ANALISIS DE PRECIOS UNITARIOS

ES EL ANÁLISIS QUE SE REALIZA PARA CALCULAR LOS RECURSOS QUE NECESITO PARA UNA PARTIDA.
LOS RECURSOS SON:
MANO DE OBRA:
- SE CALCULA POR HH, Y SE CONSIDERA TRABAJOS DE 8 HRS DIARIAS
- SE CATEGORIZA POR: CA, OP, OF Y AY.
- SU PRECIO UNITARIO DEBE ESTAR INCLUIDO TODOS LOS BENEFICIOS SOCIALES.
MATERIALES
- EL APORTE UNITARIO DEPENDE DE LAS UNIDADES DE LA PARTIDA QUE SE ANALIZA.
- EL PRECIO UNITARIO DEBE ESTA SIN EL IGV.
- SE CONSIDERA EL DESPERDICIO DE TODOS LOS MATERIALES QUE SE NECESITEN
EQUIPOS Y HERRAMIENTAS
- LOS EQUIPOS SE CALCULAN POR HM.
- LAS HERRAMIENTAS MANUALES SE CALCULA COMO % DE LA MANO DE OBRA

UNA CUADRILLA ES UN GRUPO DE PERSONAS QUE REALIZAN UN MISMO TRABAJO


EL RENDIMIENTO ES LA CANTIDAD DE TRABAJO QUE DEBERÍAN HACER EN 1 DIA (TEÓRICO)

LA CANTIDAD DE TRABAJO ES (C): C= CUADRILLA x HORAS TRABAJADAS


RENDIMIENTO
BAJADAS
ANALISIS DE PRECIOS UNITARIOS
PARTIDA: Asentado de ladrillo kk 18H - Soga COSTO S/. 60.14
RENDIMIENTO: 8 M2/DIA
RECURSO UND CUADRILLA CANTIDAD PRECIO TOTAL
MANO DE OBRA
CAPATAZ HH 0.10 0.1000 S/. 21.00 S/. 2.10
OPERARIO HH 1.00 1.0000 S/. 19.00 S/. 19.00
AYUDANTE HH 0.50 0.5000 S/. 16.00 S/. 8.00
S/. 29.10
MATERIAL
LADRILLO KK18H UND - 38.00 S/. 0.65 S/. 24.70
CEMENTO BLS - 0.20 S/. 20.00 S/. 4.00
ARENA GRUESA M3 - 0.022 S/. 40.00 S/. 0.88
S/. 29.58
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANU %MO 0.05 S/. 29.10 S/. 1.46
S/. 1.46

PARTIDA: Acero corrugado f'y=4200 COSTO S/. 4.85


RENDIMIENTO: 240 KG/DIA
RECURSO UND CUADRILLA CANTIDAD PRECIO TOTAL
MANO DE OBRA
CAPATAZ HH 0.10 0.0033 S/. 21.00 S/. 0.07
OPERARIO HH 1.00 0.0333 S/. 19.00 S/. 0.63
AYUDANTE HH 0.50 0.0167 S/. 16.00 S/. 0.27
S/. 0.97
MATERIAL
ACERO CORRUGADO KG - 1.05 S/. 2.48 S/. 2.60
ALAMBRE KG - 0.200 S/. 5.10 S/. 1.02
S/. 3.62
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANU %MO 0.05 S/. 0.97 S/. 0.05
TRONZADORA HM 1 0.0333 S/. 6.25 S/. 0.21
S/. 0.26

PARTIDA: Tarrajeo en interiores COSTO S/. 26.58


RENDIMIENTO: 15 M2/DIA
RECURSO UND CUADRILLA CANTIDAD PRECIO TOTAL
MANO DE OBRA
CAPATAZ HH 0.10 0.0533 S/. 21.00 S/. 1.12
OPERARIO HH 1.00 0.5333 S/. 19.00 S/. 10.13
AYUDANTE HH 1.00 0.5333 S/. 16.00 S/. 8.53
S/. 19.79
MATERIAL
CEMENTO BLS - 0.24 S/. 20.00 S/. 4.80
ARENA FINA M3 - 0.025 S/. 40.00 S/. 1.00
S/. 5.80
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANU %MO 0.05 S/. 19.79 S/. 0.99
S/. 0.99

PARTIDA: Concreto f'c = 210 Kg/cm2 COSTO S/. 354.60


RENDIMIENTO: 12 M3/DIA
RECURSO UND CUADRILLA CANTIDAD PRECIO TOTAL
MANO DE OBRA
CAPATAZ HH 0.10 0.0667 S/. 21.00 S/. 1.40
OPERARIO HH 3.00 2.0000 S/. 19.00 S/. 38.00
AYUDANTE HH 5.00 3.3333 S/. 16.00 S/. 53.33
S/. 92.73
MATERIAL
CEMENTO BLS - 9.30 S/. 20.00 S/. 186.00
ARENA GRUESA M3 - 0.65 S/. 40.00 S/. 26.00
PIEDRA CH. M3 - 0.60 S/. 60.00 S/. 36.00
AGUA M3 - 0.180 S/. 5.00 S/. 0.90
S/. 248.90
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANU %MO 0.05 S/. 92.73 S/. 4.64
MEZCLADORA HM 1 0.6667 S/. 12.50 S/. 8.33
S/. 12.97

PARTIDA: Salida de tomacorrientes COSTO S/. 46.12


RENDIMIENTO: 6 PTO/DIA
RECURSO UND CUADRILLA CANTIDAD PRECIO TOTAL
MANO DE OBRA
CAPATAZ HH 0.10 0.1333 S/. 21.00 S/. 2.80
OPERARIO HH 1.00 1.3333 S/. 19.00 S/. 25.33
AYUDANTE HH 0.50 0.6667 S/. 16.00 S/. 10.67
S/. 38.80
MATERIAL
CAJA RECTANGULAR UND - 1.00 S/. 1.50 S/. 1.50
CEMENTO BLS - 0.02 S/. 20.00 S/. 0.40
CONECTORES UND - 3.00 S/. 0.50 S/. 1.50
CURVA 1/2" UND - 2.00 S/. 0.80 S/. 1.60
PEGAMENTO 1/16 GAL GLN - 0.015 S/. 25.00 S/. 0.38
S/. 5.38
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANU %MO 0.05 S/. 38.80 S/. 1.94
S/. 1.94