Logistics Management

Eslsca MBA Program

Assignment no. 1

Submitted to: Prof. Sayed El Khouly

Submitted by: Ahmed Moselhi

Class 55i

Date: 04 Sept., 2018


Assignment no. 1 - Logistics Management

Problem 1

Answer:

Quarter (x) Units (y) (X*Y) X2 y/ SI (y-y/)


1.00 5.00 5.00 1.00 4.17 1.20 0.83
2.00 4.00 8.00 4.00 4.33 0.92 0.33
3.00 3.00 9.00 9.00 4.50 0.67 1.50
4.00 5.00 20.00 16.00 4.67 1.07 0.33
5.00 6.00 30.00 25.00 4.83 1.24 1.17
6.00 5.00 30.00 36.00 5.00 1.00 0.00
7.00 4.00 28.00 49.00 5.17 0.77 1.17
8.00 6.00 48.00 64.00 5.33 1.12 0.67
Sum 36.00 38.00 178.00 204.00 10.00 6.00
9.00 5.50
10.00 5.67

Y= a+bX
b= 0.167
a= 4
n= 8
Linear regression equation is: Y = 4 + 0.167 X
MAD = 0.750

1|Page
Assignment no. 1 - Logistics Management

Problem 2

Answer:

Regular Total
Month Forecast
capacity
Overtime Subc. Holding
Prd.
Cost

March 50 40 8 2 50 $4,440
April 44 40 4 44 $3,680
May 55 40 8 7 55 $5,140
June 60 40 8 12 60 $5,840
July 50 40 8 2 50 $4,440
August 40 40 3 43 $3,560
September 51 40 8 3 48 $4,190
Total 350 280 47 350 $31,290

2|Page
Assignment no. 1 - Logistics Management

Problem 3

Answer:
Q1 Q2 Q3 Dummy Capacity
Demand
Initial 50 (0) (4) (8) (0) 50
Inventory
1 RP 400 (30) 100 (34) (38) (0) 500
OT (65) (69) (73) 150 (0) 150
SC (100) (104) (108) 100 (0) 100
2 RP 400 (30) (34) (0) 400
OT 50 (65) 50 (69) 50 (0) 150
SC (100) (104) 100 (0) 100
3 RP 600 (30) (0) 600
OT 100 (65) (0) 100
SC (100) 200 (0) 200
Demand 450 550 750 600 2350 2350

Cost of this plan=400*30+100*34+400*30+50*65+50*69+600*30+100*65 = $58,600

3|Page
Assignment no. 1 - Logistics Management

Problem 4

Answer:

UNITS
SEASON (X) (Y) (X*Y) (X²) (Y') |Y-Y'| SI
WINTER 1 140 140 1 149.74 9.74 0.93
SPRING 2 150 300 4 148.50 1.50 1.01
2016
SUMMER 3 200 600 9 147.26 52.74 1.36
FALL 4 100 400 16 146.02 46.02 0.68
WINTER 5 120 600 25 144.78 24.78 0.83
SPRING 6 140 840 36 143.54 3.54 0.98
2017
SUMMER 7 210 1470 49 142.30 67.70 1.48
FALL 8 105 840 64 141.05 36.05 0.74
WINTER 9 100 900 81 139.81 39.81 0.72
SPRING 10 160 1600 100 138.57 21.43 1.15
2018
SUMMER 11 200 2200 121 137.33 62.67 1.46
FALL 12 90 1080 144 136.09 46.09 0.66
SUM 78 1715 10970 650 412.07 12.00
b= -1.24 -- a= 150.98 -- n= 12
Linear regression equation is: Y= 150.98 - 1.24X MAD = 34.34
SEASON (X) UNITS (Y') AF
WINTER 13 134.85 111.43
SPRING 14 133.61 139.85
2019
SUMMER 15 132.37 189.29
FALL 16 131.12 91.37

4|Page
Assignment no. 1 - Logistics Management

Problem 5

Answer:

5|Page