Documente Academic
Documente Profesional
Documente Cultură
Chapter
Chapter V Contents Home
III
CHAPTER-IV
PROCEDURE FOR ARRANGING POWER SUPPLY ON TEMPORARY BASIS
18. General:-
Any person desirous of availing temporary power supply shall comply with
the requirements of this chapter.
Temporary supply for one day to public meetings and government functions
with a connected load of 2 KW or less will be extended on payment of a fixed
charge of Rs.50/- per service or as applicable as per tariff in force.
20. Procedure Applicable To Low Tension Power Supply Of Not More Than
10 KW And Not More Than 15 Days, Without Extension Of The
Distributing Main :-
(1) The prospective consumer shall apply for temporary supply in the
prescribed form to the O&M sub-division office. He shall pay fixed charges
towards service and consumption charges as noted below :-
(2) The consumer shall get all the wiring works including service line work
done through the contractor, at his cost. However, the service line work shall
be commenced only after orders sanctioning the temporary supply are issued
by the department.
(5) The date of availing the temporary supply may be got amended by the
consumer, by applying to the authority who has issued the orders before the
commencement date indicated in the order. However, any alternate date
proposed shall commence within 15 days of the date of the first order.
(6) In case, the temporary supply is not availed as above, the charges paid
will be forfeited.
(1) The prospective consumer shall apply in the prescribed form to the
jurisdictional O&M sub-division office. Power will be sanctioned, if technically
feasible, by the competent authority. The consumer shall pay service
charges.
(4) The extension of the distributing main is normally carried out by the
department. However, the consumer may get this work done through a
contractor as per the rules and specifications.
(6) Any change in the dates of availment shall be got approved by the
consumer, by applying to the Officer who has issued the order, before the
commencement date indicated in the order. Any alternate dates shall
commence within one month from the date of orders.
(9) For further extension of the period of temporary supply, the consumer
shall apply to the jurisdictional Assistant Executive Engineer/Assistant
http://electricity.puducherry.gov.in/acts/terms/chap04.htm 2/3
10/3/2018 Terms and Conditions of Supply of Electricity - Chapter IV
(1) Use of power within consumer’s premises for Temporary purposes for
bonafide domestic use is permitted subject to the condition that the total
load of the installation of the system does not exceed the sanctioned load.
However, this is subject to change from time to time as may be prescribed in
the tariff.
(2) Where it is intended to use floor polishing equipment and such other
portable equipment temporarily in a premises having permanent supply, and
such other portable equipment shall be provided with an earth leakage circuit
breaker of adequate capacity.
The provisions under clause 21 are generally applicable for temporary high
tension supply also. However, the estimated consumption charges shall be
payable in advance as detailed below :-
Note : The energy entitlement shall be as may be fixed from time to time.
(1) The other provisions under permanent supply shall also be applicable to
temporary supply, whether Low Tension or High Tension, so far as they are
applicable.
(2) Temporary supply shall be extended only for construction and testing
purposes and not for running an Industry.
http://electricity.puducherry.gov.in/acts/terms/chap04.htm 3/3