General Notes
A A

1. All dimensions are in (mm) millimeters.

2. This drawing is a guide drawing for design of building structure, walls, doors, floor finishes and foundation pad also Required beams and intermediate columns are to be added by detail designer.
B B
3. Civil / Architecture layout drawing should be submitted to OES to check dimension & placement of equipment accordingly to OES layout drawing.

4. Wet weight of the genset is 38.1 ton with +3% dynamic load w.r.to the static load ( reference: GEJ technical instruction 1000-0041). The depth of the foundation pad should be designed as per this weight. (For GEJ Installations only).

5. Length, Width and height of the foundation pad are 10000 mm x 2400 mm x 100 mm.

6. Genset foundation pad should be flattened as per GEJ recommendation (reference: GEJ technical instruction 1000-0041).
C C
7. Height of all the panels is 2000 mm and base is 200 mm.

8. Dimension of all electrical panels should be check by customer before startup of civil work for control room.

9. It is recommended that all auxiliary cables should be laid in G.I tray instead of PVC.

10. Stair for ventilation room and power house roof will be required, Dimension will be as per site.
D D
11. Pit - 2 (Power cable Pit) dimensions are L=1500mm W=500mm D=800mm & Pit - 1 (control cable Pit) dimensions are L=1000mm W=800mm D=800mm.

12. Cooling tower capacity 700 USRT (US refrigeration ton) of each JMS 620 for combined (HT+LT Circuits) flow and wet weight of 10.8 ton (Approx) (wet weight of cooling tower,common header and individual pipings).

13. Dimensions of cooling tower are to be verified by supplier.

14. The exhaust pipe is of DN 600 mm.


E E
15. The exhaust pipe should be thermally lagged with rock wool of 50 mm thickness with almunium/galvanized iron cladding with in the engine room.

16. Ventilation room for air intake design at area 225 to 228 sq.ft for each engine.

17. We recommended one door in air intake filter room for cleaning purpose.

18. Over head tank should be above the height of cooling tower sump.
F F
19. Underground tank is required for filling of overhead tank.

20. Capacity of intake fan is 90,000 CFM ( 2 X 45,000 CFM ) and Exhaust fan is 54,000 CFM ( 49,000 CFM and 5,000 CFM) for each engine.

21. Panels abbreviations are as follows:- PRELIMINARY DRAWING


L Incoming / switch gear.
G AB Load take off./Outgoing G

MCC Motor control center. 0 18-12-2017


RevNo Revision note Date Sig. Chec.
A Module control panel.
Sheet 1/4 Rating Sheet Size A3
Trafo Auxiliaries Transformer Panel DATE SCALE
BB Battery Bank DESIGNED_BY CHECKED_BY APPROVED_BY
Zahid Fareed Mudassir Pirzada Zeeshan Ahmed / Muhammad Ali 18-12-2017
BC Battery Charger Panel
TITLE NOTES

H H
CLIENT Standard Drawing- 1 X JMS 620
DRAWING-NO

Orient Energy Systems (Pvt.)Ltd. STD/620/01

1 2 3 4 5 6 7 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A A

Stair for ventilation room and roof of


power house.
(Dimension will be required as per site)

UP
B B

UP
600
Auxiliary

UP
Transformer Pipes Class E ( Typ)
600 1000 800
10000.0mm 5000.0mm
1500 3000.0mm
[33.1ft.] [16.6ft.]
4000

C [9.9ft.] C
Lubeoil
PIT-1 Tank

800

Glazed Window

Class E (Typ)
UPVC Pipes
600 800 800 800
600

2400.0mm
[8.0ft.]

8000
L
C

700

D D
900

Outgoing
Panel (1)
4000

PIT-2
900

Incomming
Standby
Panel (2) P1 P2
ENGINE HALL

2000
Trafo
900

E Panel E
DN
600

600 2200 3200 Main Sliding Door

3600 x 4200.0 2400


6000 18000
24150

F F

PRELIMINARY DRAWING
G G
0 18-12-2017
RevNo Revision note Date Sig. Chec.

Notes:- Sheet 2/4 Rating Sheet Size A3


DATE SCALE
1. DESIGNED_BY CHECKED_BY APPROVED_BY
2. Auxiliaries equipment (BOP) final location / placement as per site. Zahid Fareed Mudassir Pirzada Zeeshan Ahmed / Muhammad Ali 18-12-2017 1:80

3. Nozzle size and orientation as per site.


TITLE
4. Insulation as per site.
H 5. Please see sheet 1/4 for detailed notes. CLIENT Standard Drawing- 1 X JMS 620 H
6. Ms structural stair / Step platform (Detachable type) to access control room. DRAWING-NO
7.
Orient Energy Systems (Pvt.)Ltd. STD/620/01

1 2 3 4 5 6 7 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A A

700 USRT Cooling Tower


(For each Engine)

B See Note 05 B

See Note 06
Silencer

See Note 03
See Note 09

3000 3000

1000 kg Crane
C C
Ventilation Room

225 to 228 sq. ft Intake Fans Exhaust Fan


3650
3270
02 x 45,000 CFM 49,000 CFM

Air filter 600

150
Louvered panel 60
(Customer Scope) 0 LEV : +4600
1200
LEV : +4200
Exhaust Fan
D 5,000 CFM D

10
00

6500
Column See Note 03

Glazed Window
CONTROL ROOM 1400
Lubeoil

3400
Tank
900

LEV : +1050

1500
100
E E
900

CABLE ROOM
1200

LEV : -1200

3000 10000 5000


6000 18000
24150
F F

SECTION A - A

Notes:-
1. Supplier will confirm/makesure rated supply of air to the engine as per OES recommendation, 50% at alternator and 50% rest of engine. PRELIMINARY DRAWING
G 2. G
3. Opening size of the fan / frame should be verified by fan manufacture / supplier drawing. 0 18-12-2017
4. Auxiliaries equipment (BOP) final location / placement as per site. RevNo Revision note Date Sig. Chec.

5. Cooling tower to be placed on roof / ground as per structure / site requirement. Sheet 3/4 Rating Sheet Size A3
DATE SCALE
6. Minimum clearance 800 mm from floor and please discuss with cooling tower supplier / manufacturer for foundation pad design and drawing. DESIGNED_BY CHECKED_BY APPROVED_BY
18-12-2017 1:100
7. Engine foundation to be designed by civil consultant with respect to soil bearing capacity. Zahid Fareed Mudassir Pirzada Zeeshan Ahmed / Muhammad Ali

8. Silencer support and further detail will be confirmed be designer. SECTIONAL DRAWING
TITLE
9. louvers should be on any wall to avoid over pressure and hot air accumulation.
H H
10. Nozzle size and orientation as per site. CLIENT Standard Drawing- 1 X JMS 620
11. Insulation as per site. DRAWING-NO
12. Please see sheet 1/4 for detailed notes.
Orient Energy Systems (Pvt.)Ltd. STD/620/01

1 2 3 4 5 6 7 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A A

50.0

100.0
2400
50.0 50.0

100.0

100.0
B B
100.0
Round steel bar 10mm
Depth of foundation depends
dia. welded in place
on soil quality / Bearing
capacity civil consultant work.

ZOOM DETAIL ZOOM DETAIL


SCALE 1 : 5
SECTION B -B SCALE 1 : 5

C
Depth of foundation depends
SCALE 1:30

10000
C

50
50

D D
ALTERNATOR

ENGINE

2400
E E

Round steel bar 10mm


dia. welded in place

F 1000 1000 F

FOUNDATION PAD PRELIMINARY DRAWING


FLATNESS DETAIL
G SCALE 1:30 G
0 ISSUE FOR APPROVAL 18-12-2017
RevNo Revision note Date Sig. Chec.

Sheet 4/4 Rating Sheet Size A3


DATE SCALE
DESIGNED_BY CHECKED_BY APPROVED_BY
Zahid Fareed Mudassir Pirzada Zeeshan Ahmed / Muhammad Ali 18-12-2017

Notes:- FOUNDATION PAD FLATNESS DETAIL FOR FOR JMS 620


TITLE
1.
H 2. Nozzle size and orientation as per site. H
CLIENT Standard Drawing- 1 X JMS 620
3. Insulation as per site. DRAWING-NO
4. Please see sheet 1/4 for detailed notes.
Orient Energy Systems (Pvt.)Ltd. STD/620/01

1 2 3 4 5 6 7 10 11 12 13 14 15 16

S-ar putea să vă placă și