secondary voltage and
note the injected and measured voltage values.
Calculate the %age error by formula= (expected voltage- Injected voltage / expected voltage) x100
(b) Digital VT operated AC Voltmeter
Procedure
1. The preparation & procedure of digital meter testing is same analogue meters.
(3) Digital Power demand meter (DPDM) testing
Digital Multifunction are widely used now a days as they provide the full metering information of Current,
voltage, power factor, frequency and Power as well. These meters can also be connected to PCC trough
SCADA or SAS for remote monitoring.
Purpose
To verify measuring meter accuracy.
This test is done on 0%,25%,50%,75% ,100%,120% of rated voltage and full scale display (FSD) of
meter.
Test Equipment
Freja 300 as it can inject 3 phase voltage, connection cables, AC supply
Preparation
Procedure
Go to freja300 Mode1 1st page of 7 and set voltage 25% of rated secondary voltage i.e 110*25/√3=15.8
V for each phase.
Press the start button of Freja 300.
Note the primary voltage between Ph-Ph and each phase-G appeared on meter display
Similarly inject 50%, 75%, 100% and 120% of meter rated secondary voltage and note the primary
values of voltage appeared on meter.
Calculate the %age error and compare with manufacturer provided limit.
50% 31.76 110 109 110 192 191 191 190 109.7 0.4 0.2 0.2 0.06 -0.15 0.06
75% 47.63 164 165 164 287 285 286 285 164.55 -0.4 0 0.2 -0.12 0.09 -0.12
100% 63.51 219 220 219 381 380 382 380 219.4 0.2 0 0.4 -0.08 0.13 -0.08
120% 76.21 264 263 264 455 455 455 456 263.28 -0.2 -0.2 -0.2 0.02 -0.06 0.02
213
In freja300 Mode1 1st page of 6 and set current 25% of rated secondary current i.e 1*25/ 100=0.25A for
each phase.
25% 0.25 749.5 748.5 749.5 750 750 750 0.0667 0.2 0.066667
50% 0.5 1498.5 1499.5 1497.5 1500 1500 1500 0.1 0.0333 0.166667
75% 0.75 2245 2248 2249 2250 2250 2250 0.2222 0.0889 0.044444 ±0. 17
This test is done by injecting rated secondary voltage/current and changing the phase angle only i.e
0°,45°,90°,135°,180°,270° and 315°
In freja300 Mode1 1st page of 6 and set current 1A and voltage 63.5V for each phase.
Make the angle between U&I 0°.
MW MVAR MVA
Injected
Injected
current in Phase angle
volta
phase (A) Calculated Measured %age Error Limit Calculated Measured %age Error Limit Calculated Measured %age Error Limit
63.5 1 45° 1394.54 1396 -0.1 1393 1394 -0.07 1974 1973 0.05
63.5 1 90° 0 0 0 1972.2 1974 -0.09 1974 1973 0.05
63.5 1 135° -1394.54 -1394 0.03 ±0.2% 1394.5 1390 0.32 ±0.5% 1974 1973 0.05 ±0.2%
The procedure and preparation of this test is same as power measurement test except the
current/voltage is injected for specified time.
Adopt the same procedure as in power measurement test and injection should be made i.e for 05
minutes on each angle.
Note the reading of MWH and MVARH after 05 minutes displayed on meter screen.
Calculated power can be find using same power formula only multiply with time:-
Active Energy =√3 V I Cosø x time =1.732x380000x3000xCos0° / 106=1974.48MW x5/60=164.5MWH
Reactive Energy =√3 V I Sinø x time
MW MVARH
Injected
Injected
current in Phase angle
volta
phase (A) Calculated Measured %age Error Limit Calculated Measured %age Error Limit
This test is done by injecting the rated voltage in the meter and changing the frequency.
63.5 45 45 45 0
63.5 50 50 50 0
63.5 55 55 55 0
63.5 60 60 60 0
63.5 65 65 65 0
This test is performed by injecting rated voltage and changing the phase angle from 0 to 180°.
Injected
Injected Expected
current in Phase angle Expected PF=Cos Actual Reading % Error
volta Reading
phase (A)
63.5 1 0° 1 1 1 0
Purpose
To verify measuring accuracy of meter.
Test Equipment
Digital accuracy meter i.e. ZERA, Connection leads, Freja 300, AC supply, calculator, stop watch..
Preparation
Digital energy meter are fully programmable through software usually by the manufacturer.
Install the manufacturer provided software in computer/laptop.
Give Auxiliary supply to energy meter and calibration meter.
Connect the energy meter with laptop and then open meter main menu enter your system data i.e
CT/PT ratios, limits and items to be displayed in various columns of meter programme.
216
After entering your desired value in each card click OK and then save the settings.
Enable the meter in Test mode.
Procedure
217
Expected values-c 219.39 219.39 219.39 2000 2000 2000 0.03191 0.0283 0.02826 0.15 0.15 0.2 ±0.2%
63.5 1 30° 05 minutes 0.866 94.99 (Del) 94.98 94.97 0.02 0.5 54.84 (Del) 54.85 54.71 0.02
63.5 1 60° 05 minutes 0.5 54.84 (Del) 54.7 54.71 0.02 ±0.2% 0.866 94.99 (Del) 94.98 94.97 0.02 ±0.2%
63.5 1 90° 05 minutes 0 0 0 0 0 1 109.69 (Del) 109.68 109.5 0.17
63.5 1 180° 05 minutes -1 109.69 (Rec) 109.52 109.5 0.17 0 0 0 0 0
63.5 1 270° 05 minutes 0 0 0 0 0 -1 109.69 (Rec) 109.6 109.5 0.17
Meter accuracy test is one by injecting meter rated secondary voltage and at 10%, 100% rated
secondary voltage.
Sample test record
63.5 1 0 -0.05
63.5 0.1 90° -0.04
63.5 1 90° -0.04
63.5 0.1 180° -0.05
63.5 1 180° -0.05
63.5 0.1 270° -0.03
63.5 1 270° -0.04
Pulse test
Purpose
To verify measuring accuracy of transducer
Test Equipment
Current injection set i.e Freja 300, Multi meter, AC supply.
Preparation