Measurement Period: Four weeks (20 workdays, 8 hours per day)

A. Total Payroll hours for Technician for the period 160


B. Monthly allotment of Non-Productive hours per Technician:

Total hours for Breaks 10


Total hours for Clean Up 5
Total hours for Safety / Union Meetings 1
Total: Expected Productive Hours (A – B) 134
C. Total Productive Hours for Technician for the period: 100

Technician Productivity for the period: (C divided by total of B) 75%

Technician Productivity standards vary greatly throughout the Fleet Industry. Generally
accepted ranges may fall between 70% - 80% when labor hour charges are based on actual
time spent on repair operations. Standards may be in the 80% - 90% range when labor
standards are used exclusively in determining labor hour charges.