Sunteți pe pagina 1din 9

IET Generation, Transmission & Distribution

Research Article

Optimal coordination of directional ISSN 1751-8687


Received on 14th June 2017
Revised 27th September 2017
overcurrent relays using improved Accepted on 26th January 2018
E-First on 12th March 2018
mathematical formulation doi: 10.1049/iet-gtd.2017.0945
www.ietdl.org

Vipul N. Rajput1 , Farhad Adelnia2, Kartik S. Pandya1


1Department of Electrical Engineering, Charotar University of Science and Technology, Changa, Gujarat, India
2Faculty of Electrical and Computer Engineering, Semnan University, Semnan 3519645399, Iran
E-mail: vipulrajput16986@gmail.com

Abstract: Achieving optimum coordination of directional overcurrent relays is a very complicated task in the large
interconnected system including huge numbers of relays. In the literature, various objective functions (OFs) are reported to
obtain minimum operating time of relays and minimum prescribed discrimination time between the operations of primary and
backup (P/B) relays. In this paper, the performance of five well-established OFs is examined, and in addition, a new OF is
proposed to improve the previously proposed OFs. The proposed OF (POF) minimises operating time of P/B relays together
with discrimination time between their operations. Also, the coordination problem is formulated considering near and far-end
faults and solved by using a genetic algorithm. In order to evaluate the effectiveness, the POF is implemented over the IEEE 14-
bus and IEEE 30-bus distribution networks, and obtained results are compared with those obtained by using previously
proposed OFs presented in the literature.

1 Introduction algorithm [14], ant colony algorithm [5], teaching learning-based


optimisation [15], harmony search algorithm [3] etc. To improve
Directional overcurrent relays (DOCRs) are widely used as a the computational efficiency, the hybrid methods are also utilised
primary protection in sub-transmission and distribution networks, to solve the coordination problem of DOCRs, including GA-LP
as well as a backup protection of distance relays in transmission [1], GA-NLP [2], biogeography-based optimisation algorithm-LP
networks [1]. The DOCRs can be required to obtain the fault zone [16], and PSO-gravitational search algorithm [17].
discrimination in multi-looped, parallel feeder, double-end fed, and Now, owing to the availability of numerous entrenched
ring main systems. The coordination of DOCRs is the process of optimisation methods, it is a natural curiosity to step ahead for
selecting the suitable relay settings, namely plug setting (PS) and finding some other approaches for effective solution of optimal
time multiplier setting (TMS), in such a way that the primary relay coordination of DOCRs. In this regard, some authors point towards
responds faster than any other relays of the system. In case of the the modification in the problem formulation of relay coordination.
failure of primary relay or associated circuit breaker, backup relays The most commonly utilised OF is the minimisation of weighted
have to operate after a prescribed time interval, ensuring the correct sum of the operating time of primary relays [1, 2]. However, in a
sequential operation of P/B relay pairs [2]. The perfect relay larger interconnected system with huge numbers of relays and
coordination can reduce the chances of equipment damage and coordination constraints, the aforesaid method sometime leads to
improve the electrical power service to the consumers by isolating the larger discrimination time between P/B relay pairs. This is
the least possible part of the system [3]. On the other hand, the because the coordination constraints are not incorporated directly
overall relay coordination is a very complicated task, because a in the OF. To reduce the discrimination time, the coordination
relay works as the primary relay for its primary protection zone and constraints are integrated as a part of the OF [7]. However, this
the same relay may serve as a backup of some other primary relays method endures the problem of mis-coordination of P/B relay
in the system. Even though the safeguards are taken for designing pairs. In [8, 9], the problem of mis-coordination associated with the
and setting of DOCRs-based protection scheme, mis-coordination previous method has been improved by adding a new term in the
may occur in the operation of P/B relay pairs. Therefore, the use of OF. Nevertheless, these methods have problems of large operating
efficient approaches is essential for the accurate coordination of time of primary and backup (P/B) relays. To overcome the
relays. mentioned problem, a new OF is developed in [10, 11], which
One of the most popular approaches in the literature is to find integrates operating times of both P/B relays with coordination
the optimal relay settings by using optimisation methods. Over the constraints. By adding this new term, the improved solutions have
past decades, several optimisation methods have been used to solve been obtained, but still the problem of mis-coordination is
the coordination problem. For the first time in 1988, the subsisted.
coordination of DOCRs is presented in the frame of the In this paper, in order to obtain the optimal relay coordination, a
optimisation problem and solved by the linear programming (LP) novel OF based on GA is proposed to improve the earlier presented
method [4]. Afterwards, LP methods have gained good recognition OFs. The main contribution of the proposed method is to reduce
to solve this problem due to their simplicity [5]. Owing to fixed operating time of relays with preserving the discrimination time at
value assumed for PS in LP techniques, the obtained solution may a minimum prescribed value. In other words, the proposed method
float away from optimal state. To optimise both PS and TMS minimises the operating time of primary relays and maximises the
simultaneously, the coordination problem is formulated as a non- operating time of backup relays in case of mis-coordination. In
linear programming (NLP) problem, and is solved by using the addition, the proposed method minimises operating time of backup
sequential quadratic programming method [6]. Subsequently, relays in case of larger discrimination time between P/B relay
heuristic methods have become a tool to solve the relay pairs. In this way, the proposed method eliminates the problem of
coordination problem in the last few years. These methods include mis-coordination, and simultaneously reduces the operating time of
genetic algorithm (GA) [7–11], particle swarm optimisation (PSO) relays by achieving the prescribed coordination between P/B relay
[12], seeker algorithm [13], enhanced backtracking search pairs. Furthermore, if the relay coordination problem is solved by

IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094 2086
© The Institution of Engineering and Technology 2018
Δti, j(F1) = t j(F1) − ti(F1) − CTI (5)

Δti, j(F2) = t j(F2) − ti(F2) − CTI (6)

where Δti,j(F1) and Δti,j(F2) are discrimination time which present


the time difference with CTI between the operations of P/B relays
for near and far-end faults, respectively. It can be clearly seen from
(3) to (6) that the negative value of Δt shows the mis-coordination
which results in the infeasible solution. Similarly, the solution of
Fig. 1  Illustrative diagram of P/B relays for near and far-end faults (F1 relay coordination can be said feasible for the positive value of Δt,
and F2) and optimal solution can be achieved under zero value of Δt.

considering only near-end faults, there will be chances of violation 2.2 Bounds on TMS
in the coordination constraints based on far-end faults [6]. To avoid
this problem, the effects of both near and far-end faults are The TMS regulates the time delay before the relay operates when
considered in the coordination problem. the current attains a value equal to or more than pickup current
setting [3]. The boundary constraints on TMS can be stated as
2 Problem formulation TMSi, min ≤ TMSi ≤ TMSi, max (7)
For the optimum coordination of DOCRs, the most common OF
utilised in the literature is the minimisation of the total operating where TMSi,min and TMSi,max are the minimum and maximum
time of the primary relays [1, 2]. It is expressed as follows: value of TMS of relay Ri, which are provided by relay
manufacturer.
m
OF1 = ∑ witi (1)
2.3 Bounds on PS
i=1

The bounds on PS of the relay can be stated as


where ti indicates operating time of relay Ri for fault in its primary
protection zone, m is the number of primary relays, and wi is the PSi, min ≤ PSi ≤ PSi, max (8)
weight coefficient representing the operating time of relay Ri. The
value of wi is generally set to one [2]. Moreover, the non-linear and where PSi,min and PSi,max are the minimum and maximum values
well-known standard inverse definite minimum time characteristic of PS of relay Ri.
curve based on IEC-60255-3 standard [2] has been considered in To make sure that the relay does not malfunction under normal
this paper. It is defined as load or small amount of overload condition, the minimum pickup
current setting should be equal to or more than 1.25 times of the
0.14 × TMSi maximum load current. Similarly, maximum pickup setting should
ti = 0.02 (2)
Ic, i /PSi −1 be less than or equal to 2/3 times of the minimum fault current, to
make sure that the relay is sensitive to the smallest fault current [1–
where TMSi and PSi are the TMS and PS of relay Ri, respectively, 3].
and Ic,i is the fault current passing through the operating coil of
relay Ri. 2.4 Bounds on operating time of relay
The constraints subjected to the feasible solution of relay Any relay in the system needs certain minimum amount of
coordination can be defined as follows. operating time, also it cannot be allowed to take more time for the
operation [2]. The constraints related to the boundaries on
2.1 Coordination constraints operating time of relay can be stated as
In overcurrent protection scheme, the primary relay must have ti, min ≤ ti ≤ ti, max (9)
sufficient chance to protect its zone. In case of failure of primary
relays, corresponding backup relay(s) have to trip after the
operating time of primary relay plus coordination time interval where ti,min and ti,max are the minimum and maximum operating
(CTI) [16]. These sequential operations of P/B relay pair should time of Ri.
satisfy the coordination criteria for preventing the mis-coordination In the coordination problem of DOCRs, objective function
of relays. (OF), coordination constraints and operating time constraints
As seen in Fig. 1, the coordination constraints between primary become non-linear due to the non-linear characteristic of relay.
relay Ri and corresponding backup relay(s) Rj can be written for Therefore, the coordination problem is referred as complex and
near and far-end faults as follows: non-linear optimisation problem and solved by considering large
numbers of linear and non-linear constraints. To find the feasible
t j(F1) − ti(F1) ≥ CTI (3) solution for satisfying these constraints, evolution for the OF
should be well designed.
t j(F2) − ti(F2) ≥ CTI (4)
3 Problem statement
where tj(F1) and ti(F1) are the operating time of backup relay Rj In this section, various well-established OFs presented in literature
and primary relay Ri, respectively, for near-end faults, whereas are described. The most common OF expressed by (1) minimises
tj(F2) and ti(F2) are the operating time of backup relay Rj and the operating time of only primary relays. Since the coordination
primary relay Ri, respectively, for far-end faults. The CTI depends constraints are not directly incorporated in this OF, possibility of
upon the types of relays, operating time of circuit breaker, relay the larger discrimination time, and hence the larger operating time
error and safety margin. Typically, the CTI is selected between 0.3 of backup relays are increased. To minimise the operating time of
and 0.5 s for electromechanical relays, whereas it is considered relays along with the discrimination time, different OFs are
between 0.1 and 0.2 s in microprocessor-based relays [12, 18]. developed in the literature.
The coordination constraints can be rewritten in terms of
discrimination time as

IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094 2087
© The Institution of Engineering and Technology 2018
precisely, it should be cleared that the operating time of P/B relays
is lower in case 2, and therefore, case 2 has to be selected.

3.3 OF4
The more simplified version of OF3 is proposed in [9]. It is
expressed as
Fig. 2  Sample network
m n
3.1 OF2 OF4 = α1 ∑ ti2 + β3 ∑ Δtpbk − Δtpbk
2
(13)
i=1 k=1
In [7], OF1 is modified to reduce the discrimination time between
the P/B relay pairs along with operating time of primary relay. It is
defined as where β3 is considered equal to α2β22 of OF3, because only part of
second term of OF3 is removed.
m n For the positive value of Δt, OF4 functions same as OF1 and
OF2 = α1 ∑ ti2 + α2 ∑ Δtpbk
2
(10) the similar difficulties of higher discrimination time and higher
i=1 k=1 operating time of backup relays are existing as explained in
following two cases:
Δtpbk = tbk − tpk − CTI (11)
α1 = 1, β3 = 2, CTI = 0.2.
where Δtpbk is the discrimination time between kth P/B relay pairs, Case 1: Δtpb = 1.0, tp = 0.2, tb = 1.4, OF4 = 0.04.
n is number of P/B relay pairs, and k represents each P/B relay Case 2: Δtpb = 0.6, tp = 0.2, tb = 1.0, OF4 = 0.04.
pairs which varies from 1 to n. tpk and tbk are the operating time of
P/B relays, respectively. α1 and α2 are the positive weight factors to In both cases, the same value for OF4 is found by using (13).
control the first and second terms of OF2. As it is obvious from the results of case 1 and case 2, the
The problem associated with the OF2 is explained using the discrimination time and operating time of backup relay are lower in
part of an interconnected system having the primary relay Rp and case 2. Therefore, case 2 must be selected by the algorithm. From
backup relay Rb as shown in Fig. 2. The following two cases are the results of above cases, it can be said that the OF4 does not have
assumed to describe the difficulty with OF2. In all the cases, the any sensitivity to positive Δt.
value of α1 and α2 is considered to be 1, whereas the value of CTI
is taken 0.2 s. 3.4 OF5
Although the mis-coordination problem has been overcome in OF3
Case 1: Δtpb = − 0.15, tp = 0.15, tb = 0.20, OF2 = 0.045.
and OF4, the difficulties of larger operating time of backup relays
Case 2: Δtpb = 0.20, tp = 0.15, tb = 0.55, OF2 = 0.0625. and higher discrimination time are still existing. To overcome this
dilemma associated with OF3 and OF4, the authors in [10, 11]
As explained by (5) and (6), because of the negative value of presented a new OF by adding the new terms. It is expressed as
Δtpb, case 1 presents mis-coordination, whereas case 2 is a feasible
case. However, the value of OF2 is lower in case 1 than case 2, and m n
thus, the algorithm selects case 1 as a more optimum solution. On OF5 = α1 ∑ ti2 + α2 ∑ |Δtpbk − | Δtpbk | | ⋅ tpk
2
+ Δtpbk
the other hand, by accurate considerations, case 2 must be chosen. i=1 k=1 (14)
2
+ | Δtpbk| ⋅ tbk .
3.2 OF3
In (14), if Δtpbk is supposed to be a positive value, the second term
To overcome the mentioned difficulty with OF2, Razavi et al.
proposed new formulation for the OF [8]. It can be stated as of OF5 will be (2Δtpbk·tbk2). Similarly, for the negative value of
Δtpbk, second term of OF5 will be (2Δtpbk·tpk2). According to (5)
m n
and (6), the higher positive value of Δtpbk shows larger value of
OF3 = α1 ∑ ti2 + α2 ∑ Δtpbk − β2 Δtpbk − Δtpbk
2
(12)
i=1 k=1
operating time of backup relay (tbk), and OF5 tries to minimise the
operating time of tbk. Same way, the negative value of Δtpbk shows
where β2 is used to consider mis-coordination. As can be seen from larger value of operating time of primary relay (tpk), and OF5 tries
(12), for positive value of Δtpbk, second term of OF3 becomes to minimise the operating time of tpk. Thus, OF5 minimises the
(Δtpbk)2. For the negative value of Δtpbk, it is (Δtpbk(2β2 − 1))2. operating time of P/B relays according to Δtpbk.
Clearly for the positive value of β2, value of the OF3 will be In the OF5, the negative effect of larger operating time of
greater in the case of negative Δt. Therefore, the chromosome backup relays and larger discrimination time have been resolved.
related to mis-coordination which produces the large value of the However, the mentioned problem in OF2 is still existing. It is
OF3 will not be selected. Also, based on evaluation and selection explained by the same cases considered in OF2.
process of GA, the chromosomes with less value of Δt must have
more chances to survive. α1 = 1, α2 = 10, CTI = 0.2.
Although the problem of mis-coordination is resolved by OF3, Case 1: Δtpb = −0.15, tp = 0.15, tb = 0.2, OF5 = 0.09.
the higher operating time of P/B relays are still existing. To clarify Case 2: Δtpb = 0.20, tp = 0.15, tb = 0.55, OF5 = 1.2325.
this problem, following two cases, among many other, of
chromosomes being processed, are considered: As previously discussed in OF2, case 2 is better than case 1.
However, in the OF5, algorithm selects case 1 as a better solution.
α1 = 1, α2 = 2, β2 = 100, CTI = 0.2.
Case 1: Δtpb = 0.5, tp = 0.4, tb = 1.1, OF3 = 0.66. 4 New method
Case 2: Δtpb = 0.6, tp = 0.2, tb = 1.0, OF3 = 0.76.
As obvious from previous discussion, each OF suffered from mis-
coordination or larger operating time of relays. In this paper, the
Owing to the lower value of OF3 in case 1, algorithm selects POF is developed to overcome these difficulties. The POF is
case 1 as more optimum solution than case 2. By observing expressed as

2088 IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094
© The Institution of Engineering and Technology 2018
Fig. 5  Single-line diagram of IEEE 14-bus modified distribution network

variable is generated randomly which obeys the normal


distribution. G represents the generation counter and is initially set
to 1. Afterwards, the procedure of the remaining sections of the
program is performed. Then, the value of G is increased by one and
procedure is repeated. When the value of G reaches to the
generation size, the process will be terminated. In the next step, the
evaluation of the POF is carried out for each chromosome in the
current generation. The chromosome with higher value of POF is
automatically ignored in the next generation. After sorting of
Fig. 3  Flow diagram of the proposed method chromosome according to their fitness value, the best ones are
granted for the new population in the next generation. In the next
step, basic operations of natural genetic operators (i.e. crossover
and mutation) are implemented to the pairs of chromosomes. I is
the population counter and is counted until the population size. The
process will be terminated after the fixed numbers of generations,
Fig. 4  Structure of chromosome in GA for n relays
and the best results of PS and TMS at the last part of the
m n 2
programme will be displayed.
tpk
POF = α1 ∑ ti2 + α2 ∑ |Δtpbk − | Δtpbk | | ⋅ 2
i=1 k=1 tbk (15) 5 Test results
2
+ Δtpbk+|Δtpbk| ⋅ tbk . The proposed method described in Section 4 is evaluated by using
the IEEE 14-bus and IEEE 30-bus modified distribution networks.
As can be seen from (15), second term of OF5 will be For better realisation of the solution, the effects of both near and
(2Δtpbk·tpk2/tbk2) for the negative value of Δtpbk. On the other hand, far-end faults are considered in the problem formulation of relay
POF works similar to OF5 for the positive value of Δtpbk. coordination. To investigate the performance of proposed method,
As clearly seen in (14), the OF5 minimises the operating time obtained results are compared with the previous methods expressed
of primary relays in case of mis-coordination (Δtpbk < 0). It is noted by OF1 to OF5.
that the negative value of Δtpbk shows greater operating time of
5.1 IEEE 14-bus modified distribution network
primary relays and lesser operating time of backup relays. As OF5
only minimises the operating time of primary relays, the mis- The single-line diagram of a modified distribution network of IEEE
coordination problem may not be resolved. On the other hand, POF 14-bus system is shown in Fig. 5. This meshed distribution
minimises the operating time of primary relays, and at the same network is supplied through two distribution transformers with
time, maximises the operating time of backup relays in case of mis- 10% transient reactance connected at buses B1 and B2. The system
coordination. Hence, the POF completely resolves the problem of has a total of 16 DOCRs installed at each end of the line. The
mis-coordination between the operations of P/B relays. Similar to system data are given in [19, 20]. Based on the system, DGs are
OF5, the POF minimises the operating time of backup relays for assumed to be connected at buses B5 and B7. The selected DGs are
larger positive value of Δtpbk. This characteristic of POF minimises synchronous type with a rating of 5 MVA, operating nominally at
the operating time of relays along with maintaining the 0.9 lagging power factor [20]. The ratio of current transformers of
discrimination time at prescribed level. relays (1, 2, 3, 5, 7, 8, 9, 10), (11, 12, 15, 16) and (4, 6, 13, 14) is
The flow diagram of this GA-based new method is shown in assumed to be 120:1, 80:1 and 40:1, respectively. The information
Fig. 3. After entering the data, the P/B relay matrix is computed. In of P/B relay pairs and fault current passing through them for near
the next step, P/B relay fault currents for near and far-end faults are and far-end faults are given in Table 1. It should be noted that, for
calculated. As previously mentioned, if the relay coordination far-end fault to primary relays 3, 5 and 6, the fault current passing
problem is solved by considering only near-end faults, some through corresponding backup relays 6, 4 and 13 is lower than their
coordination constraints based on far-end faults are not satisfied. pickup current, so these P/B relay pairs are ignored for far-end
Therefore, the coordination problem is formulated by considering faults. The OF1 to OF5 are earlier OFs presented in the literature,
both near and far-end faults in this method. After the input of the whereas POF is the proposed new method of the paper. The values
data and GA parameters, the chromosome is defined in the form of of weight factors corresponding to each OF are tabulated in
the genetic string which includes decision variables, namely, TMS Table 2, which are considered as given in the respective literature.
and PS for each relay. Fig. 4 shows the structure of chromosomes All OFs are applied to solve the coordination problem using GA on
when the network consists n overcurrent relays. In the GA, group IEEE 14-bus distribution system. The GA parameters are
of chromosomes known as population are randomly selected, considered as the number of generation = 4000, population size = 
including two sections for each chromosome [1, 11]. Also, each 100, crossover rate = 0.95 and mutation rate = 0.01. All the relays

IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094 2089
© The Institution of Engineering and Technology 2018
Table 1 3-Φ short circuit results of near and far-end faults for IEEE 14-bus network
Primary relay (PR) Backup relay (BR) Near-end fault Far-end fault
PR BR PR BR
1 4 4952 404 2804 173
1 6 4952 928 2804 221
2 11 2318 2318 1426 1426
3 2 5968 1420 2280 822
3 6 5968 928 — —
4 14 2140 1777 407 66
5 2 5444 1420 2989 823
5 4 5444 404 — —
6 13 2294 924 — —
6 16 2294 1370 924 994
7 10 4770 1150 3689 729
8 12 1820 1820 1454 1454
9 8 5070 1470 2463 393
10 15 2147 1784 1151 857
11 7 3689 3689 2318 2318
12 1 2804 2804 1740 1740
13 3 2683 2320 924 614
14 5 4370 2989 1799 902
14 16 4370 1370 1799 897
15 5 3913 2989 1784 1340
15 13 3913 924 1784 444
16 9 2826 2463 1365 1107

Table 2 Weight factors for different OFs


Weight factor OF2 [7] OF3 [8] OF4 [9] OF5 [10, 11] POF
α1 1 1 1 1 1
α2 1 2 — 10 1
β2 — 100 — — —
β3 — — 20,000 — —

Table 3 Minimum and maximum limits of PS for IEEE 14-bus network


Relay no. PSmin PSmax Relay no. PSmin PSmax
1 0.70 2.50 9 0.90 2.50
2 0.50 2.50 10 0.80 2.50
3 0.50 2.50 11 0.62 2.50
4 0.57 2.50 12 0.60 2.50
5 0.98 2.50 13 0.57 2.50
6 0.50 2.50 14 0.50 1.10
7 0.65 2.50 15 0.60 2.50
8 0.50 2.18 16 0.75 2.50

are considered as digital DOCRs. The CTI is assumed to be 0.2 s The PS and TMS selected by GA for different OFs are tabulated
for each P/B relay pair. in Table 4. By executing these relay settings, operating time of
The range of TMS is considered continuously from 0.1 to 1.1 relays and discrimination time of each relay pair are calculated. By
[1, 13]. The minimum and maximum bounds on PS are calculated implementing all OFs, the obtained total operating times of
as [1] primary relays and corresponding backup relays for both near and
far-end faults are given in Table 5. Also, the calculated
OLF × ILi discrimination time (Δt) of each P/B relay pair, for both near and
PSi, min = max , min tap setting (16)
CTi far-end faults, is presented in Table 6.
From the second column of Table 5, it can be seen that the OF1
2 × I f i, min gives minimum total operating time of primary relays for near-end
PSi, max = min , max tap setting (17) faults compared to OF2 and OF3, and almost similar to OF4. On
3 × CTi
the other hand, OF1 leads larger discrimination time between P/B
where OLF is the overload factor and it is considered as 1.25. ILi, relay pairs for both near and far-end faults as shown in third and
fourth column of Table 6. It is because the coordination constraints
Ifi,min and CTi represent the maximum load current, minimum fault are not directly incorporated in the OF formulation. With
current and CT ratio of relay Ri, respectively. The minimum and increasing the discrimination times, the total operating time of
maximum available tap settings of relays are considered in order of backup relays is also increased in OF1 especially for far-end fault
0.5 and 2.5. By using (16) and (17), calculated limits of PS for each which is shown in the fifth line of the second column of Table 5.
relay are presented in Table 3. To overcome the difficulty with OF1, the OF2 integrates the

2090 IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094
© The Institution of Engineering and Technology 2018
Table 4 Relay settings obtained by different OFs for IEEE 14-bus network
Relay no. OF1 OF2 OF3 OF4 OF5 POF
PS TMS PS TMS PS TMS PS TMS PS TMS PS TMS
1 1.329 0.508 1.733 0.456 0.703 0.749 2.184 0.436 2.035 0.360 2.500 0.349
2 1.996 0.281 1.858 0.303 0.894 0.474 1.159 0.367 1.300 0.326 2.500 0.204
3 2.428 0.292 1.277 0.420 0.796 0.569 1.971 0.318 0.849 0.444 0.500 0.484
4 1.817 0.299 0.979 0.406 0.572 0.606 1.336 0.357 1.101 0.328 1.869 0.257
5 1.912 0.413 1.040 0.518 1.417 0.539 1.010 0.497 1.847 0.383 1.722 0.339
6 2.069 0.425 1.148 0.520 0.864 0.697 1.851 0.448 1.547 0.393 0.533 0.586
7 1.267 0.519 1.027 0.577 0.716 0.735 0.677 0.638 1.599 0.493 2.500 0.345
8 1.673 0.320 0.547 0.467 0.552 0.599 0.587 0.479 0.501 0.421 0.500 0.425
9 1.173 0.480 1.275 0.424 0.927 0.630 1.230 0.455 0.943 0.471 2.500 0.291
10 1.357 0.347 1.099 0.400 0.885 0.499 1.962 0.288 0.877 0.434 2.500 0.204
11 1.712 0.439 1.637 0.460 0.660 0.707 1.981 0.428 0.622 0.600 2.500 0.317
12 2.204 0.408 1.854 0.423 1.023 0.651 0.810 0.590 2.428 0.339 2.500 0.336
13 1.801 0.410 1.137 0.517 0.588 0.716 1.873 0.398 2.183 0.386 2.497 0.337
14 0.570 0.520 0.500 0.591 0.519 0.727 0.755 0.524 0.500 0.458 0.500 0.481
15 0.827 0.544 1.554 0.461 0.620 0.704 1.323 0.454 1.195 0.506 2.500 0.291
16 1.400 0.447 1.537 0.387 0.758 0.673 1.854 0.391 0.935 0.451 2.500 0.290

Table 5 Total operating time of P/B relays for near and far-end faults for IEEE 14-bus network
Total operating time, s OF1 OF2 OF3 OF4 OF5 POF
∑tp,near 13.854 14.178 17.484 13.970 13.051 11.698
∑tb,near 17.810 17.878 21.374 17.836 16.410 15.286
∑tp,far 17.842 17.904 21.401 17.858 16.436 15.309
∑tb,far 34.095 28.231 32.548 30.662 25.587 25.078

Table 6 Discrimination time (s) between P/B relays for near and far-end faults for IEEE 14-bus network
PR BR OF1 OF2 OF3 OF4 OF5 POF
Δtnear Δtfar Δtnear Δtfar Δtnear Δtfar Δtnear Δtfar Δtnear Δtfar Δtnear Δtfar
1 4 0.001 0.991 0.013 0.488 0.000 0.411 0.001 0.643 0.000 0.446 0.000 0.854
1 6 0.001 1.594 0.000 0.886 0.000 0.938 0.000 1.377 −0.024 0.926 0.000 0.445
2 11 0.011 0.001 0.003 −0.006 0.012 0.002 0.000 0.057 0.028 0.000 0.000 0.007
3 2 0.227 0.400 0.150 0.344 0.128 0.181 0.213 0.261 0.078 0.182 0.000 0.303
3 6 0.344 — 0.201 — 0.312 — 0.341 — 0.056 — 0.144 —
4 14 0.001 1.993 0.000 2.042 0.000 2.713 0.012 3.249 −0.084 1.448 0.000 1.546
5 2 0.000 0.275 0.000 0.297 0.000 0.116 0.001 0.169 0.000 0.146 0.000 0.333
5 4 0.117 — 0.064 — 0.184 — 0.130 — 0.001 — 0.144 —
6 13 0.031 — 0.072 — 0.000 — 0.000 — 0.186 — 0.000 —
6 16 0.154 0.001 0.001 −0.109 0.149 0.000 0.121 0.000 0.121 0.000 0.000 0.000
7 10 0.000 0.293 0.001 0.262 0.001 0.260 0.001 0.440 0.000 0.205 0.000 0.457
8 12 0.000 0.015 0.000 0.045 0.000 0.023 0.000 0.013 0.000 0.057 0.000 0.059
9 8 0.001 4.567 0.001 0.914 0.000 1.198 0.000 1.017 −0.141 0.595 0.000 0.698
10 15 0.001 0.031 0.003 0.175 0.000 0.050 0.001 0.037 −0.001 0.141 0.000 0.133
11 7 0.001 0.042 0.017 0.050 0.001 0.051 0.004 0.001 0.000 0.100 0.000 0.075
12 1 0.001 0.033 0.016 0.097 0.000 0.035 0.001 0.166 −0.058 0.000 0.000 0.100
13 3 0.000 1.427 0.000 0.722 0.000 0.585 0.001 1.028 0.000 0.379 0.000 0.186
14 5 0.240 1.084 0.177 0.717 0.179 0.935 0.149 0.637 0.240 1.002 0.074 0.673
14 16 0.363 0.477 0.168 0.256 0.363 0.412 0.302 0.431 0.291 0.358 0.244 0.419
15 5 0.000 0.289 0.001 0.110 0.000 0.264 0.001 0.118 −0.115 0.088 0.000 0.135
15 13 0.000 0.231 0.062 0.173 0.036 0.130 0.032 0.244 0.000 0.261 0.170 0.445
16 9 0.001 0.173 0.002 0.173 0.000 0.209 0.000 0.146 0.000 0.158 0.000 0.302
∑ Δt (s) 1.495 13.92 0.956 7.635 1.365 8.511 1.311 10.03 0.576 6.492 0.775 7.169

coordination constraints in the OF formulation. As a result, the coordination is observed in the results of OF3 which can be seen
obtained total discrimination time in the OF2 is significantly from the seventh and eighth column of Table 6. Thus, the problem
minimised compared to OF1, OF3 and OF4. By reducing the of mis-coordination is completely solved by using the OF3, but the
discrimination time of P/B relay, the operating time of backup obtained total operating time of P/B relays is higher for both the
relays is also minimised specially for far-end fault which is shown near and far-end faults as shown in the fourth column of Table 5.
in the fifth line of the third column of Table 5. However, two mis- By using the OF4, the operating times of primary relay are
coordinations are observed in OF2 which are highlighted by bold minimised mainly for the near-end fault, as can be clearly seen in
digits in the sixth column of Table 6. In contrast, no mis- the first line of the fifth column of Table 5. Owing to the

IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094 2091
© The Institution of Engineering and Technology 2018
Table 7 Required iterations and time for convergence for
IEEE 14-bus network
OF Numbers of iteration CPU time, s
OF1 292 13.861
OF2 240 12.871
OF3 138 7.938
OF4 186 9.643
OF5 104 4.9669
POF 90 4.0267

Fig. 7  Convergence of GA-based different methods for IEEE 14-bus


network

From above discussion, it should be inferred that the pervious


OFs experienced the negative effects of either larger operating time
of relays or mis-coordination. On the other hand, as can be clearly
seen from Tables 5 and 6, the superior results are obtained using
the POF. The POF significantly minimises the operating time of the
P/B relays compared to OF1 to OF5, whereas the total
discrimination time is faintly larger than OF5 and lesser than OF1
to OF4. It is also noted that mis-coordinations remained in the
results of OF5, while POF gives best solution with no violation.
For both near and far-end faults, the average value of the
operating time of the primary relays, backup relays and
discrimination time obtained by all the OFs is illustrated in
Fig. 6  Average value of
Figs. 6a–c. As seen in Fig. 6a, the obtained average operating time
(a) Operating time of primary relays, (b) Operating time of backup relays, (c)
of primary relays for near and far-end faults is, respectively, 0.731
Discrimination time between P/B relays for IEEE 14-bus network
and 0.957 s in the case of POF, which is lesser than all other OFs.
Again, the average operating time of backup relays for near and
insensitivity to discrimination time (Δt) for positive Δt, OF4 leads
far-end faults is in order of 0.955 and 1.567 s in POF as shown in
larger discrimination time mainly for far-end fault as seen in the
Fig. 6b, which is also lesser than OF1 to OF5. On the other hand,
tenth column in Table 6. As discussed in Section 3, OF5 is
the average discrimination time between P/B relay pairs obtained
developed to reduce the larger operating time of relays along with
by POF is in order of 0.035 and 0.377 s for near and far-end faults
the reduction of discrimination time. The obtained total operating
respectively, which are higher than the OF5 and less as compared
time of P/B relays is minimum in case of OF5 compared to OF1 to
to OF1 to OF4. Although the discrimination time is lesser in case
OF4, whereas the total discrimination time is lesser as compared to
of OF5 compared to POF, the obtained solution by using POF is
all the remaining OFs. On the other hand, six cases of mis-
feasible.
coordination are observed in the results of the OF5 which are
The convergence performance of GA-based different methods
highlighted in eleventh column of Table 6. Although OF5 gets a
is illustrated in Table 7 and Fig. 7. As clearly seen from Table 7
success in overcoming the problem of larger operating time of
and Fig. 7, with improving the mathematical terms in the OFs, the
relays, the problem of mis-coordination still remained.
convergence performance of GA is also improved. The GA
The results of OF1 to OF5 are scrutinised as follows:
converges in 4.0267 s and 90 iterations in case of POF which is
less as compared to all other methods.
• OF1 and OF4 give the minimum operating time of primary
relays, whereas the obtained discrimination time and operating
time of the backup relays are larger. 5.2 IEEE 30-bus modified distribution network
• OF2 and OF5 significantly reduce the discrimination time The performance of all the OFs is further evaluated on IEEE 30-
between P/B relay pairs and operating time of backup relays, but bus distribution network as shown in Fig. 8. This network is fed
the problem of mis-coordination still remains. Therefore, the from three primary distribution transformers connected to buses
solution obtained by OF2 and OF5 can be considered infeasible. B1, B6 and B13 and three DGs connected to buses B3, B10 and
• In the OF3, the mis-coordination problem is totally overcome, B15. The system has a total of 38 DOCRs installed at each end of
but the total operating time of P/B relays is higher. the lines. The detail information about the system is given in [19,

2092 IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094
© The Institution of Engineering and Technology 2018
Fig. 8  Single-line diagram of IEEE 30-bus modified distribution network

Table 8 Total operating time of P/B relays for near and far-end faults for IEEE 30-bus network
Particular OF1 OF2 OF3 OF4 OF5 POF
∑tp,near, s 28.484 29.369 33.278 28.611 25.746 22.307
∑tb,near, s 36.771 37.246 41.632 37.568 32.660 29.789
∑tp,far, s 37.376 37.374 42.214 36.992 32.688 29.495
∑tb,far, s 65.207 59.518 65.701 64.689 51.963 51.548
∑Δtnear, s 7.221 4.958 6.206 7.322 3.062 3.104
∑Δtfar, s 28.812 20.795 22.945 27.907 16.359 19.572
violated cases 0 14 0 0 24 0
numbers of iteration 484 445 258 387 155 129
CPU time, s 62.553 58.457 34.615 44.700 26.197 18.323

21]. The weight factors corresponding to each OF, value of GA noted that the mis-coordination cases are observed in the results of
parameters, available range of tap settings and CTI are considered OF5, whereas POF gives the solution without any mis-coordination
same as the previous system. case. Furthermore, it can be seen from Table 8 that the GA requires
By implementing GA using different OFs, the obtained results 18.323 s and 129 iterations to converge at near optimum solution in
for IEEE 30-bus network are summarised in Table 8. As previously case of POF which is better than OF1 to OF5.
discussed, OF1 minimises the operating time of primary relays and
it is insensitive to Δt. As a result, the total operating time of 6 Conclusion
primary relays, especially for near-end faults obtained by using
OF1 is minimum compared to OF2 and OF3 and nearly to OF4. On In this paper, the new method based on GA has been proposed for
the other hand, a larger value of total discrimination times for near- the coordination of DOCRs. In the proposed method, a new OF has
end (Δtnear) and far-end faults (Δtfar) have been observed in the been developed which concurrently minimises the operating time
results of OF1. Since the coordination constraints are included in of primary relays and maximises the operating time of the backup
the formulation of the OF2, the minimum discrimination time and relays in case of mis-coordination. Similarly, it minimises the
hence minimum operating time of backup relays are obtained using operating time of the backup relays for larger positive value of the
the OF2 as seen in the third column of Table 8. However, total discrimination time. To demonstrate the effectiveness of the
numbers of 14 coordination constraints are violated as seen in the proposed method, it is tested on the IEEE 14-bus and IEEE 30-bus
eighth line of the third column of Table 8. On the other hand, no distribution networks, and obtained results have been compared
mis-coordination case is observed in the results of OF3 as seen in with earlier well-established OFs. The comparative analysis reveals
the fourth column of Table 8. However, the obtained total operating that the proposed OF significantly minimises the operating time of
times of relays for both near and far-end faults are increased. the P/B relays for both near and far-end faults, and also maintains
Further, the OF5 works same as OF1 for positive values of Δt. the discrimination time between P/B relay pairs at the prescribed
Hence, it tends to increase the discrimination time and also the level. Moreover, the GA converges to the best solution in lesser
operating time of backup relays as shown in the fifth column of numbers of iteration and lesser time in case of POF compared to
Table 8. On the other hand, the OF5 gives superior results previously proposed methods. As the POF considerably minimises
compared to OF1 to OF4 in terms of both operating times of relays operating time of the relays without involving any mis-
and discrimination times. However, a total number of 24 mis- coordination and with the improved convergence rate, it is verified
coordination cases are observed in the results of OF5 as shown in to be a more efficient and successful for optimum relay
the eighth line of sixth column of Table 8. It is also observed that coordination compared to earlier methods.
the violation in coordination constraints in the results of OF2 and
OF5 is increased with increasing the complexity of the system. On
the other hand, the POF significantly minimises the operating times
of P/B relays for both near and far-end faults as compared to OF1
to OF5. Also, the obtained total discrimination time is lesser than
OF1 to OF4, whereas it is slightly higher than the OF5. It is also

IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094 2093
© The Institution of Engineering and Technology 2018
7 References [11] Moravej, Z., Adelnia, F., Abbasi, F.: ‘Optimal coordination of directional
overcurrent relays using NSGA-II’, Electr. Power Syst. Res., 2015, 119, pp.
[1] Noghabi, A.S., Sadeh, J., Mashhadi, H.R.: ‘Considering different network 228–236
topologies in optimal overcurrent relay coordination using a hybrid GA’, [12] Mansour, M.M., Mekhamer, S.F., El-Kharbawe, N.-S.: ‘A modified particle
IEEE Trans. Power Deliv., 2009, 24, (4), pp. 1857–1863 swarm optimizer for the coordination of directional overcurrent relays’, IEEE
[2] Bedekar, P.P., Bhide, S.R.: ‘Optimum coordination of directional overcurrent Trans. Power Deliv., 2007, 22, (3), pp. 1400–1410
relays using the hybrid GA-NLP approach’, IEEE Trans. Power Deliv., 2011, [13] Amraee, T.: ‘Coordination of directional overcurrent relays using seeker
26, (1), pp. 109–119 algorithm’, IEEE Trans. Power Deliv., 2012, 27, (3), pp. 1415–1422
[3] Rajput, V.N., Pandya, K.S.: ‘Coordination of directional overcurrent relays in [14] Othman, A.M., Abdelaziz, A.Y.: ‘Enhanced backtracking search algorithm for
the interconnected power systems using effective tuning of harmony search optimal coordination of directional over-current relays including distributed
algorithm’, Sust. Comput., Inform. Syst., 2017, 15, pp. 1–15 generation’, Electr. Power Compon. Syst., 2016, 44, (3), pp. 278–290
[4] Urdaneta, A.J., Nadira, R., Perez Jimenez, L.: ‘Optimal coordination of [15] Kalage, A.A., Ghawghawe, N.D.: ‘Optimum coordination of directional
directional overcurrent relays in interconnected power systems’, IEEE Trans. overcurrent relays using modified adaptive teaching learning based
Power Deliv., 1988, 3, (3), pp. 903–911 optimization algorithm’, Intell. Ind. Syst., 2016, 2, (1), pp. 55–71
[5] Shih, M.Y., Salazar, C.A.C., Enríquez, A.C.: ‘Adaptive directional [16] Albasri, F.A., Alroomi, A.R., Talaq, J.H.: ‘Optimal coordination of directional
overcurrent relay coordination using ant colony optimisation’, IET Gener. overcurrent relays using biogeography-based optimization algorithms’, IEEE
Transm. Distrib., 2015, 9, (14), pp. 2040–2049 Trans. Power Deliv., 2015, 30, (4), pp. 1810–1820
[6] Birla, D., Maheshwari, R.P., Gupta, H.: ‘A new nonlinear directional [17] Srivastava, A., Tripathi, J.M., Mohanty, S.R., et al.: ‘Optimal over-current
overcurrent relay coordination technique, and banes and boons of near-end relay coordination with distributed generation using hybrid particle swarm
faults based approach’, IEEE Trans. Power Deliv., 2006, 21, (3), pp. 1176– optimization–gravitational search algorithm’, Electr. Power Compon. Syst.,
1182 2016, 44, (5), pp. 506–517
[7] So, C.W., Li, K.K., Lai, K.T., et al.: ‘Application of genetic algorithm for [18] Ravindranath, B., Chander, M.: ‘Power system protection and switchgear’
overcurrent relay coordination’. Developments in Power System Protection, (New Age International Press, New Delhi, India, 1977), pp. 57–58
Sixth Int. Conf. (Conf. Publ. No. 434), 1997 [19] Christie, R.: ‘Power systems test case archive’. Available at http://
[8] Razavi, F., Abyaneh, H.A., Al-Dabbagh, M., et al.: ‘A new comprehensive www.ee.washington.edu/research/pstca/
genetic algorithm method for optimal overcurrent relays coordination’, Electr. [20] Saleh, K.A., Zeineldin, H.H., Al-Hinai, A., et al.: ‘Optimal coordination of
Power Syst. Res., 2008, 78, (4), pp. 713–720 directional overcurrent relays using a new time-current-voltage
[9] Mohammadi, R., Abyaneh, H., Razavi, F., et al.: ‘Optimal relays coordination characteristic’, IEEE Trans. Power Deliv., 2015, 30, (2), pp. 537–544
efficient method in interconnected power systems’, J. Elect. Eng., 2010, 61, [21] Chabanloo, R., Abyaneh, H.A., Agheli, A., et al.: ‘Overcurrent relays
(2), pp. 75–83 coordination considering transient behaviour of fault current limiter and
[10] Adelnia, F., Moravej, Z., Farzinfar, M.: ‘A new formulation for coordination distributed generation in distribution power network’, IET Gener. Transm.
of directional overcurrent relays in interconnected networks’, Int. Trans. Distrib., 2011, 5, (9), pp. 903–911
Electr. Energy Syst., 2015, 25, (1), pp. 120–137

2094 IET Gener. Transm. Distrib., 2018, Vol. 12 Iss. 9, pp. 2086-2094
© The Institution of Engineering and Technology 2018

S-ar putea să vă placă și