Stage 1 Stage 2
1. Install tremie pipe into trench panel installed with reinforcement cage. 1. Install Tremie hopper to the tremie pipe
RTS Viaduct RTS Viaduct
Stage 3 Stage 4
1. Concrete the dwall/barrette pile by tremie method 1. Concrete the dwall/barrette pile up to the design cut‐off‐level
RTS Viaduct RTS Viaduct