Sunteți pe pagina 1din 6

Abstract Sheet

ABSTRACT SHEET

Name of Work :- Construction of proposed subway at chainage 68.170 Camran Sanvordem

Railway Span (Box)

Item
Code Ref. SOR Description Unit Qty. Rate Amount
No.
Earthwork in excavation of foundation of structures of culvert abutments, piers,
retaining walls, drains etc.as per drawing and technical specification, including
GSR 2014 State
setting out construction of shoring and bracing removal of stumps and other
2.01 Sector -
deleterious matter, dressing of sides and bottom, back filling the excavation earth
Corrigendum - I
to the extent required and utilising the remaning earth locally for road work as per
MORTH Specification 304. - upto 3 m depth (including dewatering)
item no. 4129 in Ordinary Soil (all types of soil) - By meachnical Means Cum 1044.00 31.00 32364.00

Extra for mechanical compaction of earth/blanketing material filled in


embankment with contractor’s rollers of suitable capacity, type and size to
achieve specified density as per specification, testing as per IS codes incl. cost of
2.02 SSR No 013130 Sqm 166.00 11.37 1887.42
water, T&P consumable material and all labour as a complete job. The work is to
be executed as per Latest edition of "Guidelines for Earthwork in Railway
Projects" issued by RDSO, Lucknow

GSR 2014
2.03 Highway sector Sand Filling in Foundation Trenches as per Drawing & Technical Specification Cum 17.00 1989.00 33813.00
11.3

M/s. TECHNOGEM CONSULTANTS PVT. LTD. ARS-1


Abstract Sheet

Item
Code Ref. SOR Description Unit Qty. Rate Amount
No.
Providing, hoisting and fixing in position upto floor two level M25 Grade precast
RCC work including setting in cement mortar 1:3 (1 cement : 3 coarse sand) and
finishing smooth with 6mm thick cement plaster 1:3 (1 cement : 3 fine sand) on
exposed surfaces complete including cost of centering, shuttering, finishing,
Admixtures in recommended proportion (as per IS:9103) to accelerate, retard
setting of concrete, improve workability without impairing strength and durability,
SSR No excluding cost of cement and steel reinforcement, as per approved plan &
2.04 Rmt 27.00 2876.41 77663.07
043010 - 11 direction of Engineer incharge.- In string courses, bands, coping, bed plates,
anchor blocks, plain window sills, and the like
Note:- (i) As per General Instruction No. 1.5 - " Design Mix cement concrete of all
grades from M-15 to M-40 will be paid at same rate irrespective of grade mention
in the item. (Hence M-25 operated insted of M-20; duly op-erating the cement
coefficient of M-25 i.e. 4.34 or as per design mix.)
(ii) This item should be used for RCC Base Slab.

Providing and laying in position machine mixed, machine vibrated and machine
batched Design Mix Cement Concrete M35 grade (Cast - in Situ) In Bottom/top
slab, side walls, toe wall and sumps haunch filling head walls or any other
component using 20 mm graded crushed stone aggregate and coarse sand of
approved quality of cast-in-situ RCC box of size upto 5 M (bigger inside
2.05 SSR No 194010 Rmt 114.00 1977.04 225382.56
dimension) including finishing, Admixtures in recommended proportions (as per IS
9103), if approved in Mix design, to accelerate, retard setting of concrete, improve
workability without impairing strength and durability, complete as per drawings
and technical specifications as directed by Engineer in charge. Payment for
cement, reinforcement and shuttering shall be paid extra.

SSR No
2.06 Supply and using cement at worksite :OPC 43 grade MT 48.00 6818.00 327264.00
033060 - 61

M/s. TECHNOGEM CONSULTANTS PVT. LTD. ARS-2


Abstract Sheet

Item
Code Ref. SOR Description Unit Qty. Rate Amount
No.

Supplying Reinforcement for R.C.C. work including straightening, cutting,


SSR No
2.07 bending, placing in position and binding all complete. High yield strength MT 28.00 65728.00 1840384.00
045010 - 14
deformed bars

MCGM Providing Fusion Bonded Epoxy Coating (FBEC) to reinforcing steel bars as
BRIDGE SOR per IS 13620: 1993 specifications for a coating thickness of 175 microns ( with
2.08 MT 28.00 13365.00 374220.00
2013 - Item No.- permissible variation of 50 microns) including testing at plant etc. complete as per
BW-5-8 specifications.

Providing and laying of Filter media with granular materials/stone crushed


aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
GSR 2014
specifications to a thickness of not less than 600 mm with smaller size towards
2.09 Highway sector Cum 72.00 1572.00 113184.00
the soil and bigger size towards the wall and provided over the entire surface
Item no. 12.1
behind abutment, wing wall and return wall to the full height compacted to a
firm condition complete as per drawing and technical specification.

Providing and applying two coats of coal tar or bitumen confirming to IS 3117 -
SSR No
2.10 1965 on the top and sides of RCC box/slabs @ 1.70 Kgs / Sqm after cleaning the Sqm 270.00 77.76 20995.20
195020
surface with all labour and materials complete job as directed by the Engineer

Centring and shuttering including strutting, propping etc. and removal of form for :
SSR No
2.11 In Bottom/top slab, side walls, toe wall and sumps haunch filling head walls or any Sqm 516.00 233.50 120486
195030 - 38
other component

M/s. TECHNOGEM CONSULTANTS PVT. LTD. ARS-3


Abstract Sheet

Item
Code Ref. SOR Description Unit Qty. Rate Amount
No.
Providing and placing at required place, filled up gunny bags with earth / stone
dust for the retaintion and protection of embankment or for any other purpose at
locations other the track, with all contractors materials, labours , tools & plants etc.
complete.
2.12 NS Each 5000.00 14.80 74000
Note:- Empty bags (of 50kg cement) should be filled up to 75% of its capacity and
tied up with binding wire.
Ref:- Accepted Lt. No. H / W.148 / II / 29 / 2014 / 01 / WEST / W5 of dated 26-05-
2014

Removal and replacing the filled up gunny bags with earth / stone dust from the
site after completion of the work with all contractors materials, labours , tools &
2.13 NS plants etc. complete. Each 5000.00 8.07 40350
Ref:- Accepted Lt. No. H / W.148 / II / 29 / 2014 / 01 / WEST / W5 of dated 26-05-
2014

Construction of embankement with approved material obtained from borrowpits


GSR 2014
with all lifts and leads, transporting to site, spreading, grading to required slope
2.14 State Sector Cum 474.00 521.00 246954
and compacting with vibratory roller to meet requirement of Table 300-2 as per
14505
MORTH specification 305.

M/s. TECHNOGEM CONSULTANTS PVT. LTD. ARS-4


Abstract Sheet

Item
Code Ref. SOR Description Unit Qty. Rate Amount
No.
Providing lighting arrangement at works site during nite hours for carring out
various works on track and other specified locations with contractors generators
and lighting equipments including fuel , carriage, labour etc. Complete. The
lighting shall be of total intensity of 42000 lumens which shall be generally Per Shift
2.15 NS provided with 4 Halogen lights of Per 6.00 1585.08 9510.48
500 W each or as approved by Engineer-in-charge. The rates shall be for Generator
10Hours shift to be decided by Engineer-in-charge.
Ref:- Accepted Lt. No. H / W.148 / II / 29 / 2014 / 01 / WEST / W5 of dated 26-05-
2014

Placement of precast RCC segmental box with the help of road crane as desired
location carefully by pulling method during traffic and power block with all
contractors labours tools & materils preparedness of surface as directed by
2.16 NS engineer including inserting 32 dia. rods 1200 mm long in holes filing of joints by MT 353.00 2769.66 977689.98
epoxy mortar and laying of required sand including cost of epoxy and sand.
Ref:- Accepted Lt. No. H / W.148 / II / 29 / 2014 / 01 / WEST / W5 of dated 26-05-
2014

Sealing the joints of Pre cast RCC box units after placing it in to the correct
position, with cement mortar 1 : 2 Mix with Contractor's Cement of Approved
quality including labours,tool & plants , loading , unloading , lead & lift etc
2.17 NS Rmt 184.00 140.09 25776.56
complete as per the direction of the Engineer - in - charge.
Ref:- Accepted Lt. No. H / W.148 / II / 29 / 2014 / 01 / WEST / W5 of dated 26-05-
2014

M/s. TECHNOGEM CONSULTANTS PVT. LTD. ARS-5


Abstract Sheet

Item
Code Ref. SOR Description Unit Qty. Rate Amount
No.

GSR 2014 Providing and fixing weepholes with rigid PVC make laid in position with a
2.18 State Sector required slope and level while layingpipes of approved the concrete of retaining
Item No. wall,wing wall and earth retainig structure complete as directed by the Engineer
in charge.
A) 110 mm dia Rmt 45.00 360.00 16200

GSR 2014 Painting on concrete surface (Providing and applying 2 coats of water based
2.18 Highway Sector cement paint to unplastered concrete surface after cleaning the surface of dirt, Sqm 153.00 147.00 22491
Item Code 13.6 dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m.)
Total Cost Rs. 4580615

i.e. Total Cost in Cr. 0.46

M/s. TECHNOGEM CONSULTANTS PVT. LTD. ARS-6

S-ar putea să vă placă și