Documente Academic
Documente Profesional
Documente Cultură
net/publication/299432953
CITATIONS READS
0 1,652
3 authors, including:
Some of the authors of this publication are also working on these related projects:
Experimental and Statistical Study on the Behavior of Bounded Foundation on Sandy Soil View project
All content following this page was uploaded by Mohammed Yousif Fattah on 27 March 2016.
management of a geotechnical site investigation is the key to and design a foundation for a building in permafrost is
obtaining sufficient and correct site information for designing a complex. It depends on (Holubec Consulting Inc, 2010):
structure in a timely manner and with minimum cost for the a) design criteria of the proposed structure;
effort needed. b) historic knowledge of general site conditions and building
In this paper, a case study of a multi-story building in Baghdad
performance;
city is analyzed. The building was originally designed to be
c) drilling equipment availability;
supported by a raft foundation. During construction, unexpected
d) time of year the work needs to be done may determine the
settlement was recorded before completion of the tenth floor. It
geotechnical site investigation method and finally;
was then decided to stop the work and make the required
calculations to check the adequacy of the raft foundation. e) the overall costs.
The calculations based on the soil investigation report showed Good planning for and management of a geotechnical site
that the allowable bearing capacity of the shallow foundation does investigation program is the key to obtain sufficient and
2
not exceed 50 kN/m which makes the raft unable to sustain the correct site information for designing a building foundation in
load imposed by eight stories. a timely manner and with minimum cost for the effort needed.
The decision was to increase the foundation load carrying
The effort and detail of the geotechnical site investigation
capacity by introducing a piled-raft system through construction
program in permafrost is complex.
of a number of bored piles 400 mm in diameter and 15.0 m long
beneath the raft distributed around the column locations at
spacing of 2.5 pile diameters. Preliminary Site Characterization (Description)
As a result, monitoring of the building settlement showed that It is important that before a field investigation program is
the settlement ceased after construction of piles. Finishing works developed a preliminary site characterization based on
were then continued and constructed safely. published literature and clients and consultants information be
prepared. The site characterization should include climate and
Index Terms— Bored pile, raft, support, settlement, collapse.
ground temperature at commissioning of the building and at
frozen ground. It can be an office (desk) study based on specifications of such soil do not ensure supporting a building
available information and may include a site visit. For larger of more than four stories without any treatment. In addition,
and settlement sensitive buildings, it is suggested that a site the design was decided to be a raft foundation at a depth of 4
visit be made during late summer when the ground thaw is at m below the N.G.L. and beneath the basement which was
its greatest, when surface drainage and groundwater can be surrounded by concrete walls.
observed and test pits can be excavated at the proposed The building is located at intersection of two
building site, and at potential construction borrow materials. secondary streets and it is of rectangular area (44.25 X 15) m.
Test pits during the deepest thaw depth, during August and The structure of the building was designed of concrete
September, allow a detailed examination of the first 3 m depth skeleton with cantilevers on both of the mentioned streets; one
that may consist of a stratigraphy of fill, organic and disturbed of about 2 m width along the short side and the other is of 3 m
soil layers respectively and the summer groundwater. This width along the long side as shown in Figure 1.
upper zone is frequently a critical zone in the design of the After completion of the skeleton for the ten floors and
foundation, its excavation and grading plan. execution of most of finishing works, signals of differential
Although the technical achievements in terms of the settlements appeared. Hence committee of execution
observations are the necessary ingredients for a new level of established observation of the building settlement by daily
applications, it is paramount that new models need to be surveying for many points and they recorded such differential
developed to link the observations to parameters describing settlement of about 120 mm at the corner were the two
the driving forces behind the deformations. With increasing cantilevers intersect (Point B).
precision levels, more subtle movements of the earth become Building Inspectors Association of Southeastern Wisconsin
detectable. Moreover, in many cases there will be more than (2003) stated that signs of collapse of a building are as
one mechanism responsible for the detected deformation. For follows: One or more walls are bowed or leaning, with signs of
this reason, geographic information systems become current or recent movement. Wall cracks may be greater than
indispensable to systematically combine all possible sources of 1/4" (6 mm) wide. The total amount of wall deflection is one
additional information that may contribute to the model inch (25 mm) or more from the original wall construction.
formulation (Ferretti et al., 2000). Water seepage may present at the floor line. Previously
The objective of this paper is to make a trial to support a repaired wall cracks show signs of continued cracking.
multi-story building by bored piles to prevent continuous Horizontal wall cracks are usually associated with bowing and
settlement and expected collapse due to unsuitable foundation may open and close with the seasons. Diagonal wall cracks or
design. displacement at vertical cracks are usually associated with
leaning walls or wall bowing adjacent to wall irregularities.
Vertical cracks are usually associated with shrinkage of
Street in Al Khademyah in Baghdad city capital of Iraq. It These guidelines were followed to inspect the building
consists of ten floors and one floor for basement. It was under consideration.
constructed on sandy clay soil of moderate bearing capacity, (Building Inspectors Association of Southeastern Wisconsin,
that the soil investigation report showed that the bearing 2003).
capacity will not exceed 5 ton/m2 at depth of 4 m below the Staff of consultants from the Scientific and Engineering
natural ground level (N.G.L.). This means that the Consultant Bureau of the University of Technology in
19
The 2nd International Conference of Buildings, Construction and Environmental Engineering (BCEE2-2015)
Baghdad advised the staff of construction to stop the works The practical proposed solution is to strengthen the existing
up to study this case and making evaluation for the structure raft foundation by constructing bored piles of small diameters
and finding the suitable solutions. under the raft foundation and bored piled of relatively large
diameters along the two sides parallel to the two intersected
Soil Investigation: streets described above. Then, the raft will be connected with
For the purpose of evaluation of the structural design for the pile cap by connecting the reinforcement of the existing
foundations and redesign, the soil investigation was repeated raft foundation with the reinforcement of the new pile cap.
through two boreholes of 20 m depth for both at the long side After long discussion with the constructer, there was an
of the building and the samples were tested in the laboratories agreement to support the raft foundation by bored piles of 400
of the University of Technology. mm diameter after making an opening in the raft with large
The investigation showed that the soil is medium to accuracy without damaging of the reinforcement.
dense clayey silty sand or clayey soil with sand. The standard This method means that the raft foundation will be converted
penetration test values were found to be (19 – 21) at the first to piled raft foundation to ensure such sharing of loads
six meters from the natural ground level and (22 – 23) down to between the piles and raft. The piled raft foundation will be
a depth of 12 m and (35 – 46) between (12 – 20) m. The level regarded as geotechnical structure which consists of three
of the ground water table was found at a depth of 1.5 m from elements, the piles, raft and soil. In design of the pile raft
the natural ground level. The report showed that the bearing foundation, the load will be shared between the piles and the
capacity at a depth of 4 m (beneath the raft foundation) is raft and the piles will be designed to carry loads which may
2
about (5 – 6) ton/ m . This ascertains that the constructed raft exceed the load supported by single pile or may be more. For
foundation is not able to support the building when it will be that reason, the raft foundation is combined with piles which
loaded by the dead and live loads. will decrease the settlement by economic way in comparison
with the principals of traditional foundation design methods.
Monitoring of Settlement:
The previous studied showed that the ratio of load which can
During this period, monitoring of the building settlement was
be carried by pile group may be 28 to 79% of the total load
continuous and the settlement at Points A, B, C and D located
and this ratio will be increased with increasing of numbers of
at the building corners were recorded (see Figure 1). Figure 2
piles (Fattah et al., 2013, 2015).
traces the recorded settlement at these points.
Redesign of foundation:
At the site visit and observing of different concrete elements, it
was found that the skeleton is not defected and all the concrete
works were constructed per high specifications and there is no
any traces of cracks and no any water seepage inside the
basement and no any inclination of any of the structural
members. The compressive strength for the concrete seems to
be of about 30 MPa. These reasons indicate that the treatment
will be directed to support the skeleton instead of releasing
parts of the loading by release of some of the upper floors
from the building.
20
The 2nd International Conference of Buildings, Construction and Environmental Engineering (BCEE2-2015)
From the field tests like standard penetration test and cone term is used to calculate the friction capacity. As the pile is
penetration test or others. supported by sandy soil; then the end bearing can be calculated
Laboratories tests: from the first term of the equation. Then, the skin friction
The capacity of the pile to support the static load can be capacity cannot be calculated because the pile penetrates clay
calculated through the following equation (Tomlinson and layers. The skin friction capacity in clayey soil can then be
Woodward, 2008): calculated using the method according the following
------------- (2)
a. Meyerhof Method:
where:
The end bearing capacity can be calculated using the
f : non-dimensional factor for the relationship between
following equation:
the length of pile and its diameter,
Qb = 0.8 N x L/B 8N ------------- (5)
Nq: factor of pile capacity,
Qb will be in Ksf units. Qb
Ab: cross sectional area of the pile,
Meyerhof suggested also the following equations for
L' : the stress at the bottom of the pile,
calculating the end capacity of piles using the magnitudes of
K: factor of lateral soil pressure at depth z,
standard penetration test (N) for driven piles:
Cf : correction factor for k value when ,
Qb = 0.45 N x L/B (tsf) (for coarse sand) ------ (6)
': effective angle of internal friction for soil,
Qb = 0.4 N x L/B (tsf) (for medium sand) ------ (7)
: the angle of friction between the soil and the pile,
Qb = 0.33 N x L/B (tsf) (for fine sand) ----- (8)
: angle of inclination of the pile with the vertical,
For the purpose of determination of the skin friction; Meyerhof
z': effective overburden pressure acting at the centre of the
suggested the following equation:
pile length increment, L ، 0 z L, and Qs = N/50 (tsf) ------------- (9)
Cz: the perimeter of the pile at depth z. where:
Qs : the skin friction at ton / square foot, and
It can be observed that the first term of the equation 2 is
used to calculate the end bearing of the pile; and the second
22
The 2nd International Conference of Buildings, Construction and Environmental Engineering (BCEE2-2015)
N: the ratio number of standard penetration test at all length of The last mentioned load must be carried by internal 400
pile. mm diameter piles and they are distributed according to the
drawings (Figure 1) as follows:
b. Martin et al. (1987): 10 internal piles (tension and compression piles) are
The end bearing of pile can be determined by using the needed along the long side of the building (the internal length
following equation: opposite to the long side on the street).
q = C . N (MN/m2) ------------- (10) 4 internal piles (tension and compression piles) are needed
C = 0.45 (for pure sand) along the short side of the building (the internal short side on
C = 0.35 (for silty sand) the street).
3 piles x 4 bays = 12 piles will needed to surround each of the
capacity for the piles was calculated as follows: The number of internal columns is ten;
1. For piles of 400 mm diameter; the load will be 30 tones. Then, 10 columns x 12 piles = 120 piles for surrounding the
stage of time. In the same time, one can demolish the raft
foundation in far corners related to other column to be
ready for casting and to execute piles away from that
which had been just executed.
4. These procedures will ensure not to demolish a large area
of the raft foundation in one bay to prevent any structural
defect.
5. The last stage is to execute the external piles which are of
800 mm diameter at an spacing of 1.6 m (centre to centre).
To prevent any failure of soil at construction time; it must
be constructed by the sequence of constructing piles 1, 4,
7, 10 etc. and then 2, 5, 8 and the residual.
6. The construction of the external piles can be established
after a reasonable time (one month) after execution of 1 to
14 piles and finishing the the raft foundation casting.
Figures 3 to 7 illustrate the stages of construction of bored
piles.
a.
60
Start of Point A
End of Pile
Remediation Construction Point B
80
Point C
Settlement, mm
Point D
100
120
140
160
180
1/5/2014
1/4/2014
b.
Conclusions:
1. The remediation work of the building which includes
cantilevers from two sides started with construction of the
internal piles in the beginning of the work. These piles
worked as tension piles to prevent the overturning of the
building outward when the external piles were constructed.
2. The construction of the internal piles (surrounding
columns) required demolishing an exacted area of the
existing raft foundation for an area enough for execution
three piles oriented in one corner of one column. The piles
in the same bay waited to another stage of time. In the
same time, the raft foundation in far corners related to
other column was demolished to be ready for casting and to
execute piles away from that which had been just
executed. These procedures ensured not to demolish a
large area of the raft foundation in one bay to prevent any
a. structural defect.
3. Good planning and management of a geotechnical site
investigation program is the key to obtain sufficient and
correct site information for designing a building foundation
in a timely manner and with minimum cost and effort.
REFERENCES
1. Fattah, A. Y., Yousif, M. A., Al-Tameemi, S. M., (2013),
“Bearing Capacity of Pile Group and Piled Raft
Foundations on Sandy Soil”, Journal of Engineering and
Development, University of Al-Mustansiriya, Vol. 17,
No.2, pp. 64-96.
2. Fattah, A. Y., Yousif, M. A., Al-Tameemi, S. M., (2013),
" Effect of Pile Group Geometry on Bearing Capacity of
Piled Raft Foundations", Structural Engineering and
Mechanics, Vol. 54, No. 5, Techno-Press Ltd., Korea,
DOI: http://dx.doi.org/10.12989/sem.
3. Ferretti A., Ferrucci F. Prati C., Rocca F., (2002), "SAR
b. Analysis of Building Collapse by Means of the
Fig. 7: Bonding of pile and raft reinforcement. Permanent Scatterers Technique" - Proceedings of the
International Geoscience and Remote Sensing
Symposium (IGARSS 2000).
26
The 2nd International Conference of Buildings, Construction and Environmental Engineering (BCEE2-2015)