Documente Academic
Documente Profesional
Documente Cultură
• I'ER_PUSTAKAAN
\'-~ .., MAKSI·I'l'I\K ffUI .
SI~LICRAM, INC.: J<:r.RCTRONIC TESTI:\G OPERATlO:'XS
\ve put in a plccc or automated equlpment a year ago transformers, relays. and crystals. Component testing
that only fits the requirements of one customer, This was required for IWO reasons. First. if defective cornpo-
equipment reduced the direct labor required to test his nents were not caught early in the manufacturing cycle.
components and. because of Our tabor-based burden al-
locatlon system. substantially reduced hi. cos rs, But
the COStof repair could exceed the manufacturing cost
putting a $40.000 machine IntO the general burden pool of tile pcodocr itself. Studies indicated that B defective
raised the costs to our other customers. It just doesn't resistor caught before use in the manufacruring process
make sense shooUnc yourscli in the 100( at the same COSttwo cents. If tbe resistor was nO{ caught until the
lime you arc lowering the COMp.1ny'SCOStof operations. end product was in the field, however. the cost of repair
could ron into the thousands of dollars. Second, a large
proportion of Scligrarn's work was defense related. Mil-
itary specifications frequently required extensive testing
Introduction of components utilized ill aerospace and naval products.
By 1988. ETO had the ability to test 6.500 dilfercru
The Electronic Testing Center (ETO). a division of components. Typically, however, the division would test
Selig nun. Tnc., provided centralized testing for elcc-
about 500 different components each month and be-
tronic components such as integrated circuits. E'rO was tween 3,000 and 3,50() per year, Components were I'C-
created (IS a result of a decision in 1979 to consolidate
ceived from customers in lots; ill 1988 ETO would rc-
electronic testing from I I differenl divisions of
ceivc approximately 12,000 IOlS of components.
Seligram. P,TO commenced services to these divisions
ETO performed both electrical and mechanical test.
in 1983. Ltwas estimated Ihat centralization would save ing. Electrical testing involved measuring the electrical
Seligrarn in excess of $20 million in testing equipment
characteristics of the components and compnring those
investment over the next flve years. measurements with the components' specifications. For
ET() operated as u cost center und transferred prod ..
example. the specifications for all amplifier may have
ucts to other divisions nl full COSt(dlrect costs plus allo- called lor a l-volt input to be arnplified into a to-vcu
cated burden). Although ETO was a captive division,
output. ETO would deliver a l-volt input to the compo-
other divisions within Seligrnm were allowed to use ncru. By measuring the amplifier's output. ETO gauged
outside testing services if E'l'O could not meet their cost
its conformance with specifications.
or service requirements. ETO was permitted 10 devote Mechanical testing included solderability, compo-
up to 100/0of its testing capacity ttl outside customers
neru burn-in, thermal shock. lead straightening. and
but chose to work mainly with other Seligram divisions leak detection. Solderability involved the inspection of
due to limited marketing resources,
components to see if they held solder. Burn-in was the
ETO employed approximately 60 hourly personnel
extended powering of components at high temperature.
and 40 administrative and technical staff members. Bud-
Thermal shock involved the cycling of components be-
geted expenses were $7.9 million in 1988 <see Exhibit I).
tween high and low temperatures. Lead ~lr.lightcning
was the detection and correction of bent leads on com-
Testing Procedures ponents such us axial compooerus. Leak detection ex-
ETO expected to te.\! between 35 and 40 million com- amined hermetically sealed ICs for leaks.
ponents in 1988. These components included integrated Components varied significantly in the number and
circuits (Ies). diode •• trnnsisrors, capacitors. resistors, type of electrical and mechanical testing procedures
they required. This variation resulted in about 200 dif·
ferent srandard process flows for the division. Process
'Ilut; c.'lie .....11' prep;u'tld by Pro(e$IOC' Pt.ler Jl 0 Tume),. Portl~ Sl8.Ie Uni·
ftows were determined b)' the different combinations of
~'t'lSil)!.;"1".4 Uri~ophl" lUl\('r, c)or.IC,'r~l I'lueJrnl (IFnde.r(he ~lIpel'\'isjon of Pro- tests and specifications requested by the customer.
resse, I(,,"in C(~r)
Based on these combinations, ETO planners deter-
COI)}riy.l Q::) l\lt'll( by .l,e 1~1':)!I;k"' :111"hdlll"', nf 1I1II"\'llWC'.olkge Hv·
v.vd BIilJrlc:-lI Sd ..,M,1Ic a..c 11\9·0114. mined the routing of components between testing
67
/l
,
-
TRADITIONAL STAt~t>II COST SYSTEMS 69
already noticed an increase ill the number and fre- rations), and ETO's equipment could bandle up to 120
quency of complaints from ccstomers !\-'garding the terminations. Althougb the 120-tcrminalion limit had
rates (hey were charged lor testing. only been reached a couple of rimes in the pasl few
The division's uccounting manager proposed a new years, a neev gcnernrion of components with up to 256
cost accounting system to alleviate the problem. Under terminations was already being developed. Similarly,
tillS new system, burden would be directly traced to the upper limit of frequency on existing components
twOcos. pools. Tile first pool would contain burden re- was 2() MHl. (million cycles per second), whereas the
lated to the administrative and technical functions (di- frequency on the next generation of components was
vlslcn management. engineering, planning. and adrnin- expected 1.0 be 50 MH%.
jstrutivc personnel). This pool would be charged On a The equipment required to teNI the next gene.....
nion of
rate per direct labor dollar. The second pool would in- components would be expensive. Each machine CO$tap-
clude all other burden costs and would be charged proximately $2 million. Testing on this equipment
based on machine hours. Exhibit 3 provides the pro- would be more automated than existing equipment,
posed burden rates. with longer test cycles and the generation of more tCSL
Shortly after the accounting manager submitted his ~atu per part. It wus also likely (hat lot sizes would be
proposal. a ccnsultanr hired by Seligram's corporate tnrger,The new equipment would not replace the exist-
management prepared an assessment of ETO'" cost sys- ing equipment bul would merely add capabilities ETO
tem. He recommended the implementation of a three- did not currently possess. Addilionally, the new equip-
burden pool system utili7.ingseparate burden centers for meru would only be needed to service (he requirements
each test room and a common technical and administra- of one Or two customers in the foreseeable future. Ex-
live pool. Burden would be directly traced to each of hibit S provides u summary of the new equipment's eco-
the three burden pools. Like the accounting manager" nomics and operating characteristics.
.yMcm, burden costs in the test rooms would then be al- The impact of this new equipment would be an ac-
located on a machine hour basis. Technical and adrnin- celeration in the decline in direcl labor hours pcr 101.of
lstraiivc costs would continue to be charged on a rate cornponenrs. At 'he sante lime, burden would increase
per direct labor dollar. with the additional depreciation and engineering: costs
'to examine the impact of the two alternative. sys- ..ssociated with the new equipment. This would resuu in
tems, E.TO management asked that a study be con- • large increase in the burden nile per direct labor dol-
ducted On a representative sample of pans. Exhibit 4 tar, As Paul Carte, Manager of lITO. saw it, the acquisi-
provides a breakdown of actual direct labor and ma- lion of the new equipment could have a disastrous effect
chine hour requirements per 101for thc five components on the division', pricing structure if rhe labor-based al-
selected for the study. location system remained in use:
EXHIBIT J
SELlGRAM. INC.:
ELECTRONIC TESTING CENTER
1988 Budgeted Expenses
EXHIBIT 2
SEUGRAM, INC.:
ELECTRONIC TESTING OPERATIONS
Calculationof Burden Rotc
Based on 1988 Plan
BURDEN F.l..EMEN't
144.6%
Variable $1,426,317
O.:pn:ci~tion 1,288,000
Other fixed: l.999.665
'total burden: $4,113,982
CHM'1'F.R 2 TRADITIONAL SI'AC:E " COST SYSTEMS 71
EXHIBIT 3
SELIGRAM, INC.:
ELECTRONIC TESTING OPERATIONS
Proposed Burden Rates
Based on 1988 Plan
MACHINE HRS
Fixed
Vllrj,;oie Odl'f'l:dlltiOlJ Olh~T TOl4l1
t>.f;lin 1t:.1 room $ 887.379 $ 88.779 $1.126.958 52.103.116
l<otlXh.a.nlc:d ~$\ 100m .. ,,3.833 808.100 679.327 1.926.263
Total bul'dm $1,331,212 ~ SI.801.2S5 54.029.379
Vt),rI~blt s 95.105
fjxed:
Dt!pr(('i.lIion 391.118
Otlw, 19~.380
ToW 56&1.603
stndUck; all direct b_boI'C'OIOtS. incllldJng dift'd labo~oo!>l1lnrurred in both :~
eocms 11.' wen as eI18;ncmns.
EXHIBtT4
SELIGRAM, INC.:
ELECTRONIC TESTING OPERA110NS
Direct Labor and Machine HOUT Requlrements
Actuals for One Lot
M.\Cffit.,;E uOURS
/
'.