Documente Academic
Documente Profesional
Documente Cultură
Cabrera. The Finishing Department of Focus, Inc. uses a standard cost system and a Agamata. In analyzing the factory overhead variances, the following relevant data
flexible budget. were taken from the original information:
Normal capacity 135,000 units or 405,000 hours
Denominator activities are as follows: Standard hours 390,000 hours
Machine hours 140 Actual hours 380,000 hours
Finished pieces produced 2,800 Standard overhead rates:
Fixed P3.00 per hour
The standard costs in connection with this production are: Variable 2.00 per hour
Direct materials at P1.20 P3,360 Total P5.00 per hour
Direct labor at P0.1125b 315 Actual:
Factory overhead* 1,400 Variable P800,000
Total P5,075 Fixed 1,250,000
*Includes an allowance for variable overhead at a rate of P0.30 per piece.
Analyze the factory overhead variances using the:
The actual production for the month was: 1. Two-way analysis
Machine hours 130 2. Three-way analysis
Finished pieces produced 2,860 3. Four-way analysis
4. Five-way analysis
The actual cost for this production was:
Direct materials P3,575 Problem 3
Direct labor 286 Cabrera. The following events took place at Construct Co., during the month of
Factory overhead* 1,573 September 2018:
Total P5,434
*Includes P573 of fixed overhead. 1. Produces and sold 50,000 units at a sales price of P10 each. The budgeted
sales were 45,000 units at P10.15 each.
Required:
1. Determine the standard cost per finished product. 2. Standard variable cost per units is as follows:
2. Compute the materials variances. Direct materials (2 lbs. at P1.00) P2.00
3. Compute the direct labor variance. Direct labor (0.10 hours at P15) 1.50
4. Analyze factory overhead variance using: Variable manufacturing overhead (0.10 hours at P5) 0.05
a. Two-variance method. Total cost per unit P4.00
b. Three-variance method.
c. Four-variance method. 3. Fixed manufacturing overhead cost per month is P80,000.
Output 1,000 lbs. P300 Compute the material mix and yield variances.