Documente Academic
Documente Profesional
Documente Cultură
2012
INDUSTRIAL TRAINING REPORT
PEER MARK ENGINEERING
SDN. BHD.
2012
i
DECLARATION
I declare that all parts of this report are the result of my own work except the
Quotations and the references, the sources of which have been acknowledged in the
bibliography.
…………………… .
2012 FALIQ BIN AJIR
ii
SIGNATURE PAGE
………………………..
Company Supervisors
………………………..
Lecturer Supervisors
ACKNOWLEDGEMENT
Assalamualaikum w.b.t.
I would like to thank the company that have given me the opportunity to learn more about
the industry that is PEER MAR ENGINEEERING Sdn Bhd . During the training I was
nurtured and spoon fed with a pool of knowledge that are very valuable. The company
have thought how the real working environment are , they are so gallant that they trust
me by handing me a real job , which turn out to be really valuable experience. Special
thanks to company managers especially Mr. Ravi Chanan and Mr. Maswandy who guide
and assigned me with task and Mr. Shamsul Abbas who really help me a lot and teach
many things about the industry and very supportive , and to Mr Ruzaidi and Mr. Zahir
who help me and my friend whenever we have problems with our work , support and
help me in completing this program successfully and also the owner of the company Mr.
Marcus who gives us the opportunity to work with the company. Thanks for guiding and
helping me in learning and gaining knowledge in oil and gas industrial career.
Not to forget for all other workers because giving me a good cooperation and
made me as one of the PEER MARK ENGINEERING family. Hope that PEER MARK
ENGINEERING Sdn. Bhd. will continue its growth and be success in future and
iii
ABSTRACT
The report is divided into two sections, Economic Section and Technical Section.
The Economic Section contains the company background and profile of PEER MARK
ENGINEERING SDN. BHD .The company is specialize in design and manufacturing of
process modules , heat transfer equipment , pressure vessels , process column and other
equipment for oil and gas , petrochemical , power plant and general industries . The
product is marketed locally and worldwide. In the technical section, the trainee was given
a project to complete during industrial training. The project is Provision of Computer
Assisted Operations (CAO) at ANGSI-B. As a trainee I was assigned as a Quality Control
Inspector of the project who represents PEER MARK ENGINEERING. From the project,
the trainee has gained valuable working experience and managed to complete the
industrial training report.
iv
TABLE OF CONTENTS
Declaration…………………………………………………………………………… ii
Signature page…………………………………………………………………………...
Acknowledgement…………………………………………………………………….iii
Abstract…………………..………………………………………………………….. iv
List of Appendices…………………………………………………………………….v
List of Illustrations……………………………………………………………………vi
Chapter 1………………………………………………………………………………1
Chapter 2……………………………………………………………………….……...5
Chapter 3……………………………………..…………….……………..………….. 9
Chapter 4……………………………………………………………………..……… 27
Bibliography……………………………………………………………………………29
Appendices………………………………………………………………………...… 30
Illustrations…………………………………………….………………………………42
v
LIST OF APPENDICES
Appendix 1………………………………………………………………………………29
Appendix 2……………………………………………………………………………....30
Appendix 3………………………………………………………………………………31
Appendix 4………………………………………………………………………………32
Appendix 5………………………………………………………………………………33
Appendix 6………………………………………………………………………………34
Appendix 7………………………………………………………………………………35
Appendix 8………………………………………………………………………………36
Appendix 9………………………………………………………………………………37
Appendix 10……………………………………………………………………………...38
Appendix 11……………………………………………………………………………...39
Appendix 12……………………………………………………………………………..40
Appendix 13……………………………………………………………………………...41
vi
LIST OF ILLUSTRATIONS
Illustration 1……………………………………….……………………………………..42
Illustration 2…………………………………………….…….………………………….43
Illustration 3…………………………………………………..…….……………………44
Illustration 4……………………………………………………….……………………..45
Illustration 5……………………………………………………………………………...46
Illustration 6………………………………………………………………...……………47
Illustration 7……………………………………………………………...………………48
Illustration 8……………………………………………………………..………………49
Illustration 9……………………………………………………………………………..50
Illustration 10……………………………………………………………………..……..51
vii
CHAPTER I
INTRODUCTION
CHAPTER I
(INTRODUCTION)
company. Industrial Training also is compulsory to all MFI full time students since it is
one of criteria for graduation. Trainee needed to complete their INTRA in 16 weeks, upon
which a report is submitted to the assigned supervisor in MFI. Students also need to make
a presentation regarding their training to the panel members who are lectures from the
respective technical department. Marks will be given after evaluating the student. The
An informal training done work in area situation, and in the last semester at real working
condition area, such as in industrial company or for an industrial project which to be done
in Malaysian France institute and the industrial training much have constraints and they
The objective of the training in the Industrial environment is to develop the autonomy,
environment.
importance.
a recommendation to student.
2
INDUSTRIAL TRAINING LOCATION
The industrial training was done at the PEER MARK ENGINEERING SDN. BHD. The company is
located at Lot 8965 , Jalan Udang Galah , TELOK GONG, PORT KLANG. The address of the
company is:
The position that was given to the trainee is the Q.C (quality control). The trainee was
department. The Q.C is responsible to check the quality of the product , quantity ,
with client , organize Welder Qualification Test (WQT) , organize Hydrostatic test and
many more. The task of QC inspector is to make sure that the task will go on progress
without any problems.. The Company supervisor is the person that entirely responsible of
the trainee progress. He will give the entire task to the trainee. The industrial Training
took 16 weeks starting from 19th December 2011 and end on 7th April 2012.
3
Working Schedule
1. Time of work
At 8.30 a.m. until 5.30 p.m.
On Saturday work at 8.30 a.m. until 1.00 p.m.
Overtime (OT) is recommended if there is many work.
Every Monday need to come early at 8.00 a.m to attend Tool Box
Meeting.
Breakfast for 30 minutes at 10 a.m to 10.30 a.m
Lunch break for 1 hour at 12 p.m to 1 p.m
There is also break at 3 p.m for 30 minutes
Overtime (OT) will start on 5.30 p.m an onwards.
Basically as a trainee we are encouraged to do overtime to help with the
work because there is not enough man power in Peer Mark Engineering.
2. Allowance
Allowance will be pay as follow :
Basic allowance RM600.00
OT allowance RM100.00
Total RM700.00
4
CHAPTER II
COMPANY PROFILE
Lot 8965 ,
2. Address : Jalan Udang Galah,
Telok Gong,
42000 Port Klang
Selangor Darul Ehsan.
.
5
10. Organization Chart : (Refer Appendix 1)
68,000 sq.ft.
60,000 sq.ft.
79,200 sq.ft.
47,520 sq.ft.
6
COMPANY PROFILE
The Company has been accredited by ASME with ASME “U” Stamp, ASME “U2”
Stamp, “R” Stamp and National Board Registration. They are now also working on
developing ISO 9002 Standard to integrate strength and conscientious attitude to gain a
solid reputation in oil and gas industry. Our team of professionals are fully conversant
with international standards as well as practices on all design codes. With the support
of the latest technology of equipment and softwares, we provide unique & precise
engineering solutions to cater to the specific demands of the industry throughout the
region.
The fabrication yard, which situated in Port Klang has made us a preferred fabricator
for process skid modules as well as oversized equipment serving the Oil & Gas,
Petrochemical, Power Plant and general industries regional. We have successfully
supplied equipment and packages to multi-national and local companies in the country as
well as end users in Thailand, Vietnam, Myanmar, Indonesia, Brunei, Philippines, India,
Oman, Qatar and etc.
7
CORPORATE LOGO
COMPANY EXPERIENCE
(Refer Appendix 13)
8
CHAPTER III
(REPORT ON PROJECT)
ROLE OF QC DEPARTMENT
Inspect Material
Fit-up inspection
Visual Inspection
Entertain Client and inspector
Request for Non Destructive Examination
Identify joint that needed for Radiographic test
Documentation of Manufacturing Data Record (MDR)
Ensuring that the correct welding procedure specification (WPS) are being
applied by production department and welders are qualified to perform the
intended work.
Any other responsibilities as stated in the ASME.
Ensure that all procedure and the project is met with ASME Code .
9
manufacturer company has to follow strictly. This is to ensure the quality
of the product at its best.
In our point of view, that objective of this project is to helps us in getting exposed
to the real working experience as a QC inspector and the whole team of
management. Besides increasing our knowledge, we also apply what we have
learnt before in mfi:
Estimating the materials
Technical drawings
Optimizing the material
Organizing the management board
Innovating the project
Listing tools and machines
Specification of welding types
Elaborate the procedures of processes
Estimate the cost
In terms of mechanics, force, equilibrium, force and other theories
This project totally improves our skills. We get to manage the timeline in-
consistent with the fixed schedule: we would love to try to produce great
products. We also learn how to handle a project and work in a team.
ARRIVAL OF MATERIAL
1. Firstly the material arrive , and as QC inspector trainee have to check the size
the material and the Heat Number so that it is compatible with the ordered
material and check it with mill certificate with the supervision of Client
Representative.
2. After that, use the Heat Number and material type , specification and size to
make a FIT-UP inspection report and Material Inspection Report. All of this
Report needed to be approved by 3 party : manufacturer , client and owner .
FIT-UP INSPECTION
1. After all the material is clear and get the approval of QC inspector, Store
supervisor (material handler) will give the material to production. Then the
work will be proceed by Production where they will start the fit-up inspection
base on drawings that has been given to the welder by production department.
2. The fit-up inspection will be monitored and approved by QC inspector based
on the design.
3. After fit-up is finish , welding is proceed. Based on the project, the welding
process used is GTAW/SMAW for 3 and ½ inch and more thickness of the
pipe and GTAW for 3 inch and bellow.
4. ( Example of ISO Drawing : Refer Appendix 9).
12
WELDING
1. During the welding, QC will make sure that the welder is already qualified and
provided with welder card.
2. Qc will also make sure that the welder used the correct welding process and
position.
3. QC inspector will make visual inspection on the weldment and if its pass the
visual requirement, QC can proceed for Non-Destructive Testing and
Radiographic test.
4. There are 4 welder for this project that use welder number of W016,W057,W022
and W023.
5. For piping is Welder W016 (GTAW/SMAW) and (GTAW) and Welder W057
(GTAW).
6. For Structural is Welder W022 and W023 (SMAW).
7. The welder are qualified and experience welder. There are no problem with
NON-DESTRUCTIVE TESTING after the test are carried out on the weld.
13
EXAMPLE OF WELDER WPQ FOR THIS PROJECT
VISUAL INSPECTION 14
a) PRIOR TO WELDING
After the parts are assemble for welding, the inspector should check the weld
joint for root opening, edge preparation and other feature that might affect the
quality of the weld. The inspector should check the following conditions for
conformity to the applicable specifications.
b) DURING WELDING
Visual inspection is the primary methods for controlling quality. Some of the
aspects of fabrication that can be checked include the following:
c) AFTER WELDING
Items that are checks by visual inspection after welding include the following:
15
1. In this Project the required NDE is 100% Magnetic Particle Test on all joint
and 100% Radiographic test on all butt joint.
2. QC must keep updated with all the joint that are finished to request the NDE.
MPT must be done first before Radiographic test can be done.
3. The NDE company used for this project is PRESCAN SDN. BHD. (NDE
Report : refer Appendix 2 and 3 )
4. All magnetic particle used in either dry or wet MPI technique shall have good
contrast color against test surface , high permeability . low retentively and
sufficiently fine
5. All areas to be inspected shall be sprayed with coat of white contrast paint of a
thickness not exceeding 24 microns. It could demonstrated with Burmah
Castro field indicator that indications can be detected through the maximum
coating thickness applied.
6. The surface of the part to be tested shall be essentially clean , dry and free of
contaminants such as oil, grease . loose rust, thick paint, welding flux, spatter
or other material that may hinder the movement of iron powder or
interpretation of result indication.
7. MPT used a machine called Yoke to obtain reading.
8. Applied magnetic ink either through aerosol(wet method) or puffer(dry
method) onto the area where magnetic field has been induced with the current
still on.
9. Then observed for indications formed by the magnetic particles.
10. After that cut off current flow before remove the yoke.
11. Then collect the data.
12. For Radiographic test it is running on specified time where there are no person
is working mainly at night. This is for safety reasons.
13. Only NDE personnel shall be on the area during Radiographic testing.
17
Example of Radiographic Test Report
HYDROSTATIC TEST 18
19
inches pipe spool of 153 bar . The Hydrotest specification is based on ASME
B31.3.
10. The metal temperature during the hydrotest shall be maintained at least (17
Celsius) above the minimum design metal temperature but need not exceed (48
Celsius) to minimize the risk of brittle fracture.
11. The Hydrotest were runs on 3 different occasion due to differences of pressure.
12. During the hydrotest the pressure recorder and gauge used is for 10000 psi .
13. The hyrotest step is that the pressure is increase 25% at first , and then it is
increased to 50% for 15 minutes , then it is increased to 75% for another 15
minutes and then it is increase to 100% and is hold for 1 hour . After it is hold
for 1 hour , the pressure is decrease to 75% and then it it slowly decreased until
0% . From the Hydrotest it is showed that there are no leak and the client and
owner representatives are satisfied with the test.
14. The hydrostatic pressure / time data shall be recorded on a certificate , the
report will show the following data (HT chart : refer appendix 4) :
Hydrostatic test pressure
Tag no.
Date of test
Ambiesnt temperature at time of test
Pressure gauge no / range and gauge calibration certificate
Pressure recorder no / range and calibration certificate
The figure shows the pressure recorder is set-up for Hydrostatic Test
20
EXAMPLE OF HYDROSTATIC INSPECTION REPORT
21
1. After all the Pipe Spool are clear of Hydrotest , painting is carried out.
2. Firstly before painting is carried out, the surface must be prepared. The Surface
is prepared by cleaning the surface of the pipe/structure by using blast cleaning.
3. The compressed air supply used for blasted cleaning shall be free from water
and oil. Oil separators and traps shall be provided , installed in coolest part of
the system.
4. All welded area shall be dressed free of slag , weld spatter , scales , shivers ,
unacceptable undercut and other imperfections before blasting.
5. All fabrication, welding and testing should be completed before surface
preparation begins.
6. Blast Cleaning shall be carried out to achieve requirement of client specification
and blast nozzle pressure to be checked before stat to each shift.
7. Blasted surface shall be de-dusted using dry compressed air free of oil traces
before the application point.
8. Blasted surfaces shall be coated within 4 hours after completion of blasting and
while the surface is at the specified standard.
9. Garnet will be used to obtain the required surface cleanliness and anchor
profile.
10. After the Surface is clean , Painting can be carried out.
11. Handling, preparation and application of paint shall be fully agree with the
manufacturer’s recommendations.
12. Painting shall not be applied when temperature of substrate surface is less that
10 Celsius above the dew point of surrounding air or the relative humidity is
greater than 85%.
13. The paint shall applied uniformly to obtain one even coat. Within the DFT
range, free of runs , sags , overspray , dry spray , wrinkling , mud cracking ,
22
inadequate cure, blisters and with sound adhesion to its substrate or preceding
coat.All runs or sags shall be brushed out immediately
14. Each Coat of paint Shall be allowed to dry for a period of time within the limits
prescribed by paint manufacturer, before over coating. Normally, all Painted
surfaces shall be lightly abraded by emery (sand) paper, prior to over coating.
15. All relevant information and inspection items checked shall duly report in the
blasting and painting report.
16. For ths project there are 2 types of painting system used. System 1A and 5A.
The painting system 1A has 3 coat. the first coat is BARRIER 77 , 2 nd
coat is DURAMASTIC and the 3rd coat is DURATHANE AS . The
needed DFT microns reading must exceed more than 275. The painting
system is for carbon steel with design temperature equal or less than 110
Celsius. The colour for Support and instrument stand using this system
for the project is YELLOW while Pipe Spool using this painting system
is WHITE.
The painting 2nd system is System 5A(1) , it has 2 coat . the first coat is
resist 78 and the second coat is SOLVALIT MIDTHERM. The needed
DFT microns reading must exceed more than 135. The painting system
is for Carbon steel with design temperature above 110 Celsius. The
color of the pipe spool painted using this system is White.
All color of the painting is based on PETRONAS Client Specification.
17. After all the painting is done report of overall work is required. (BLASTING
AND PAINTING REPORT) it is to be inserted in the Manufacturer Data
Record.
The figure show that the
client checks the painting
system using DFT meter and
a trainee observing surface
preparation and painting at
the painting yard.
1. As a QC inspector , we need to compile all the document and data that has been
collect during the fabrication in 1 complete file of Manufacturer Data Record
that will be given to Client 2 weeks after finish of fabrication.
2. All submitted procedure and approved procedure is compulsory and all the
report such as :
Inspection Test Plan (Refer Appendix 11)
Approved Procedure
Material Inspection Report
Mill Certificate
Fit-up inspection report
Dimensional Report
Welding inspection report (Refer Appendix 8)
Welder Certificate (Welder Performance Qualification)
WPS/PQR
Magnetic Particle Testing report
Radiographic Test Report
NDE personnel certificates
ISO Drawing (Piping and Structure)
Weld Map
Hydrostatic test Chart and report (Refer Appendix 4)
Blasting and Painting report (Refer Appendix 11)
Inspection Release Note
3. MDR is important because it show all the progress of the fabrication. It is also
act as reference for Client.
24
PACKING
1. After all the fabrication and painting is finish and already get the approval of
Client representative and the date of the fabrication is almost over , The product
is ready for packing and to be delivered to TERENGGANU and be sent to
OFFSHORE DOCK ANGSI-B.
2. Delivery order and Packing list is made to organize the packing.
3. The product are packed with care so that the quality of the product will remain
intact.
4. Some of the product were put in the box and some are wrapped.
5. After the product is already pack , QC inspector need to entertain Client
representative to witness and make a final inspection on the quality and the
quantity of the product.
6. After Client representative has approved, the product is ready for delivery.
7. The Delivery order needed to get the approval from 3 party that is , the QC
inspector , Client Representative and Logistic Company.
25
Other On Going Job
Instead of Provision of Computer Assisted Operations (CAO) at ANGSI-B , there are also
other On-Going job in Peer Mark Engineering such as :
2. During the work of Provision of gas jet pump application for ANGSI platform,
when the project already delivered , the client found that there’s is a defect on the
weldment (a clear visual defect) . They are furious on how it is pass for
Hydrostatic test n clear of all NDE. But the Pipe is already at the OFFSHORE
platform of ANGSI. So the client company want us to send all the Radiographic
Test Report and all other NDE report via email to them. The problem is later
solved by sending welder to repair at the site (ANGSI) .
26
CHAPTER IV
During this Industrial training as a trainee I have learn so many valuable knowledge that
can be my advantages in the future and become more confident and equipped with
knowledge that are useful in the Oil and Gas industry. As a trainee and student of Unikl
Malaysia France Institute I am also very proud because most of the person I met in the
industry knows well of MFI and there are also some already successful Welding Engineer
and Inspectors started from MFI. As a trainee I learn all about being QC inspector during
my stint in Peer Mark Engineering. They have taught me how to handle a document ,
making visual inspection , read ISO drawing , P&ID , making NDE request, interacting
with client , about the material , about procedure , hydrostatic test, make my own format
of Radiographic Test percentage (failure) per Welder and how important is Radiographic
Test in the world of welding. Being involved in work environment in company, the
trainee had gained experience and a lot of things especially knowledge in manufacturing
but also with other staffs and human operators. Trainee also learned the culture of work
27
through waste identification, elimination, prevention and people will make this happen.
this culture, all jobs can be done systematically . In Peer Mark Engineering , trainee not
only learn about QC , but also Production where they need to interact with all the workers
in workshop and not only inspect the material but also get into production work as well.
Trainee also is involved as SAFETY officer as they also follow SAFETY officer
Engineering gets no special attention as they are also treated the same like any other
employers and can also voice their idea’s. Peer Mark Engineering is an industry leader –
a company that thrives on providing the highest quality products and services to its
customers. The work environment is exciting and fast-paced. Peer Mark have built a
culture that encourages active participation and contribution by all. And it is all about
Team Work.
28
Bibliography
1. Copy right reserved – PME 2006 , About us, http://peer-
mark.com/default.aspx
2. Copy right reserved – Metal One Engineering Sdn. Bhd. , About Metal
One , http://www.metalone-eng.com/
29
APPENDICES
33
Appendix 1 : Peer Mark Engineering Organization Chart
30
Appendix 2 : Radiographic Test report
31
Appendix 3 : Radiographic Test report
32
Appendix 4 : Hydrostatic Test report
33
Appendix 5 : Hydrostatic Inspection Report
34
Appendix 6 : Hydrostatic Test Pressure Sketch
35
Appendix 7 : Example of 1 of the Calibration Certificates
36
Appendix 8 : Welding Inspection Report
37
Appendix 9 : 1 of the Project ISO drawing Provision of Computer Assisted
38
PEER MARK ENGINEERING SDN BHD
Lot 8965 , Jalan Udang Galah, Telok Gong,
42000 Port Klng, Selangor Darul Ehsan. Malaysia Radiographic
Tel: 603-3134 3881 / 603-31343882 Fax : 603-3134 1398 P Test
Magnetic
NDT WORK ORDER JOB NO. : Particle Test
PME/1339/12 Ultrasonic Test
To : PRESCAN SDN. BHD From : Dye-Penetrant
FALIQ Test
Attn : Mr. Vincent / Mr. Jimmy Date : Hardness Test
15/3/12
Please carried out the following testing on: 15/3/12-10.00 p.m
ASME A105N~A1
3. B05-06100-SP2 2" Sch 160 8.74m J1 GTAW W057
B31.3 06 GR. B
m
ASME A105N~A1
5. B14-06232-SP5 2" Sch 160 8.74m J1 GTAW W057
B31.3 06 GR. B
m
39
Appendix 11 : Blasting & Painting report and Inspection And Test Plan of Provision
40
Appendix 12 : Company Certificates
41
Appendix 13 : Company Experience List
42
Illustration
Illustration 1 : Gas Skid of KBB Nothern Hub Project
43
Illustration 2 : Installation of GLNG skid
44
Illustration 3 : Visual Inspection on a Vessel by QC inspector before Hydrostatic
Test
45
Illustration 4 : Preheat before welding for KBB Northern Hub Project
46
Illustration 5 : Inspection of SILO for a Japanese company
47
Illustration 6 : Inspection and finding heat number for every material for Material
and fit-up inspection report for HIJAU GAS OIL Project (Air Tank).
48
Illustration 7 : Hydrostatic test is being carried out for GLNG project
49
Illustration 8 : The delivery of Provision of Computer Assisted Operation at ANGSI-
B to Terengganu
50
Illustration 9 : Removal of surface defect on a stainless steel dish head of its nozzle
weld
51
Illustration 10 : Unpacking the Ball valve for KBB Northern Hub Project
52