PAGE (Página) 1 OF 7
DATE (FECHA): 9/30/2015 JOB (OT): 687-1
EQUIPMENT: SEPARADOR TRIFASICO DE PRUEBA SEP 1 DRAWINGS: REV: 0
(EQUIPO) (PLANOS) REV:
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)
PAGE (Página) 2 OF 7
DATE (FECHA): 9/30/2015 JOB (OT): 687-1
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)
PAGE (Página) 3 OF 7
DATE (FECHA): 9/30/2015 JOB (OT): 687-1
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)
PAGE (Página) 4 OF 7
DATE (FECHA): 9/30/2015 JOB (OT): 687-1
Bevel Prepair Examination Fit up & Tack welds VE NDE ✘ RT FULL RT SPOT
Inspect. Inspect. Report
JOINT
I.P. QC
I.P. QC
I.P. QC
I.P. AI
I.P. AI
I.P. AI
Examination Inspection Inspection Examination Inspection Inspection Examination
Results Results Results Results Results Results Results
Results Results No.
L1 H H H
L2 H H H
C1
cuerpo a H H H
cabeza
C2
cuerpo a H H H
cuerpo
C3
cuerpo a H H H
cabeza
STEP DESCRIPTION
1 VE BORDES PARA SOLDAR S/UG-93 (d)(1), UG-95
2 GRADOS DE LOS BISELES S/PLANO & TOLERANCIAS
3 LUZ DE PENETRACION S/PLANO & TOLERANCIAS
4 CHEQUEAR ALINEAMIENTO S/UW-33
5 VE PUNTOS DE ARMADO S/UW-31( c )
6 CHEQUEO DE LIMPIEZA ZONAS A SOLDAR UW-32(a)
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)
PAGE (Página) 5 OF 7
DATE (FECHA): 9/30/2015 JOB (OT): 687-1
EQUIPMENT: SEPARADOR TRIFASICO DE PRUEBA SEP 1 DRAWINGS: REV: 0
(EQUIPO) (PLANOS) REV:
I.P. QC
I.P. QC
I.P. AI
I.P. AI
I.P. AI
Examination Inspection Inspection Examination Inspection Inspection
Results Results Results Results Results Results
Results Results Results No.
A H H
B H
C H
D H H
F H H
G1 - G2 H
H1 - H2 H
I1 - I2 H
J1 - J2 H
K1 - K2 H
L H
M H
M1 H H
N H
O H
P H
Q H
R H
S H
T H
U H
V H
W H
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)