: CC-MAS
Cold Commissioning Procedure Rev. No. : 00
Page : 1 Of 5
Page : 2 Of 5
System Description:
Centrifugal blower or fan that provides combustion air to the main burners of the reformer and
as a back up supply for auxiliary burners.
Start-up Conditions:
• Confirm machinery cooling water flow to bearings > FAL M53.1 and .2.
(FAL M53.1 and .2 = 1.0 m3/h)
Page : 3 Of 5
Field checks:
Open all hand valves on the combustion air lines to the heat recovery system.
Pre-start conditions:
• Put Main Air flow controller FC-B07 in MANUAL and dial output to 0%. (E9-31) (FV-B07
CLOSED signal is indicated)
System Start-up:
• Put software selector for Main Air Blower to READY/RUN. (READY signal is indicated)
• Start Main Air Blower by putting software selector to START. (RUN signal is indicated)
• Input Main Air Blower discharge pressure set-point using controller PC-B02 in AUTO
(PC-B02 set-point = 0.18 barg).
• After testing the main blower through vent line, divert the main air flow from vent line to
dilution air line by opening dilution air block valve SOV-C05-1. (ZSO-C05-1 open signal is
indicated). (Note: Auxiliary air back up valve SOV-C05 2 should be closed)
• Gradually open the temperature control valve of flue gas TV-C02 1 in manual mode and
close vent valve PV-B02 2.
Doc. No.: CC-MAS
Cold Commissioning Procedure Rev. No. : 00
Page : 4 Of 5
• Gradually open main air flow control valve FV-B07 and close temperature control valve
of flue gas TV-C02 1 and record the main air flow. (Note: Main burners natural gas should be
closed.)
• Gradually open temperature control valve TV-B36 1 (cold combustion air pre heater
bank-1 by pass line) and close manual hand valve BF-04 on cold combustion air pre heater
bank-1 &2.
• Gradually open hand valve HV-B15.2 on main air back up line to auxiliary air main
(Auxiliary air hand valve HV-B15.1 & auxiliary air to after burner hand valve BF-04 should be
closed) and close temperature control valve TV-B36 1 (cold combustion air pre heater bank-1
by pass line). Now open reformer temperature control valve TV-B22 to test main air flow through
auxiliary burners. (Note: Auxiliary burners natural gas should be closed)
Shutdown Interlocks:
Main Air Blower will shut down if Emergency Stop is pushed or:
• Fan Bearing Vibration > VSHH-B01.1 or .2. (VSHH-B01=7mm/sec “Main Air Blower High
Vibration Shutdown” will annunciate)
• Fan Bearing Vibration > VSHH-B01.3 or .4. (VSHH-B01=7mm/sec. “Main Air Blower
High Vibration Shutdown” will annunciate)
• Fan Bearing Temperature > TSHH-B64.1 or .2. (TSHH-B64=900C “Main Air Blower
Bearing High Temperature Shutdown” will annunciate)
• Ejector Stack Fan CP-C11 shuts down. (“Main Air Blower Shutdown” will annunciate)
• Electrical fault. (“Main Air Blower Shutdown” will annunciate)
To transfer dilution air supply to Aux Air Blower and shut down Main Air Blower:
• Decrease the set-point for main air blower discharge pressure PC-B02 to bring it closer
to the auxiliary air blower discharge pressure per PC-B09.
• Put software selector for DILUTION AIR SUPPLY to AUX. AIR when controller PC-B02
stabilizes. (ZS-C05.1B CLOSED signal is indicated, ZS-C05.2A OPEN signal is indicated)
Doc. No.: CC-MAS
Cold Commissioning Procedure Rev. No. : 00
Page : 5 Of 5
• Put Main Air flow controller FC-B07 in MANUAL and dial output to 0%.
(“Closed” signal is indicated)
• Put Main Air Blower discharge pressure controller PCB02 in MANUAL and dial output to
0%. (Inlet guide vane PV-B02.1 will close and CLOSED signal is indicated, Main Air Blower vent
valve PV-B02.2 will open and OPEN signal is indicated)
• Stop Main Air blower by putting software selector to position “0”
(“Main Air Blower Shutdown” will annunciate)