B.1 Objective
The objective of this document is to aid the selection of the best suppliers to guarantee quality
and quantity of the product during the life span of the project. In addition, it gives the supplier
and the costumer the confidence that all requirements and prerequisites of the customer are
taken into consideration.
B.3 Abbreviations
Abbreviation / Explanation / description
technical term
0S 0 – Series Phase, Nil - Series
The 0 - Series shall ensure that before the start of production of a new prod-
uct, all the parts fit together in the assembly and assess the dimensional as-
pects of a part. The function of tools, checking fixtures and equipment is test-
ed under series production requirements. The 0 - Series contains the com-
plete production run as a trail run of the series production phase. This phase
shall only be built with parts out of series tooling.
2nd tier, 3rd tier Sub supplier of the supplying supplier or assembly supplier
BTV Supplier Quality Engineer (Bauteileverantwortlicher)
BZD Documentation of build status (Bauzustandsdokumentation - additional Link)
Cp/ Cpk Process capability index, a number to assess a process statistically
D- Characteristics Characteristics of a product which are mandatory to document
FS/GS Forward Sourcing / Global Sourcing
HIS Manufacturer initiative software (Herstellerinitiative Software)
HW Hardware
JIS Just In Sequence
JIT Just In Time
KTL Supplier Quality Manager of the producing plant (Kauf Teile Leiter)
KVS Engineering maintenance system (Konstruktions Verwaltungs System)
N/A Not Applicable
NOLIS Online Standards System (Normen-Online-Informations System)
OEM Original Equipment Manufacturer
PEP Product Emergence Process
PSK Product Steering Group (Produkt Steuer Kreis)
PVS Production Validation Series; it is aiming to get last commitment to the assem-
bly of parts. The Assembly has to done under series representative processes
with series tooling parts. (Produktions-Versuchs-Serie)
QPL Quality- Project Leader
C.1 Background
The aim of the QTR is that the offer, based on the following questions, is checked for plausibil-
ity, completeness and feasibility (see formula-Q-Specifically, at www.vwgroupsupply.com).
The quoting supplier is obliged to make all necessary documents available before the nomina-
tion
C.2 Procedure
The supplier shall be notified by the purchase department to complete the QTR documentation.
This will be subject to a deadline which will be in line with the quotation. Delays in the comple-
tion of the documentation will automatically lead to escalation and in the worst case exclusion
from the procurement process.
All questions are mandatory. Questions with one asterisk (*) require a detailed answer and if
they cannot be answered appropriately, it will lead automatically to a degradation (Red). Ques-
tions with a double asterisk (**) are related to software developments. Questions which are not
applicable have to be marked accordingly with N/A.
After the submission of a completed documentation, an internal, cross functional validation and
verification will take place. After the review, the supplier may be invited to present the documen-
tation. Documents, which are not sufficient or complete, go back to the supplier for improve-
ment. Volkswagen AG holds the right to request the data for future reference, if necessary.
C.3 Results
The result, based on the information submitted will be re-presented to the supplier qualitatively
(green / red or the pass / fail). The supplier is expected to sign the result sheet. A Supplier with
“Red” or “fail” result will not be considered for nomination. The QTR results sheet will influence
the procurement process and will be part of the nomination letter.
1.1 Project
The supplier must nominate a project leader, who will ensure a successful start of production
(plus 90 days). This person will apply the Qualification Programme of New Parts (see Formel Q
Integral “New Parts Development System”) and present it to the customer in line with the pro-
gramme.
The name, function and deputy of the project leader must be reported to the Quality department
of the leading sampling VW Group plant and to the Supplier Quality Engineer (BTV).
The supplier is responsible for showing the internal and external capacities for simulation, man-
ufacturing and development and series tests, according to the scope of the technical specifica-
tions designated by the customer. They must show this with their project planning and proof that
they can fulfil the technical requirements, volume and timing schedules.
Layout and location of the suggested Plant location and layout available to be
1e) plant / manufacturing location including shown ( Reference to timing plan for new
company infrastructure equipment)
Reference of similar already developed Does the company have experience in this
1f)* and products / carried out projects type (or similar) parts, show evidence of
similar parts
Name of project leader (complete project, Is the project manager known and what is
1g) SW dev. /HW dev. etc. Inclusive the list- his/her experience
ing of experiences as a project manager)
Amount of projects, which are currently How many projects does the project man-
1h) worked at by the project leader ager run - throughout the timeline of the
project
Detailed organisation chart of the overall Project team org chart showing tasks, re-
project team (tasks, responsibilities, per- sponsibilities and percentage of time allo-
1i)
centage of project involvement and loca- cated to project - over the timeline of the
tion of team members) project
Flow chart and systems for processing of Process flow for implementing engineering
1j) engineering changes changes (incl. examples of systems / doc-
uments)
1k)* Agreement project proposition See 1.2
2 Product development
The supplier has to fulfil in line with the technical requirements of the bid specification basic
requirements in the area of product development.
The below listed questions blocks shall cover the main topics of the responsible design engi-
neer.
2.1 Systems
4.2 Traceability
The supplier is responsible for ensuring traceability, origin, their storage, tests and distribution of
the purchased raw material / components (HW/SW, charges) and each process, as well as dur-
ing each project phase. These same considerations apply to reworked components.
The changes in engineering level must be documented in line with the Formel Q Konkret pre
series documentation incl. part history. All relevant changes, the volume of parts and their per-
formance must be identifiable to the produced amount of parts.
5 Product
NOTICE: The answer of every question is obligation. Not to be able to be answered questions
with a star (*) that one, operate automatically to the devaluation (Red).
Questions with a duplicate star (**) refer to software development.
Questions not valid are with to answer n/a