Casing doesn't reach bottom Wellhead installation delays Good drilling practices Accept
4,07 Long rate hole R&E Hole cleanning program 8% 4 6 9 A
Casing circulation aviability
Improper Cementing job Cement no reaching surface Hydraulic program Accept Prepare a top job
Require a Top job cement. Cement design -Inner string job contingency plan
4,08 Lack of Integrity shoe R&E 12% 5 6 10 A
Too much cement to surface.
Cellar leak Rig settling Facilities design Accept
Spill Start with low drilling parameters
4,09 Wellhead installation problems R&E 5% 4 5 8 A
Delays
Improper wellhead installation Delays SOP (Level tool in place) Accept
4,10 Bad seal R&E Wellhead design 10% 4 5 8 A
BOP installation issues Wellhead test
BOP test failure Delays BOP inspection Accept
4,11 Well control problems R&E BOP installation program SOP 5% 4 6 9 A